Rain days in Kennedale, Texas
Kennedale averages 58 rain days a year, counting days with at least 0.10 in of precipitation in the PRISM 4 km grid cell that contains it (1991-2020 normals). May is the wettest month at 7.2 rain days and July the driest at 3.7. That is close to the Texas median of 56.
Quick answers
How many rain days does Kennedale get a year?
About 58: that many days in a normal year bring 0.10 in or more of rain or melted snow. That makes Kennedale the 364th wettest of 784 Texas cities and towns.
What is the wettest month in Kennedale?
May, with 7.2 rain days in a normal year. To cover 9 years in 10, plan for 11.
What is the driest month?
July, with 3.7 rain days (plan for 8).
How many heavy-rain days does Kennedale get?
23 a year with 0.50 in or more, most often in May (2.9).
Why these counts are lower than some weather sites': a rain day here means 0.10 in or more. Counts based on 0.01 in (NOAA's "days with precipitation") or 0.04 in (WeatherSpark) also include drizzle and trace days.
Rain days by month
The wettest three months are April-June, with 17.6 rain days combined; the driest are July-September, with 12.0. June swings the most from year to year: it averages 5.5 rain days, but covering 9 years in 10 takes 11. The most rain days in a single month since 1981 was 19, in May 2015.
| Month | Normal rain days | Plan for 9 of 10 yrs |
Heavy days ≥ 0.50 in |
Precip (in) | Record (year) |
|---|---|---|---|---|---|
| January | 4.1 | 7 | 1.4 | 2.37 | 8 (1992) |
| February | 4.4 | 8 | 1.8 | 2.61 | 10 (2018) |
| March | 5.1 | 9 | 2.3 | 3.34 | 11 (2020) |
| April | 4.9 | 7 | 2.2 | 3.14 | 11 (2026) |
| May | 7.2 | 11 | 2.9 | 4.43 | 19 (2015) |
| June | 5.5 | 11 | 2.1 | 3.37 | 12 (1992) |
| July | 3.7 | 8 | 1.3 | 2.02 | 10 (2007) |
| August | 3.8 | 7 | 1.4 | 2.18 | 10 (2017) |
| September | 4.5 | 9 | 1.4 | 3.07 | 13 (2018) |
| October | 5.3 | 9 | 2.7 | 4.47 | 13 (2009) |
| November | 4.6 | 8 | 1.7 | 2.74 | 11 (2004) |
| December | 4.3 | 6 | 1.9 | 2.78 | 12 (1991) |
| Year | 57.5 | 23.1 | 36.53 |
Rain day: at least 0.10 in. Plan for: the 90th percentile of 1991-2020 yearly counts, rounded up to a whole day. Record: 1981 to date.
The last 12 months vs normal
From November 2025 through October 2026, Kennedale had 50 rain days against a normal of 57.4: a dry stretch, 7.4 days below normal. 5 of 12 months came in above normal and 7 below. The biggest departure was April 2026, with 11 rain days against a normal of 4.9. Precipitation totaled 33.47 in against 36.52 in normally.
| Month | Rain days | Normal | Difference | Precip (in) | Normal (in) |
|---|---|---|---|---|---|
| Nov 2025 | 6 | 4.6 | +1.4 | 5.85 | 2.74 |
| Dec 2025 | 0 | 4.3 | -4.3 | 0.00 | 2.78 |
| Jan 2026 | 2 | 4.1 | -2.1 | 1.58 | 2.37 |
| Feb 2026 | 1 | 4.4 | -3.4 | 1.65 | 2.61 |
| Mar 2026 | 3 | 5.1 | -2.1 | 2.69 | 3.34 |
| Apr 2026 | 11 | 4.9 | +6.1 | 4.59 | 3.14 |
| May 2026 | 9 | 7.2 | +1.8 | 5.17 | 4.43 |
| Jun 2026 | 4 | 5.5 | -1.5 | 3.39 | 3.37 |
| Jul 2026 | 5 | 3.7 | +1.3 | 2.16 | 2.02 |
| Aug 2026 | 0 | 3.8 | -3.8 | 0.00 | 2.18 |
| Sep 2026 | 3 | 4.5 | -1.5 | 0.94 | 3.07 |
| Oct 2026 | 6 | 5.3 | +0.7 | 5.45 | 4.47 |
Kennedale rain days month by month
Against the median Texas location, Kennedale gets more rain days in April and May, by half a day or more; other months are within half a day.
Rain days in January
Kennedale averages 4.1 rain days in January, 1.4 of them heavy, with 2.37 in of precipitation. Plan for 7 to cover 9 years in 10; the record is 8 (1992). January 2026 had 2, 2.1 below normal.
Rain days in February
Kennedale averages 4.4 rain days in February, 1.8 of them heavy, with 2.61 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 10 (2018). February 2026 had 1, 3.4 below normal.
Rain days in March
Kennedale averages 5.1 rain days in March, 2.3 of them heavy, with 3.34 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 11 (2020). March 2026 had 3, 2.1 below normal.
Rain days in April
Kennedale averages 4.9 rain days in April, 2.2 of them heavy, with 3.14 in of precipitation. Plan for 7 to cover 9 years in 10; the record is 11 (2026). That is 0.5 more than the median Texas location (4.4). April 2026 had 11, 6.1 above normal.
Rain days in May
Kennedale averages 7.2 rain days in May, 2.9 of them heavy, with 4.43 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 19 (2015). That is 1.3 more than the median Texas location (5.9). May 2026 had 9, 1.8 above normal.
Rain days in June
Kennedale averages 5.5 rain days in June, 2.1 of them heavy, with 3.37 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 12 (1992). June 2026 had 4, 1.5 below normal.
Rain days in July
Kennedale averages 3.7 rain days in July, 1.3 of them heavy, with 2.02 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 10 (2007). July 2026 had 5, 1.3 above normal.
Rain days in August
Kennedale averages 3.8 rain days in August, 1.4 of them heavy, with 2.18 in of precipitation. Plan for 7 to cover 9 years in 10; the record is 10 (2017). August 2026 had 0, 3.8 below normal.
Rain days in September
Kennedale averages 4.5 rain days in September, 1.4 of them heavy, with 3.07 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 13 (2018). September 2026 had 3, 1.5 below normal.
Rain days in October
Kennedale averages 5.3 rain days in October, 2.7 of them heavy, with 4.47 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 13 (2009). October 2026 had 6, 0.7 above normal.
Rain days in November
Kennedale averages 4.6 rain days in November, 1.7 of them heavy, with 2.74 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 11 (2004). November 2025 had 6, 1.4 above normal.
Rain days in December
Kennedale averages 4.3 rain days in December, 1.9 of them heavy, with 2.78 in of precipitation. Plan for 6 to cover 9 years in 10; the record is 12 (1991). December 2025 had 0, 4.3 below normal.
Using these numbers in a construction schedule
For Kennedale, the normal column is the expected count: 58 days over a full year, 35 of them from April through October. Put those days in the schedule as non-work days or float before the job starts, not after it slips.
Average or plan-for? An average is exceeded about half the time. If May work has no float, carry 11 weather days for it rather than 7.2: Kennedale had that many or fewer in 9 of 10 years from 1991 to 2020. Use the normals across a long job and the plan-for figure only for months on the critical path.
Heavy days. Kennedale averages 23 days a year with 0.50 in or more, most often in May (2.9). Those are the days most likely to stop earthwork, paving and concrete outright.
Claiming time for abnormal weather. Under AIA A201-2017 §15.1.6.2, a claim for extra time because of adverse weather has to show the conditions were abnormal for the period, could not have been reasonably anticipated, and had an adverse effect on the scheduled work. The normals above show what could be anticipated in Kennedale; the claim also needs the day-by-day record for your site and dates.
Price a rain-day report for a site in Kennedale. Enter your dates to see actual rain days against this normal for free. The full PDF ($99) adds the daily record, a month-by-month comparison and a method statement you can attach to a schedule update or claim.
Check rain days near KennedaleNearby
Kennedale is in Tarrant County, which averages 56 rain days a year across the county. Kennedale gets 1 more rain days a year than that county-wide average.
The nearest larger city, Arlington (7 mi away), averages 55 rain days a year: Kennedale gets 2 more.
Closest other areas in Texas:
- Forest Hill, Texas: 58 rain days / yr, 3 mi
- Everman, Texas: 56 rain days / yr, 4 mi
- Dalworthington Gardens, Texas: 57 rain days / yr, 5 mi
- Pantego, Texas: 56 rain days / yr, 6 mi
- Arlington, Texas: 55 rain days / yr, 7 mi
- Edgecliff Village, Texas: 57 rain days / yr, 7 mi
- Mansfield, Texas: 59 rain days / yr, 8 mi
- Crowley, Texas: 55 rain days / yr, 10 mi
Related guides
- AIA A201 Weather Delay Claims (ยง15.1.6.2): The Three Tests, With Real Numbers
- How Many Weather Days to Put in a Construction Schedule (Normal vs Plan-For)
- How to Document Weather Delays on a Construction Project (Checklist + Daily Log)
Method and source
A rain day is a day with at least 0.10 in (2.54 mm) in PRISM's daily estimate, which covers the 24 hours ending 12:00 UTC. Heavy days use 0.50 in. Normals are 1991-2020 averages. Records run from 1981 to the last complete month. Figures are for the 4 km cell containing the Census point for Kennedale (32.642747, -97.215704). Data through 2026-11-24; page updated 2026-11-25. How we count rain days.
Source: PRISM Group, Oregon State University, https://prism.oregonstate.edu. These are gridded estimates, not gauge readings; conditions at a particular site can differ.