Weather Delay Claim Report: Rain Days vs the 30-Year Normal for Any Job Site ($99)

The weather half of a delay claim turns on one question: was the rain abnormal for that place and time of year? This report answers it for the job site's own address, using PRISM 4 km gridded daily precipitation (Oregon State University, 1981 to present) against the 1991-2020 normal. Enter the address and delay period on the home page to see the headline count free.

What the claim has to prove

Under AIA A201-2017 §15.1.6.2, a claim for additional time based on adverse weather must be documented with data showing the weather was "abnormal for the period of time, could not have been reasonably anticipated" (AIA A201-2017), and that it had an adverse effect on the scheduled construction.

The report supplies data for the first two tests: rain days in your period against the 30-year normal for the same calendar window, and how many of the 30 baseline years had fewer. The adverse effect comes from your daily logs and schedule. See how to document weather delays and the A201 weather delay guide. Contracts word this differently and many modify A201, so check yours. This is not legal advice.

What's in the report

The default rain day is 0.10 in; set anything from 0.01 to 2.00 in to match your contract. One report covers up to 1,096 days at one site for $99, paid through Stripe, with the PDF delivered on your order page.

Worked example: Atlanta and Nashville, July 2026

PRISM 1991-2020 normals for the 4 km cell containing each city's Census point, data through 2026-11-24. A rain day is 0.10 in or more.

Place, July Normal rain days Plan-for (90th percentile) July 2026 Record since 1981
Atlanta, GA 10.0 13 17 23 (1994)
Nashville, TN 8.9 13 15 16 (1981)

Atlanta's July normal is 10.0 rain days. A scheduler planning for a wet July would carry 13, the 90th percentile. July 2026 had 17: seven above normal and four above the plan-for count. A schedule built for a wet July would still have come up short, which is the kind of evidence the "reasonably anticipated" test asks for.

Nashville had 15 rain days against a normal of 8.9 and a plan-for of 13, with 9.42 in of rain against a normal of 4.82 in. The free rain-day pages show monthly normals for any US city or county.

Rural and remote sites

Station-based reports usually rely on a nearby airport or cooperative observer gauge. For a pipeline, wind farm or highway job, the nearest one can be tens of miles away, and summer rain is local. In July 2026 the Atlanta cell counted 17 rain days, while the cell at Marietta, about 15 miles northwest, counted 11. Against Marietta's own normal of 9.7 and plan-for of 13, that month does not look abnormal. Atlanta's does.

PRISM combines gauges, terrain and, in the central and eastern US since 2002, radar into a 4 km grid over the contiguous US. Every address in the lower 48 has a daily record back to 1981, station or not. More in historical rainfall by address.

Compared with other sources

Source Data Price and delivery
RainDayRecord PRISM 4 km grid, any address, 1991-2020 baseline $99 per site, instant PDF
Ilystics NOAA GHCN station data, AIA formatted $249 per report
AWIS Station-based rainfall reports and rain-day calculations Price not listed on its home page
StormRecord One address, one date, hourly conditions $9.99 per date
NOAA NCEI certified copies Official station records Ordered from NCEI; you compute the comparison

Competitor prices are as listed on their sites in November 2026 and can change; check before you buy. See certified weather records for a construction claim for when certification matters.

Limits

This is a modeled estimate for a 4 km cell, not a certified gauge record. Gridded values typically differ from a single gauge by several millimetres a day, more in the West, in the cool season and on very wet days. PRISM re-models recent days several times and treats them as stable after six months. If your contract names a station, pair this report with NCEI certified data from it. Details are on the methodology page.

Frequently asked questions

Does this report prove my weather delay claim?

No report proves a claim on its own. It documents whether rain was abnormal for the period and place. Logs and schedule analysis show the adverse effect, and your contract sets what is required.

Can I match the rain-day threshold in my contract?

Yes. Set any threshold from 0.01 to 2.00 in. The report also shows counts at five standard thresholds.

What day boundary does the data use?

PRISM defines a day as the 24 hours ending at 12:00 UTC (7am Eastern Standard Time), labelled with the date on which it ends. Line it up with your daily logs accordingly.

How far back can a report go?

Data starts January 1, 1981 and runs through November 24, 2026. One report covers up to 1,096 days.

Is this a certified weather record?

No. It is a modeled estimate from PRISM. For a certified record, order station data from NOAA NCEI and use this report for site-specific context.