How to Document Weather Delays on a Construction Project (Checklist + Daily Log)
Many weather delay claims are lost in the field, months before anyone argues about them. The daily log says "rain" and nothing else, notice went out late, and nobody can say which activity slipped or how many of those days were normal for the month.
This guide covers what to record while it is raining, what to send and when, and how to turn a wet month into a number a reviewer can check. It is not legal advice, and your contract controls.
Step 1: Read the weather clause and the notice deadline
Before the first wet week, find what weather qualifies for time, what proof is required, and how many days you have to give notice. Common defaults, which supplementary conditions often change:
- AIA A201-2017. Claims generally require written notice within 21 days after the event giving rise to the claim, or within 21 days after you first recognize the condition, whichever is later (§15.1.3.1). Weather claims must be documented as abnormal for the period, not reasonably anticipated, and as having had an adverse effect on the scheduled construction (§15.1.6.2). Our guide to A201 weather claims walks through each test.
- Federal fixed-price construction (FAR 52.249-10). Unusually severe weather is listed among the unforeseeable causes that excuse delay. The contractor must notify the contracting officer in writing within 10 days from the beginning of the delay, unless the contracting officer extends that time.
- ConsensusDocs 200. Delay, including adverse weather not reasonably anticipated, is handled in Article 6, with its own notice requirement. Check the period in your edition rather than assuming it matches A201. Our side-by-side comparison covers all three.
- USACE and state DOT work. Many specifications state how many weather days are already built into the contract for each month. Only days beyond that count are typically excusable, so find that table before you count anything.
Put the notice deadline on the schedule when a wet stretch starts.
Step 2: Log the right fields every day
A useful entry answers one question: did weather stop or slow planned work today, and by how much? Record these fields every working day, including dry ones.
| Field | What to write |
|---|---|
| Date and hours | Calendar date, scheduled shift hours |
| Rain observed | Start and stop times, rough intensity, on-site gauge reading if you have one |
| Site condition | Standing water, mud depth, haul road status, excavations flooded, slab wet |
| Planned activities | What the look-ahead had scheduled today |
| Activities affected | Which ones stopped, slowed or moved, with schedule activity IDs |
| Trades and crews | Who stood down or went home, headcount, hours lost |
| Equipment | What sat idle |
| Photos | Time-stamped photos of the conditions and the idle work area |
| Signed by | Name of the person who saw it |
Write facts, not conclusions. "Footing excavation F-12 to F-18 flooded, 6 in. water, concrete pour cancelled, 8 finishers sent home at 9:30" will hold up. "Rain day" will not.
A daily log you can copy
If your software does not capture these fields, paste this header row into a spreadsheet and fill one row per day:
date,shift_hours,rain_start,rain_stop,gauge_in,site_condition,planned_activities,activities_affected,activity_ids,crews_stood_down,hours_lost,equipment_idle,photo_refs,dry_out_day,recorded_by
Fill in the dry_out_day column (yes or no) on days with no rain when the site was still unworkable. More on that in Step 6.
Step 3: Back the log with independent weather data
A reviewer will also want independent data showing how much rain fell and how that compares with normal.
- On-site rain gauge. The best record of what fell on your site, but it has no 30-year history to show what is normal.
- Weather station (NOAA, airport, cooperative observer). Long records and official status, but summer storms are local, and a station 15 miles away can miss a downpour on your site or record one you never had.
- Gridded data (PRISM). PRISM, from Oregon State University, estimates daily precipitation on a 4 km grid across the contiguous US from rain gauges, terrain and, in the central and eastern US since 2002, radar. It gives every address a daily record back to 1981 and a 30-year normal, which matters most for rural sites with no station nearby.
A PRISM day runs from 12:00 UTC to 12:00 UTC (7 a.m. Eastern Standard Time, 8 a.m. during daylight saving time) and carries the date it ends. Rain at 3 p.m. on the 10th shows up in the data dated the 11th. Match the log to the data with that offset in mind. Our methodology page covers this and the other differences between grid and gauge.
Step 4: Tie each lost day to the critical path
A rain day only earns time if it delayed work that controlled completion. If only non-critical work was planned, or the work could move indoors, the schedule may not have moved.
For each claimed day, name the critical or near-critical activity that was planned and could not proceed. Then show the effect in a time impact analysis: insert a weather fragnet into the schedule update in effect at the time and compare the forecast completion before and after. Keep the updates you used.
Step 5: Count the excess over normal, by month
Contracts generally expect you to plan for normal weather, so the claimable days are the ones above normal, or above the weather days your schedule or specification already carried.
Here is a worked example from Fort Wayne, Indiana. Figures are PRISM 1991-2020 normals for the 4 km cell containing the city, with rain days counted at 0.10 inch or more and data through 2026-11-24. "Plan-for" is the 90th percentile of the 30 baseline years: at most 3 of those 30 years had more rain days in that month.
| Month 2026 | Rain days | Normal | Plan-for | Over normal | Over plan-for | Precip (in) | Normal precip (in) |
|---|---|---|---|---|---|---|---|
| April | 14 | 7.8 | 11 | 6.2 | 3 | 8.09 | 3.82 |
| May | 8 | 8.7 | 12 | none | none | 3.28 | 4.58 |
| June | 7 | 8.3 | 12 | none | none | 3.93 | 4.13 |
| July | 7 | 7.2 | 10 | none | none | 2.68 | 3.91 |
| August | 14 | 6.8 | 9 | 7.2 | 5 | 7.30 | 4.01 |
| September | 6 | 5.8 | 9 | 0.2 | none | 5.83 | 3.06 |
| October | 3 | 6.0 | 9 | none | none | 1.04 | 2.77 |
August is the strong month. Fourteen rain days is 7.2 over the normal of 6.8 and 5 over the plan-for count of 9. No August at this cell since 1981 had more rain days. April was nearly as unusual, and no April since 1981 had more either.
July shows what is not claimable. Seven rain days is right at the July normal of 7.2. That was ordinary weather a bidder should have expected, and it belongs in the schedule, not in a claim.
September shows why you count days, not inches. Precipitation was nearly double the normal, but it fell on 6 days against a normal of 5.8. A few big storms cost fewer workdays than many small ones.
Which baseline you subtract depends on the contract. Some count the excess over the 30-year normal, some over a stated number of weather days, and some leave it to negotiation. Our guide on how many weather days to put in a schedule explains normal versus plan-for. Look up any city's monthly figures for free, for example Fort Wayne or Allen County, or browse all Indiana locations.
PRISM re-models recent days for about six months, so the figures from late May on are still provisional. Pull the numbers again before you finalize a claim.
Step 6: Log dry-out days after heavy rain
A 1.5-inch storm can shut down earthwork for days after the sky clears. Those dry-out days are easy to lose because the log for that day says "clear."
Flag heavy rain days (0.50 inch or more) in the log, then record every following day the site stayed unworkable and why: saturated subgrade, failed proof roll, flooded excavation. Some contracts and many DOT specifications count days when conditions prevented work on controlling items, not only days with rain. Others do not. Check yours. Fort Wayne's August normal is 2.6 heavy days, so a month well above that is worth noting in the claim.
Step 7: Keep weather delays separate from owner-caused delays
If an owner's late design change and a wet month overlap, mixing them in one narrative invites a fight about concurrent delay. Weather delays usually earn time only, while owner-caused delays may also earn money. Track them as separate fragnets with separate cause codes, and let the analysis show where they coincide.
Step 8: Write the notice letter
Keep notice short and on time; the analysis can follow. A typical notice covers:
- The contract and the clause you are giving notice under, for example A201 §15.1.3.1 and §15.1.6.2.
- The dates the adverse weather started and whether it is continuing.
- The work affected, with schedule activity IDs.
- A plain statement that the conditions appear abnormal for the period, with the rain-day count so far against the normal for that month at the site.
- That you are requesting an extension of the Contract Time and will submit the quantified request and supporting data by a stated date.
- That logs, photos and weather records are being kept.
Send it to the parties and by the method the contract requires, and keep proof of delivery. Under A201 that means the other party and the Initial Decision Maker, copying the Architect if it is not the Initial Decision Maker.
Checklist: before, during and after a wet stretch
- Before: find the weather clause, notice deadline and any weather-day table. Put the site's monthly normal and plan-for rain days in the baseline schedule.
- During: log every day, including dry-out days, with activity IDs, crews and photos. Send notice inside the deadline.
- After: pull independent rain-day data for the full period, count the excess month by month, run the time impact analysis, keep weather separate from owner delay, and submit it all together.
A Rain-Day Report does the data step for $99 per site: daily rain days for your dates at your address, against the 1991-2020 normal and plan-for count, as a PDF.
Frequently asked questions
What should a construction daily log say about weather?
Rain start and stop times, site conditions, which planned activities stopped, which crews stood down and for how long, and time-stamped photos. Record the effect on work, not just the weather.
How soon do I have to give notice of a weather delay?
It depends on the contract. A201-2017 generally allows 21 days, and FAR 52.249-10 requires written notice within 10 days from the beginning of the delay. Your supplementary conditions may change those periods, so check your contract.
Can I claim every day it rained?
Usually not. Most contracts expect you to plan for normal weather, so only days above the normal, or above the weather days your contract already includes, are typically claimable. Those days also need to have delayed critical work.