How to Document Weather Delays on a Construction Project (Checklist + Daily Log)

Many weather delay claims are lost in the field, months before anyone argues about them. The daily log says "rain" and nothing else, notice went out late, and nobody can say which activity slipped or how many of those days were normal for the month.

This guide covers what to record while it is raining, what to send and when, and how to turn a wet month into a number a reviewer can check. It is not legal advice, and your contract controls.

Step 1: Read the weather clause and the notice deadline

Before the first wet week, find what weather qualifies for time, what proof is required, and how many days you have to give notice. Common defaults, which supplementary conditions often change:

Put the notice deadline on the schedule when a wet stretch starts.

Step 2: Log the right fields every day

A useful entry answers one question: did weather stop or slow planned work today, and by how much? Record these fields every working day, including dry ones.

Field What to write
Date and hours Calendar date, scheduled shift hours
Rain observed Start and stop times, rough intensity, on-site gauge reading if you have one
Site condition Standing water, mud depth, haul road status, excavations flooded, slab wet
Planned activities What the look-ahead had scheduled today
Activities affected Which ones stopped, slowed or moved, with schedule activity IDs
Trades and crews Who stood down or went home, headcount, hours lost
Equipment What sat idle
Photos Time-stamped photos of the conditions and the idle work area
Signed by Name of the person who saw it

Write facts, not conclusions. "Footing excavation F-12 to F-18 flooded, 6 in. water, concrete pour cancelled, 8 finishers sent home at 9:30" will hold up. "Rain day" will not.

A daily log you can copy

If your software does not capture these fields, paste this header row into a spreadsheet and fill one row per day:

date,shift_hours,rain_start,rain_stop,gauge_in,site_condition,planned_activities,activities_affected,activity_ids,crews_stood_down,hours_lost,equipment_idle,photo_refs,dry_out_day,recorded_by

Fill in the dry_out_day column (yes or no) on days with no rain when the site was still unworkable. More on that in Step 6.

Step 3: Back the log with independent weather data

A reviewer will also want independent data showing how much rain fell and how that compares with normal.

A PRISM day runs from 12:00 UTC to 12:00 UTC (7 a.m. Eastern Standard Time, 8 a.m. during daylight saving time) and carries the date it ends. Rain at 3 p.m. on the 10th shows up in the data dated the 11th. Match the log to the data with that offset in mind. Our methodology page covers this and the other differences between grid and gauge.

Step 4: Tie each lost day to the critical path

A rain day only earns time if it delayed work that controlled completion. If only non-critical work was planned, or the work could move indoors, the schedule may not have moved.

For each claimed day, name the critical or near-critical activity that was planned and could not proceed. Then show the effect in a time impact analysis: insert a weather fragnet into the schedule update in effect at the time and compare the forecast completion before and after. Keep the updates you used.

Step 5: Count the excess over normal, by month

Contracts generally expect you to plan for normal weather, so the claimable days are the ones above normal, or above the weather days your schedule or specification already carried.

Here is a worked example from Fort Wayne, Indiana. Figures are PRISM 1991-2020 normals for the 4 km cell containing the city, with rain days counted at 0.10 inch or more and data through 2026-11-24. "Plan-for" is the 90th percentile of the 30 baseline years: at most 3 of those 30 years had more rain days in that month.

Month 2026 Rain days Normal Plan-for Over normal Over plan-for Precip (in) Normal precip (in)
April 14 7.8 11 6.2 3 8.09 3.82
May 8 8.7 12 none none 3.28 4.58
June 7 8.3 12 none none 3.93 4.13
July 7 7.2 10 none none 2.68 3.91
August 14 6.8 9 7.2 5 7.30 4.01
September 6 5.8 9 0.2 none 5.83 3.06
October 3 6.0 9 none none 1.04 2.77

August is the strong month. Fourteen rain days is 7.2 over the normal of 6.8 and 5 over the plan-for count of 9. No August at this cell since 1981 had more rain days. April was nearly as unusual, and no April since 1981 had more either.

July shows what is not claimable. Seven rain days is right at the July normal of 7.2. That was ordinary weather a bidder should have expected, and it belongs in the schedule, not in a claim.

September shows why you count days, not inches. Precipitation was nearly double the normal, but it fell on 6 days against a normal of 5.8. A few big storms cost fewer workdays than many small ones.

Which baseline you subtract depends on the contract. Some count the excess over the 30-year normal, some over a stated number of weather days, and some leave it to negotiation. Our guide on how many weather days to put in a schedule explains normal versus plan-for. Look up any city's monthly figures for free, for example Fort Wayne or Allen County, or browse all Indiana locations.

PRISM re-models recent days for about six months, so the figures from late May on are still provisional. Pull the numbers again before you finalize a claim.

Step 6: Log dry-out days after heavy rain

A 1.5-inch storm can shut down earthwork for days after the sky clears. Those dry-out days are easy to lose because the log for that day says "clear."

Flag heavy rain days (0.50 inch or more) in the log, then record every following day the site stayed unworkable and why: saturated subgrade, failed proof roll, flooded excavation. Some contracts and many DOT specifications count days when conditions prevented work on controlling items, not only days with rain. Others do not. Check yours. Fort Wayne's August normal is 2.6 heavy days, so a month well above that is worth noting in the claim.

Step 7: Keep weather delays separate from owner-caused delays

If an owner's late design change and a wet month overlap, mixing them in one narrative invites a fight about concurrent delay. Weather delays usually earn time only, while owner-caused delays may also earn money. Track them as separate fragnets with separate cause codes, and let the analysis show where they coincide.

Step 8: Write the notice letter

Keep notice short and on time; the analysis can follow. A typical notice covers:

  1. The contract and the clause you are giving notice under, for example A201 §15.1.3.1 and §15.1.6.2.
  2. The dates the adverse weather started and whether it is continuing.
  3. The work affected, with schedule activity IDs.
  4. A plain statement that the conditions appear abnormal for the period, with the rain-day count so far against the normal for that month at the site.
  5. That you are requesting an extension of the Contract Time and will submit the quantified request and supporting data by a stated date.
  6. That logs, photos and weather records are being kept.

Send it to the parties and by the method the contract requires, and keep proof of delivery. Under A201 that means the other party and the Initial Decision Maker, copying the Architect if it is not the Initial Decision Maker.

Checklist: before, during and after a wet stretch

A Rain-Day Report does the data step for $99 per site: daily rain days for your dates at your address, against the 1991-2020 normal and plan-for count, as a PDF.

Frequently asked questions

What should a construction daily log say about weather?

Rain start and stop times, site conditions, which planned activities stopped, which crews stood down and for how long, and time-stamped photos. Record the effect on work, not just the weather.

How soon do I have to give notice of a weather delay?

It depends on the contract. A201-2017 generally allows 21 days, and FAR 52.249-10 requires written notice within 10 days from the beginning of the delay. Your supplementary conditions may change those periods, so check your contract.

Can I claim every day it rained?

Usually not. Most contracts expect you to plan for normal weather, so only days above the normal, or above the weather days your contract already includes, are typically claimable. Those days also need to have delayed critical work.

All guides · Rain days by city and county