How Many Weather Days to Put in a Construction Schedule (Normal vs Plan-For)

Every schedule carries weather days, whether anyone writes them down or not. The question is how many, in which months, and what the number will mean later if a wet month turns into a time extension request.

This guide sets out a monthly method using rain-day counts at 0.10 inch or more, a common cutoff for a rain day that affects outdoor work. All numbers below are PRISM 1991-2020 normals for the 4 km cell containing each city, with data through 2026-11-24. You can pull the same figures for any US site from the rain-days pages.

Why a flat "10 weather days" allowance fails

A lump-sum allowance treats a January start the same as a July start. In most of the country those months are nothing alike.

Houston averages 9.0 rain days in June and 4.8 in April. In Portland, Oregon, December averages 14.8 and July 1.5. A flat 10-day allowance on a four-month Portland job is a little short for June through September, which averages 12.8 rain days, and covers less than a fifth of November through February, which averages 54.3.

A flat number also fails when it comes time to make a claim. Under AIA A201-2017 §15.1.6.2, a claim for time based on adverse weather has to be documented with data showing the weather was abnormal for the period, could not have been reasonably anticipated, and had an adverse effect on the scheduled construction. A single project-wide allowance says nothing about what was anticipated for a given month, so both sides end up arguing from scratch. Our guide to A201 weather delay claims covers those tests in detail.

The monthly method

List each calendar month the job is exposed to weather, then write down the expected rain days for that month at that site.

Many US Army Corps of Engineers construction contracts include a clause on time extensions for unusually severe weather, with a table of anticipated adverse weather delay days for each month, stated on a five-day work week. The contractor's schedule is expected to show those days in weather-dependent activities, and only days beyond the monthly figure count toward an extension. Wording and table placement vary by district and solicitation, so read the one in your contract. The underlying federal standard, "unusually severe weather," is an excusable cause of delay under FAR 52.249-10 for fixed-price construction (and FAR 52.249-14 for cost-reimbursement and time-and-materials contracts); we compare it with AIA and ConsensusDocs language in what counts as unusually severe weather.

Private contracts can borrow the same approach. A monthly table gives the owner, the architect and the scheduler one number per month that everyone agreed to before the work started.

Average or plan-for

Each city and county page shows two counts per month:

The normal is an average. A typical year beats it in some months and falls short in others, and in any given month it is exceeded often. If a critical activity has no float, carrying the normal means you are betting on an average month.

The plan-for is the conservative figure. Across the 100 largest cities on our pages (contiguous US), looking at every city-month with at least 3 normal rain days (898 of them), the median plan-for is 1.52 times the normal. The ratio is highest where rain comes in occasional storms, and in wet climates the gap in days is large even at an ordinary ratio:

City Month Normal rain days Plan-for
Anaheim, CA January 4.7 13
Los Angeles, CA January 5.3 13
Portland, OR December 14.8 22
Houston, TX June 9.0 15

In Southern California January rain arrives in storms. The most January rain days since 1981 was 16 in Los Angeles (1995) and 15 in Anaheim (1993). Carrying 5 days there is reasonable on average and well short about one year in ten.

A practical rule: carry the plan-for figure in the months where a weather-sensitive activity sits on the critical path with no float (mass excavation, foundations, roofing before dry-in). Carry the normal elsewhere.

Do not add up the plan-for column

Totaling the plan-for column overstates the risk, because bad months rarely line up in the same year.

For a full year, summing the twelve plan-for months gives:

City Annual normal Sum of 12 plan-for months
Portland, OR 109.5 170
Houston, TX 78.1 125
Dallas, TX 63.2 110

A Houston year with 125 rain days would need every month to be a one-in-ten month at once. The record months on the Houston page show how spread out the wet years are: the June with the most rain days since 1981 was in 2004, July in 2007, August in 2005, and November in 2000.

A better way to size a multi-month contingency is to treat the plan-for gap in each month as a measure of spread and combine the gaps the way you would combine independent tolerances: square each month's gap (plan-for minus normal), add them, take the square root, and add that to the summed normals. This is a rule of thumb that assumes months are independent. Wet months do sometimes run together in the same season, so treat the result as a floor for a long job, not a guarantee.

Applied to a full year, that gives about 93 rain days in Houston, 128 in Portland and 77 in Dallas, well under the summed plan-for figures.

Worked example: a Houston job from June through November

Suppose a site and structure package in Houston runs June 1 to November 30, with earthwork and foundations in June through August.

Month Normal rain days Plan-for Normal on a 5-day week Heavy days (0.50 in+)
June 9.0 15 6.4 3.9
July 8.2 15 5.9 3.0
August 8.5 13 6.1 3.4
September 7.5 11 5.4 3.4
October 5.1 10 3.6 2.6
November 5.8 8 4.1 3.0
Total 44.1 72 31.5 19.3

Three ways to carry it:

  1. Normal in every month: 44.1 calendar rain days. This is the defensible "reasonably anticipated" baseline, but it leaves no cushion.
  2. Plan-for in every month: 72. Overstated for a six-month job, and if this table goes into the contract as the anticipated count, it raises the bar for any future weather claim.
  3. Normal plus one combined contingency: the root-sum-square of the six monthly gaps is about 12 days, for roughly 56 calendar rain days in total. Put the contingency where it protects the critical earthwork in June through August.

June 2026 in the Houston cell had 12 rain days against a normal of 9.0 and a plan-for of 15. A schedule carrying the normal lost 3 more days than planned. A claim for those 3 days would be hard to argue as abnormal: 12 is under the plan-for of 15, and at least 27 of the 30 Junes from 1991 to 2020 had 15 or fewer.

Heavy days and dry-out time

A rain day at 0.10 inch can stop concrete placement and roofing. It may not stop interior work, and it may not be the end of the lost time for earthwork.

After a heavy day (0.50 inch or more), clay subgrades and unpaved haul roads can stay unworkable after the rain ends. The Houston June through November window averages 19.3 heavy days. Some schedulers add a dry-out day after each heavy day on activities that depend on ground conditions. Whether you do, and whether your contract lets you count a dry-out day as a weather day, is a project decision. Write the rule down before the job starts, and record dry-out days in the daily log with the reason. Our weather delay documentation checklist covers what to log.

Work days vs calendar days

Rain-day counts are calendar days. If the crew works Monday through Friday, only about 5 in 7 rain days fall on a scheduled workday. Houston's June normal of 9.0 rain days converts to about 6.4 working days.

If the contract table is stated in work days (as USACE tables are), compare it against actual lost work days, not every rainy Saturday. If your schedule runs on calendar days, do not convert, or you will under-carry by more than a quarter.

A template you can copy

Build one row per month the job is exposed to weather:

Month Normal rain days Plan-for Carried in schedule Basis
(month) from city page from city page your number normal, plan-for, or normal + share of contingency

Pull the first two columns from the monthly table on the city or county page for the job site. If the site is rural, use the county page or a free lookup on the address, since the PRISM grid covers sites with no nearby weather station. The methodology page explains how the counts are built.

When a month goes past the count

If a month beats the number you carried, log it while it happens and send notice within your contract's deadline. The free preview on the home page shows rain days at any US address for a chosen period next to the normal and plan-for count. For the claim file, the $99 Rain-Day Report gives the same comparison as a PDF, and you can view a sample report first.

Frequently asked questions

How many weather days should I put in a construction schedule?

Use the monthly normal rain days at 0.10 inch or more for each month the job runs, from 30-year data for the site. For critical months with no float, carry the 90th-percentile plan-for figure instead. Avoid a flat project-wide number.

Should I use the average or the 90th percentile?

The 30-year average is the usual starting point for what could reasonably be anticipated, which is what clauses like A201 §15.1.6.2 measure against. The 90th percentile protects the schedule. A workable approach is to carry the normal as the baseline and add one contingency sized from the monthly gaps, rather than putting the 90th percentile in every month. Check your contract.

Are weather days calendar days or work days?

Rain-day normals are calendar days. USACE weather tables state anticipated delay days on a five-day work week. Convert by multiplying calendar rain days by 5/7 for a Monday-to-Friday schedule, and check which basis your contract uses.

Does putting more weather days in the schedule hurt a later claim?

It can. If the contract states a monthly count of anticipated weather days, only days beyond that count usually qualify for an extension. A higher anticipated count protects the schedule but raises the bar for a claim. Check your contract; this is not legal advice.