Sample Rain-Day Report (PDF): What the $99 Report Contains

This weather delay report sample has the same sections and layout as a $99 order: four months in five pages, with more daily-record pages for longer periods. Send it to the owner, architect or adjuster who will review your claim before you buy.

Download the sample Rain-Day Report (PDF, 5 pages)

The sample uses illustrative data, not real PRISM values. It is set at a made-up Grand Island, Nebraska, address for March 1 to June 30, 2024. The real PRISM 1991-2020 normal for March through June in the 4 km cell containing Grand Island is 24.4 rain days, not the sample's 27.4. Ordered reports use real PRISM data for your site and dates.

Page 1: site, period and headline

The header gives the site, its latitude and longitude, and the center of the PRISM 4 km grid cell that contains it. Every number is for that cell.

Next come the period (122 days in the sample), the rain-day threshold (0.10 in by default, or any value from 0.01 to 2.00 in) and the 1991-2020 baseline.

Then the headline most claims quote: 36 rain days against a normal of 27.4 (+8.6 days), more rain days than in 27 of 30 baseline years, and 14.69 in of precipitation against a normal of 12.96 in.

Page 1: rain days by month

A bar chart and a table give each month's rain days, normal, difference, precipitation and normal precipitation. In the sample, March ran +0.2 days while April, May and June ran +2.7, +3.3 and +2.4.

Page 1: other thresholds and years exceeded

The same comparison runs at 0.01, 0.10, 0.25, 0.50 and 1.00 in. "Years exceeded" counts how many of the 30 baseline years had fewer rain days than your period. In the sample, the 0.10 in row beats 27 of 30 years, but the 0.50 in row (8 days against a normal of 8.6) beats only 9. The extra days came from moderate rain; heavy days ran slightly below normal. Cite the row matching your contract's definition; the other side will read every row.

Pages 1 to 4: daily record

Every day is listed in inches and millimetres, with rain days flagged, to line up against your daily logs. A PRISM day runs 12:00 to 12:00 UTC (7am to 7am Eastern Standard Time) and carries the date it ends, so rain on a Tuesday afternoon appears on Wednesday's line.

Last page: method, limits and source credit

Five short paragraphs state the data (PRISM AN 4 km daily, built from rain gauges, radar from 2002 and terrain), the day definition, how the normal is calculated, the date after which PRISM may still revise values (about six months before the data end) and how a grid cell differs from a gauge. Then the PRISM Group, Oregon State University credit and the report ID, which also appears in every footer. More on the methodology page.

The monthly table with real numbers: Atlanta, summer 2026

Real PRISM values for the 4 km cell containing Atlanta, June 1 to August 31, 2026, against 1991-2020 normals (data through 2026-11-24):

Month Rain days Normal Difference Precip (in) Normal (in)
Jun 2026 6 9.5 -3.5 3.08 4.40
Jul 2026 17 10.0 +7.0 5.50 5.21
Aug 2026 8 9.0 -1.0 3.03 4.43
Jun to Aug 31 28.5 +2.5 11.61 14.04

The summer ran 2.5 rain days over normal, with less rain than usual. July is the month that matters: 17 rain days against a normal of 10.0 and a plan-for count of 13, the 90th percentile of the 30 baseline Julys. The plan-for count is on the free Atlanta page; the report shows years exceeded. PRISM treats daily data as stable after about six months, so all three months may still be revised, and a report run now says so.

How to attach it to a claim

Order one report per site for the claim period, at your contract's threshold, and attach it as an exhibit. Quote the headline and the relevant monthly rows, then match the daily record to your logs and schedule to show which rain days stopped critical-path work.

AIA A201-2017 §15.1.6.2 asks a weather claim to show three things: weather that was abnormal for the period, that nobody could reasonably have planned for, and that hurt the scheduled work. The report is evidence on the first two. The third has to come from your own records. Check your own contract's wording. This is not legal advice. See how to document weather delays, the A201 weather delay guide and what the weather delay claim report includes.

Frequently asked questions

Is the data in the sample report real?

No. The sample PDF is illustrative. Ordered reports and the Atlanta table above use real PRISM data.

Is the report a certified weather record?

No. It is a reproducible analysis of public PRISM data with the method stated, not a NOAA-certified record. NOAA's National Centers for Environmental Information (NCEI) will certify copies of its station records for a fee. See certified weather records for a construction claim for how the two fit together.

How do I get a report for my own site?

Enter an address or coordinates and dates (up to 1,096 days, from 1981 on) on the home page for a free headline preview. Pay $99 at checkout and the PDF is ready on your order page.