RainDayRecord counts rain days at a job site for any period and compares them with the 30-year normal for the same calendar dates. Contractors, schedulers, claims consultants, attorneys and adjusters use the count to show whether the weather was abnormal.

Why RainDayRecord exists

Weather delay clauses usually turn on one question: was the weather worse than normal for that place and time of year? AIA A201-2017, for example, asks for data showing the weather was abnormal for the period, could not have been reasonably anticipated, and had an adverse effect on the scheduled construction (section 15.1.6.2; check your own contract). The weather part takes two numbers: what happened at the site, and what normally happens there.

The nearest weather station can be miles from the site, in different terrain, with gaps in its record. We built RainDayRecord to give a repeatable count for the site's own location in minutes, at a fixed price.

What we do

Coverage

Item Coverage
Area The 48 contiguous states and the District of Columbia
Grid PRISM 4 km cells; every address falls in one
Period January 1, 1981 to the latest PRISM day
Updates Reports: daily, data currently through 2026-11-24. City and county pages: monthly
Normal 1991-2020, the same 30 years as NOAA's current U.S. Climate Normals
Free pages 13,348: 10,239 incorporated places with 1,000 or more people (Census estimates) and 3,109 counties

Alaska, Hawaii and the US territories are not covered.

Our data source

All precipitation figures come from the PRISM AN 4 km daily dataset produced by the PRISM Group at Oregon State University (prism.oregonstate.edu). PRISM combines rain gauge observations and terrain into an estimate for each cell, and in the central and eastern US it has also blended in radar since 2002. Every report and page carries that attribution.

RainDayRecord is an independent business. We are not part of, or endorsed by, Oregon State University, the PRISM Group or NOAA. Our methodology page explains how we count days, how PRISM's 12Z-to-12Z day lines up with your daily logs, and why a grid cell can differ from a gauge on your site.

What we do not do

Contact us

Email support@raindayrecord.com. For anything about an order, include your order page link, or the email you used at checkout plus the site and dates.

Failed or late reports. If your order page says the report could not be built, reload the page; that retries the build. If it still fails, email us with the order link within 30 days of purchase and, under our terms, we will regenerate the report or refund the $99.

Lost order link. There is no account, so the order link is your way back to the PDF. If you lose it, email us from the address you paid with and we will send the link to that address.

Revised data. PRISM revises recent days for about six months as late gauge reports arrive. A report reflects the data on the day it was made. If you need figures for a recent period checked again before a deadline, ask us.

Media and partners. Journalists, software vendors and firms with many sites can use the same address, with "Media" or "Partner" in the subject line.

Frequently asked questions

Is RainDayRecord affiliated with Oregon State University or NOAA?

No. We use the PRISM dataset from Oregon State University and credit it on every page and report, but neither the university nor NOAA reviews or endorses our reports.

What happens if I pay and the report does not appear?

Reload your order page, which retries the build. If it keeps failing, email support@raindayrecord.com with your order link. We will regenerate the report or refund it, as set out in our terms.

Can RainDayRecord tell me whether my weather delay claim is valid?

No. We provide the rain-day count and the 30-year comparison. Whether a delay is excusable depends on your contract, notice and schedule. Check your contract and talk to your own advisers; this is not legal advice.