AIA A201 Weather Delay Claims (§15.1.6.2): The Three Tests, With Real Numbers
If your contract is built on AIA A201-2017, a request for more time because of rain runs through one short clause: §15.1.6.2. It sets three tests. Weather claims most often run into trouble on the first two, because "it rained a lot" is not the same as "it rained more than anyone should have planned for."
This guide walks through the clause and tests each element against real 2026 rain-day counts, including one month that looks like a claim and probably is not. It is not legal advice. Read your own agreement and supplementary conditions, which often change the A201 defaults.
Where the weather clause sits in A201-2017
Three provisions work together. Check the numbering against your copy, since it shifted between editions.
- §8.3.1, extensions of time. The Contract Time can be extended for delay caused by, among other things, adverse weather conditions documented in accordance with §15.1.6.2.
- §15.1.6.2, the weather documentation standard. A weather claim must be backed by data showing the conditions were "abnormal for the period of time," could not have been "reasonably anticipated," and had an "adverse effect on the scheduled construction" (AIA A201-2017).
- §15.1.3.1, notice. Claims are generally initiated by written notice within 21 days after the event, or within 21 days after the claimant first recognizes the condition, whichever is later. Under §15.1.6.1, a continuing delay needs only one claim.
In A201-2007 the same weather language sat at §15.1.5.2, and in A201-1997 at §4.3.7.2. If an older form is in play, the substance is close but the cites differ.
The 21-day window is the part people miss. A wet month can be over before anyone pulls the weather data, so log the delay and send notice while it is happening, then back it up with the numbers. Our checklist for documenting weather delays covers the daily log side.
Test 1: Was the month abnormal for that site?
The first test points to a comparison with what is normal at that place, in that part of the year. Two common mistakes:
- Comparing the annual total. A dry spring can hide a soaked July. The question is about the period of the delay.
- Comparing inches instead of days. Crews lose days, not inches. One 3-inch storm costs a day or two. Seventeen days of 0.25 inches can cost most of a month.
Atlanta in July 2026 shows the second point. The 4 km PRISM cell containing the city got 5.50 inches, close to its July normal of 5.21 inches. On rainfall totals alone, nothing looks unusual. But it had 17 rain days (at least 0.10 inch) against a July normal of 10.0. That gap is what slowed the work, and an inch-based comparison would have missed it.
So the baseline you want is the 30-year count of rain days for the same calendar month at the same location. You can look up any city's monthly normals for free, for example Atlanta, Raleigh or San Antonio.
Test 2: Could it have been reasonably anticipated?
A bidder in Atlanta knows July is wet. The normal (10.0 rain days) is the clearest evidence of what a contractor should have anticipated, and a reasonable starting point for the weather days a schedule carries for the month.
But the normal is an average. It is exceeded in a large share of years, so beating it by a day or two is weak evidence that the weather was beyond anticipation. A more defensible line is a high but ordinary year. On our pages we call it the plan-for number: the 90th percentile of the 1991-2020 monthly counts for that cell, so at least 27 of the 30 baseline years had that many rain days or fewer.
The gap between the two is not small. In the median city among the 100 largest in the contiguous US, the twelve monthly plan-for counts add up to about 1.55 times the twelve monthly normals. A month can be well above average and still inside the range a careful bidder should expect. See how many weather days to put in a schedule.
Here is how that played out over the last 12 complete months (November 2025 through October 2026) in those 100 cities: 324 city-months came in above their normal but at or under the plan-for count. Only 69 went past the plan-for. A claim built on one of the 69 is a much easier argument than one built on one of the 324. The list of 2026 months that beat the plan-for count names all 69.
Test 3: Did it have an adverse effect on the scheduled construction?
Weather data proves the weather. It does not prove the delay. For this element you need project records:
- The schedule. Show the rain hit activities on the critical path, or activities that became critical. Rain on a day when only interior trim was underway is hard to claim.
- Daily logs. Record crews sent home, activities stopped, and the cause, each day. Note lost days caused by wet ground after the rain stopped.
- Before and after. Show where the work stood before the wet period and how the forecast completion moved.
Owners and architects will look for this link. A rain day on the record is not automatically a lost workday.
Time, usually not money
Weather is the standard example of an excusable but non-compensable delay: it can justify more time but rarely more money. A201 §8.3.1 deals with extending the Contract Time. §8.3.3 says the section does not preclude recovery of delay damages under other provisions, but many owners add no-damages-for-delay language in supplementary conditions, and §15.1.7 contains a mutual waiver of consequential damages. Whether any cost is recoverable depends on your contract and your jurisdiction. Check with counsel.
If your contract has liquidated damages, a granted weather extension usually means relief from them for those days. That alone can make the claim worth filing properly.
When the contract fixes the weather days for you
Some owners replace the "abnormal" test with a table. The contract lists the number of weather days the contractor must absorb in each month, and only days beyond that count. US Army Corps of Engineers contracts commonly do this with a schedule of monthly anticipated adverse weather delay days, and some state and university owners put similar tables in their supplementary conditions.
If your contract has a table, it controls. Your job becomes counting actual weather days that stopped critical work and comparing them to the table. The PRISM normals are still useful as a check on whether the table is realistic. For how A201, ConsensusDocs 200 and federal FAR clauses compare, see what counts as unusually severe weather.
Three 2026 months that beat the plan-for count, and one that did not
All figures below are PRISM 4 km gridded daily precipitation for the cell containing each city. Normal and plan-for use the 1991-2020 baseline, and a rain day is at least 0.10 inch. Data runs through 2026-11-24.
| City and month | Actual rain days | Normal | Plan-for (p90) | Over normal | Over plan-for |
|---|---|---|---|---|---|
| Atlanta, GA, Jul 2026 | 17 | 10.0 | 13 | 7.0 | 4 |
| Raleigh, NC, Jul 2026 | 15 | 8.7 | 12 | 6.3 | 3 |
| San Antonio, TX, Apr 2026 | 9 | 3.8 | 7 | 5.2 | 2 |
| Atlanta, GA, May 2026 | 10 | 7.7 | 11 | 2.3 | none (1 under) |
Raleigh, July 2026. 15 rain days and 12.64 inches, against a July normal of 4.66 inches. No July in the cell's record back to 1981 had more rain days. This is about as clean as the first two tests get.
San Antonio, April 2026. 9 rain days against a normal of 3.8, more than double. No April in the record back to 1981 had more. In a dry climate a few extra days is a large departure.
Atlanta, July 2026. 17 days against a plan-for of 13, with rainfall only slightly above normal. Well past the plan-for count, though not a record: the cell had 23 July rain days in 1994.
Atlanta, May 2026, the counter-example. 10 rain days against a normal of 7.7 is about 30 percent above average. It sounds like a claim. But the plan-for count is 11, so May 2026 stayed within the range that at least 27 of the 30 baseline years fell inside. Expect pushback that a prudent bidder should have anticipated it.
For a job, run the same table for every month of the delay period. Watch whether your contract lets the owner net dry months against wet ones. In Atlanta, a May-to-August 2026 job saw 41 rain days against a combined normal of 36.2. That is only 4.8 days over for the four months, even with July 7 days over on its own.
Frequently asked questions
Which baseline years should a weather delay claim use?
Use what the contract specifies. If it is silent, the 1991-2020 period is the current official US climate normal published by NOAA, which makes it a defensible default. Using a short or hand-picked set of years invites the argument that the baseline was chosen to fit the claim. See our methodology for how the normals are computed.
Why count rain days at 0.10 inch?
It is a common working threshold for a day wet enough to affect site work, and NOAA's normals report days at or above 0.10 inch alongside 0.01, 0.50 and 1.00 inch. Some contracts or owners use a different threshold, or count only days that actually stopped work. Our pages also show heavy days at 0.50 inch or more.
Is gridded data acceptable, or do I need a weather station?
A201 does not name a data source, and many contracts are silent too, so check yours. Station records can be certified by NOAA's NCEI, which some reviewers prefer. The nearest station may be many miles from a rural site, though. PRISM estimates daily precipitation for every 4 km cell using station data and terrain. Many claims use both. Our guide to certified weather records compares them.
Does a rain day automatically mean a lost workday?
No. A rain day shows the weather. Your daily logs and schedule have to show that work on the critical path stopped or slowed because of it. Lost days from wet ground after the rain ends also need to be logged as they happen.