Rain days in Troy, Michigan
Troy averages 78 rain days a year, counting days with at least 0.10 in of precipitation in the PRISM 4 km grid cell that contains it (1991-2020 normals). May is the wettest month at 8.1 rain days and February the driest at 5.0. That is close to the Michigan median of 79.
Quick answers
How many rain days does Troy get a year?
About 78: that many days in a normal year bring 0.10 in or more of rain or melted snow. That makes Troy the 194th wettest of 342 Michigan cities and towns.
What is the wettest month in Troy?
May, with 8.1 rain days in a normal year. To cover 9 years in 10, plan for 12.
What is the driest month?
February, with 5.0 rain days (plan for 7).
How many heavy-rain days does Troy get?
19 a year with 0.50 in or more, most often in May (2.1).
Why these counts are lower than some weather sites': a rain day here means 0.10 in or more. Counts based on 0.01 in (NOAA's "days with precipitation") or 0.04 in (WeatherSpark) also include drizzle and trace days.
Rain days by month
The wettest three months are April-June, with 23.5 rain days combined; the driest are January-March, with 16.5. October swings the most from year to year: it averages 6.6 rain days, but covering 9 years in 10 takes 11. The most rain days in a single month since 1981 was 16, in November 1985.
| Month | Normal rain days | Plan for 9 of 10 yrs |
Heavy days ≥ 0.50 in |
Precip (in) | Record (year) |
|---|---|---|---|---|---|
| January | 6.1 | 8 | 1.1 | 2.31 | 12 (2005) |
| February | 5.0 | 7 | 0.9 | 1.97 | 10 (2008) |
| March | 5.4 | 8 | 1.3 | 2.34 | 10 (2023) |
| April | 7.6 | 11 | 1.8 | 3.08 | 14 (2026) |
| May | 8.1 | 12 | 2.1 | 3.74 | 13 (2011) |
| June | 7.8 | 11 | 1.7 | 3.16 | 14 (2008) |
| July | 7.2 | 9 | 1.7 | 3.17 | 13 (1992) |
| August | 6.5 | 9 | 2.1 | 3.36 | 13 (1995) |
| September | 6.1 | 9 | 1.9 | 3.18 | 12 (2011) |
| October | 6.6 | 11 | 1.5 | 2.72 | 12 (2021) |
| November | 6.3 | 9 | 1.5 | 2.55 | 16 (1985) |
| December | 5.6 | 8 | 1.2 | 2.30 | 12 (2008) |
| Year | 78.4 | 19.0 | 33.88 |
Rain day: at least 0.10 in. Plan for: the 90th percentile of 1991-2020 yearly counts, rounded up to a whole day. Record: 1981 to date.
The last 12 months vs normal
From November 2025 through October 2026, Troy had 80 rain days against a normal of 78.3, close to normal overall. 6 of 12 months came in above normal and 6 below. The biggest departure was April 2026, with 14 rain days against a normal of 7.6. Precipitation totaled 32.70 in against 33.88 in normally.
| Month | Rain days | Normal | Difference | Precip (in) | Normal (in) |
|---|---|---|---|---|---|
| Nov 2025 | 4 | 6.3 | -2.3 | 1.30 | 2.55 |
| Dec 2025 | 6 | 5.6 | +0.4 | 2.59 | 2.30 |
| Jan 2026 | 7 | 6.1 | +0.9 | 1.78 | 2.31 |
| Feb 2026 | 2 | 5.0 | -3.0 | 0.87 | 1.97 |
| Mar 2026 | 8 | 5.4 | +2.6 | 3.47 | 2.34 |
| Apr 2026 | 14 | 7.6 | +6.4 | 5.84 | 3.08 |
| May 2026 | 7 | 8.1 | -1.1 | 1.82 | 3.74 |
| Jun 2026 | 10 | 7.8 | +2.2 | 4.94 | 3.16 |
| Jul 2026 | 6 | 7.2 | -1.2 | 1.91 | 3.17 |
| Aug 2026 | 6 | 6.5 | -0.5 | 2.19 | 3.36 |
| Sep 2026 | 8 | 6.1 | +1.9 | 4.10 | 3.18 |
| Oct 2026 | 2 | 6.6 | -4.6 | 1.89 | 2.72 |
Troy rain days month by month
Against the median Michigan location, Troy gets more rain days in June and fewer in October, by half a day or more; other months are within half a day.
Rain days in January
Troy averages 6.1 rain days in January, 1.1 of them heavy, with 2.31 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 12 (2005). January 2026 had 7, 0.9 above normal.
Rain days in February
Troy averages 5.0 rain days in February, 0.9 of them heavy, with 1.97 in of precipitation. Plan for 7 to cover 9 years in 10; the record is 10 (2008). February 2026 had 2, 3.0 below normal.
Rain days in March
Troy averages 5.4 rain days in March, 1.3 of them heavy, with 2.34 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 10 (2023). March 2026 had 8, 2.6 above normal.
Rain days in April
Troy averages 7.6 rain days in April, 1.8 of them heavy, with 3.08 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 14 (2026). April 2026 had 14, 6.4 above normal.
Rain days in May
Troy averages 8.1 rain days in May, 2.1 of them heavy, with 3.74 in of precipitation. Plan for 12 to cover 9 years in 10; the record is 13 (2011). May 2026 had 7, 1.1 below normal.
Rain days in June
Troy averages 7.8 rain days in June, 1.7 of them heavy, with 3.16 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 14 (2008). That is 0.5 more than the median Michigan location (7.3). June 2026 had 10, 2.2 above normal.
Rain days in July
Troy averages 7.2 rain days in July, 1.7 of them heavy, with 3.17 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 13 (1992). July 2026 had 6, 1.2 below normal.
Rain days in August
Troy averages 6.5 rain days in August, 2.1 of them heavy, with 3.36 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 13 (1995). August 2026 had 6, 0.5 below normal.
Rain days in September
Troy averages 6.1 rain days in September, 1.9 of them heavy, with 3.18 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 12 (2011). September 2026 had 8, 1.9 above normal.
Rain days in October
Troy averages 6.6 rain days in October, 1.5 of them heavy, with 2.72 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 12 (2021). That is 0.5 fewer than the median Michigan location (7.1). October 2026 had 2, 4.6 below normal.
Rain days in November
Troy averages 6.3 rain days in November, 1.5 of them heavy, with 2.55 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 16 (1985). November 2025 had 4, 2.3 below normal.
Rain days in December
Troy averages 5.6 rain days in December, 1.2 of them heavy, with 2.30 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 12 (2008). December 2025 had 6, right on normal.
Using these numbers in a construction schedule
For Troy, the normal column is the expected count: 78 days over a full year, 50 of them from April through October. Put those days in the schedule as non-work days or float before the job starts, not after it slips.
Average or plan-for? An average is exceeded about half the time. If May work has no float, carry 12 weather days for it rather than 8.1: Troy had that many or fewer in 9 of 10 years from 1991 to 2020. Use the normals across a long job and the plan-for figure only for months on the critical path.
Heavy days. Troy averages 19 days a year with 0.50 in or more, most often in May (2.1). Those are the days most likely to stop earthwork, paving and concrete outright.
Claiming time for abnormal weather. Under AIA A201-2017 §15.1.6.2, a claim for extra time because of adverse weather has to show the conditions were abnormal for the period, could not have been reasonably anticipated, and had an adverse effect on the scheduled work. The normals above show what could be anticipated in Troy; the claim also needs the day-by-day record for your site and dates.
Price a rain-day report for a site in Troy. Enter your dates to see actual rain days against this normal for free. The full PDF ($99) adds the daily record, a month-by-month comparison and a method statement you can attach to a schedule update or claim.
Check rain days near TroyNearby
Troy is in Oakland County, which averages 77 rain days a year across the county. Troy gets 1 more rain days a year than that county-wide average.
The nearest larger city, Detroit (14 mi away), averages 79 rain days a year, about the same as Troy.
Closest other areas in Michigan:
- Clawson, Michigan: 78 rain days / yr, 3 mi
- Birmingham, Michigan: 78 rain days / yr, 5 mi
- Bloomfield Hills, Michigan: 75 rain days / yr, 5 mi
- Royal Oak, Michigan: 78 rain days / yr, 5 mi
- Rochester Hills, Michigan: 77 rain days / yr, 6 mi
- Madison Heights, Michigan: 79 rain days / yr, 6 mi
- Sterling Heights, Michigan: 80 rain days / yr, 6 mi
- Beverly Hills, Michigan: 77 rain days / yr, 6 mi
All Michigan cities and counties
Related guides
- AIA A201 Weather Delay Claims (ยง15.1.6.2): The Three Tests, With Real Numbers
- How Many Weather Days to Put in a Construction Schedule (Normal vs Plan-For)
- How to Document Weather Delays on a Construction Project (Checklist + Daily Log)
Method and source
A rain day is a day with at least 0.10 in (2.54 mm) in PRISM's daily estimate, which covers the 24 hours ending 12:00 UTC. Heavy days use 0.50 in. Normals are 1991-2020 averages. Records run from 1981 to the last complete month. Figures are for the 4 km cell containing the Census point for Troy (42.583882, -83.145533). Data through 2026-11-24; page updated 2026-11-25. How we count rain days.
Source: PRISM Group, Oregon State University, https://prism.oregonstate.edu. These are gridded estimates, not gauge readings; conditions at a particular site can differ.