Rain days in Detroit, Michigan
Detroit averages 79 rain days a year, counting days with at least 0.10 in of precipitation in the PRISM 4 km grid cell that contains it (1991-2020 normals). May is the wettest month at 8.0 rain days and February the driest at 5.3. That is close to the Michigan median of 79.
Quick answers
How many rain days does Detroit get a year?
About 79: that many days in a normal year bring 0.10 in or more of rain or melted snow. That makes Detroit the 174th wettest of 342 Michigan cities and towns.
What is the wettest month in Detroit?
May, with 8.0 rain days in a normal year. To cover 9 years in 10, plan for 13.
What is the driest month?
February, with 5.3 rain days (plan for 7).
How many heavy-rain days does Detroit get?
21 a year with 0.50 in or more, most often in May (2.4).
Why these counts are lower than some weather sites': a rain day here means 0.10 in or more. Counts based on 0.01 in (NOAA's "days with precipitation") or 0.04 in (WeatherSpark) also include drizzle and trace days.
Rain days by month
The wettest three months are April-June, with 23.0 rain days combined; the driest are December-February, with 17.1. May is also the least predictable month, with the widest gap between its average and its plan-for number. The most rain days in a single month since 1981 was 16, in November 1985.
| Month | Normal rain days | Plan for 9 of 10 yrs |
Heavy days ≥ 0.50 in |
Precip (in) | Record (year) |
|---|---|---|---|---|---|
| January | 6.2 | 9 | 1.1 | 2.39 | 13 (2005) |
| February | 5.3 | 7 | 1.1 | 2.25 | 12 (2018) |
| March | 5.7 | 8 | 1.4 | 2.59 | 11 (2023) |
| April | 7.6 | 10 | 1.9 | 3.23 | 13 (2011) |
| May | 8.0 | 13 | 2.4 | 3.78 | 15 (2004) |
| June | 7.4 | 10 | 2.2 | 3.53 | 13 (2008) |
| July | 7.2 | 9 | 2.1 | 3.28 | 11 (2023) |
| August | 6.5 | 10 | 1.9 | 3.50 | 11 (2007) |
| September | 6.6 | 10 | 2.1 | 3.40 | 14 (2011) |
| October | 6.5 | 10 | 1.7 | 2.84 | 12 (2021) |
| November | 6.3 | 9 | 1.6 | 2.66 | 16 (1985) |
| December | 5.6 | 8 | 1.4 | 2.38 | 12 (1990) |
| Year | 78.8 | 21.1 | 35.83 |
Rain day: at least 0.10 in. Plan for: the 90th percentile of 1991-2020 yearly counts, rounded up to a whole day. Record: 1981 to date.
The last 12 months vs normal
From November 2025 through October 2026, Detroit had 76 rain days against a normal of 78.9, close to normal overall. 7 of 12 months came in above normal and 4 below. The biggest departure was February 2026, with 1 rain days against a normal of 5.3. Precipitation totaled 31.18 in against 35.83 in normally.
| Month | Rain days | Normal | Difference | Precip (in) | Normal (in) |
|---|---|---|---|---|---|
| Nov 2025 | 5 | 6.3 | -1.3 | 1.37 | 2.66 |
| Dec 2025 | 6 | 5.6 | +0.4 | 2.15 | 2.38 |
| Jan 2026 | 7 | 6.2 | +0.8 | 1.58 | 2.39 |
| Feb 2026 | 1 | 5.3 | -4.3 | 0.40 | 2.25 |
| Mar 2026 | 7 | 5.7 | +1.3 | 3.53 | 2.59 |
| Apr 2026 | 10 | 7.6 | +2.4 | 4.00 | 3.23 |
| May 2026 | 8 | 8.0 | +0.0 | 2.45 | 3.78 |
| Jun 2026 | 9 | 7.4 | +1.6 | 3.94 | 3.53 |
| Jul 2026 | 3 | 7.2 | -4.2 | 2.45 | 3.28 |
| Aug 2026 | 8 | 6.5 | +1.5 | 2.33 | 3.50 |
| Sep 2026 | 8 | 6.6 | +1.4 | 4.53 | 3.40 |
| Oct 2026 | 4 | 6.5 | -2.5 | 2.45 | 2.84 |
Detroit rain days month by month
Against the median Michigan location, Detroit gets fewer in October, by half a day or more; other months are within half a day.
Rain days in January
Detroit averages 6.2 rain days in January, 1.1 of them heavy, with 2.39 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 13 (2005). January 2026 had 7, 0.8 above normal.
Rain days in February
Detroit averages 5.3 rain days in February, 1.1 of them heavy, with 2.25 in of precipitation. Plan for 7 to cover 9 years in 10; the record is 12 (2018). February 2026 had 1, 4.3 below normal.
Rain days in March
Detroit averages 5.7 rain days in March, 1.4 of them heavy, with 2.59 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 11 (2023). March 2026 had 7, 1.3 above normal.
Rain days in April
Detroit averages 7.6 rain days in April, 1.9 of them heavy, with 3.23 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 13 (2011). April 2026 had 10, 2.4 above normal.
Rain days in May
Detroit averages 8.0 rain days in May, 2.4 of them heavy, with 3.78 in of precipitation. Plan for 13 to cover 9 years in 10; the record is 15 (2004). May 2026 had 8, right on normal.
Rain days in June
Detroit averages 7.4 rain days in June, 2.2 of them heavy, with 3.53 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 13 (2008). June 2026 had 9, 1.6 above normal.
Rain days in July
Detroit averages 7.2 rain days in July, 2.1 of them heavy, with 3.28 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 11 (2023). July 2026 had 3, 4.2 below normal.
Rain days in August
Detroit averages 6.5 rain days in August, 1.9 of them heavy, with 3.50 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 11 (2007). August 2026 had 8, 1.5 above normal.
Rain days in September
Detroit averages 6.6 rain days in September, 2.1 of them heavy, with 3.40 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 14 (2011). September 2026 had 8, 1.4 above normal.
Rain days in October
Detroit averages 6.5 rain days in October, 1.7 of them heavy, with 2.84 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 12 (2021). That is 0.6 fewer than the median Michigan location (7.1). October 2026 had 4, 2.5 below normal.
Rain days in November
Detroit averages 6.3 rain days in November, 1.6 of them heavy, with 2.66 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 16 (1985). November 2025 had 5, 1.3 below normal.
Rain days in December
Detroit averages 5.6 rain days in December, 1.4 of them heavy, with 2.38 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 12 (1990). December 2025 had 6, right on normal.
Using these numbers in a construction schedule
For Detroit, the normal column is the expected count: 79 days over a full year, 50 of them from April through October. Put those days in the schedule as non-work days or float before the job starts, not after it slips.
Average or plan-for? An average is exceeded about half the time. If May work has no float, carry 13 weather days for it rather than 8.0: Detroit had that many or fewer in 9 of 10 years from 1991 to 2020. Use the normals across a long job and the plan-for figure only for months on the critical path.
Heavy days. Detroit averages 21 days a year with 0.50 in or more, most often in May (2.4). Those are the days most likely to stop earthwork, paving and concrete outright.
Claiming time for abnormal weather. Under AIA A201-2017 §15.1.6.2, a claim for extra time because of adverse weather has to show the conditions were abnormal for the period, could not have been reasonably anticipated, and had an adverse effect on the scheduled work. The normals above show what could be anticipated in Detroit; the claim also needs the day-by-day record for your site and dates.
Price a rain-day report for a site in Detroit. Enter your dates to see actual rain days against this normal for free. The full PDF ($99) adds the daily record, a month-by-month comparison and a method statement you can attach to a schedule update or claim.
Check rain days near DetroitNearby
Detroit is in Wayne County, which averages 78 rain days a year across the county. The two numbers are close but measure different things: the county figure averages all 98 of the county's grid cells, while Detroit's is the single 4 km cell at its Census point. A site elsewhere in Wayne County can differ from both.
Closest other areas in Michigan:
- Highland Park, Michigan: 79 rain days / yr, 2 mi
- Hamtramck, Michigan: 79 rain days / yr, 3 mi
- Hazel Park, Michigan: 79 rain days / yr, 5 mi
- Ferndale, Michigan: 78 rain days / yr, 5 mi
- Oak Park, Michigan: 78 rain days / yr, 7 mi
- Dearborn, Michigan: 76 rain days / yr, 7 mi
- River Rouge, Michigan: 80 rain days / yr, 8 mi
- Melvindale, Michigan: 78 rain days / yr, 8 mi
All Michigan cities and counties
Related guides
- AIA A201 Weather Delay Claims (ยง15.1.6.2): The Three Tests, With Real Numbers
- How Many Weather Days to Put in a Construction Schedule (Normal vs Plan-For)
- How to Document Weather Delays on a Construction Project (Checklist + Daily Log)
Method and source
A rain day is a day with at least 0.10 in (2.54 mm) in PRISM's daily estimate, which covers the 24 hours ending 12:00 UTC. Heavy days use 0.50 in. Normals are 1991-2020 averages. Records run from 1981 to the last complete month. Figures are for the 4 km cell containing the Census point for Detroit (42.383037, -83.102237). Data through 2026-11-24; page updated 2026-11-25. How we count rain days.
Source: PRISM Group, Oregon State University, https://prism.oregonstate.edu. These are gridded estimates, not gauge readings; conditions at a particular site can differ.