Rain days in South Gate, California
South Gate averages 25 rain days a year, counting days with at least 0.10 in of precipitation in the PRISM 4 km grid cell that contains it (1991-2020 normals). February is the wettest month at 5.6 rain days and August the driest at 0.0. That is 6 fewer than the median California location (32).
Quick answers
How many rain days does South Gate get a year?
About 25: that many days in a normal year bring 0.10 in or more of rain or melted snow. That makes South Gate the 311th wettest of 449 California cities and towns.
What is the wettest month in South Gate?
February, with 5.6 rain days in a normal year. To cover 9 years in 10, plan for 10.
What is the driest month?
August, with 0.0 rain days (plan for 0).
How many heavy-rain days does South Gate get?
9 a year with 0.50 in or more, most often in January (2.4).
Why these counts are lower than some weather sites': a rain day here means 0.10 in or more. Counts based on 0.01 in (NOAA's "days with precipitation") or 0.04 in (WeatherSpark) also include drizzle and trace days.
Rain days by month
The wettest three months are January-March, with 15.0 rain days combined; the driest are July-September, with 0.3. January swings the most from year to year: it averages 5.2 rain days, but covering 9 years in 10 takes 13. The most rain days in a single month since 1981 was 17, in February 1998.
| Month | Normal rain days | Plan for 9 of 10 yrs |
Heavy days ≥ 0.50 in |
Precip (in) | Record (year) |
|---|---|---|---|---|---|
| January | 5.2 | 13 | 2.4 | 3.11 | 15 (1993) |
| February | 5.6 | 10 | 2.3 | 3.35 | 17 (1998) |
| March | 4.2 | 7 | 1.4 | 2.17 | 14 (1983) |
| April | 1.8 | 5 | 0.5 | 0.76 | 8 (1983) |
| May | 0.8 | 2 | 0.1 | 0.28 | 6 (1998) |
| June | 0.3 | 0 | 0.0 | 0.08 | 3 (1999) |
| July | 0.1 | 0 | 0.0 | 0.03 | 2 (2015) |
| August | 0.0 | 0 | 0.0 | 0.00 | 3 (1983) |
| September | 0.2 | 1 | 0.1 | 0.08 | 3 (1982) |
| October | 1.1 | 2 | 0.2 | 0.46 | 8 (2004) |
| November | 2.0 | 4 | 0.4 | 0.78 | 8 (1983) |
| December | 4.0 | 7 | 1.5 | 2.32 | 12 (1984) |
| Year | 25.4 | 9.0 | 13.43 |
Rain day: at least 0.10 in. Plan for: the 90th percentile of 1991-2020 yearly counts, rounded up to a whole day. Record: 1981 to date.
The last 12 months vs normal
From November 2025 through October 2026, South Gate had 25 rain days against a normal of 25.3, close to normal overall. 4 of 12 months came in above normal and 6 below. The biggest departure was March 2026, with 0 rain days against a normal of 4.2. Precipitation totaled 16.94 in against 13.42 in normally.
| Month | Rain days | Normal | Difference | Precip (in) | Normal (in) |
|---|---|---|---|---|---|
| Nov 2025 | 6 | 2.0 | +4.0 | 5.29 | 0.78 |
| Dec 2025 | 4 | 4.0 | +0.0 | 3.63 | 2.32 |
| Jan 2026 | 5 | 5.2 | -0.2 | 2.45 | 3.11 |
| Feb 2026 | 5 | 5.6 | -0.6 | 3.54 | 3.35 |
| Mar 2026 | 0 | 4.2 | -4.2 | 0.00 | 2.17 |
| Apr 2026 | 2 | 1.8 | +0.2 | 0.59 | 0.76 |
| May 2026 | 0 | 0.8 | -0.8 | 0.07 | 0.28 |
| Jun 2026 | 0 | 0.3 | -0.3 | 0.00 | 0.08 |
| Jul 2026 | 0 | 0.1 | -0.1 | 0.00 | 0.03 |
| Aug 2026 | 0 | 0.0 | +0.0 | 0.00 | 0.00 |
| Sep 2026 | 1 | 0.2 | +0.8 | 0.59 | 0.08 |
| Oct 2026 | 2 | 1.1 | +0.9 | 0.78 | 0.46 |
South Gate rain days month by month
Against the median California location, South Gate gets fewer in January, February, March, April, May, November and December, by half a day or more; other months are within half a day.
Rain days in January
South Gate averages 5.2 rain days in January, 2.4 of them heavy, with 3.11 in of precipitation. Plan for 13 to cover 9 years in 10; the record is 15 (1993). That is 0.8 fewer than the median California location (6.0). January 2026 had 5, right on normal.
Rain days in February
South Gate averages 5.6 rain days in February, 2.3 of them heavy, with 3.35 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 17 (1998). That is 0.7 fewer than the median California location (6.3). February 2026 had 5, 0.6 below normal.
Rain days in March
South Gate averages 4.2 rain days in March, 1.4 of them heavy, with 2.17 in of precipitation. Plan for 7 to cover 9 years in 10; the record is 14 (1983). That is 0.8 fewer than the median California location (5.0). March 2026 had 0, 4.2 below normal.
Rain days in April
South Gate averages 1.8 rain days in April, 0.5 of them heavy, with 0.76 in of precipitation. Plan for 5 to cover 9 years in 10; the record is 8 (1983). That is 1.0 fewer than the median California location (2.8). April 2026 had 2, right on normal.
Rain days in May
South Gate averages 0.8 rain days in May, 0.1 of them heavy, with 0.28 in of precipitation. Plan for 2 to cover 9 years in 10; the record is 6 (1998). That is 0.6 fewer than the median California location (1.4). May 2026 had 0, 0.8 below normal.
Rain days in June
South Gate averages 0.3 rain days in June, 0.0 of them heavy, with 0.08 in of precipitation. Plan for 0 to cover 9 years in 10; the record is 3 (1999). June 2026 had 0, right on normal.
Rain days in July
South Gate averages 0.1 rain days in July, 0.0 of them heavy, with 0.03 in of precipitation. Plan for 0 to cover 9 years in 10; the record is 2 (2015). July 2026 had 0, right on normal.
Rain days in August
South Gate averages 0.0 rain days in August, 0.0 of them heavy, with 0.00 in of precipitation. Plan for 0 to cover 9 years in 10; the record is 3 (1983). August 2026 had 0, right on normal.
Rain days in September
South Gate averages 0.2 rain days in September, 0.1 of them heavy, with 0.08 in of precipitation. Plan for 1 to cover 9 years in 10; the record is 3 (1982). September 2026 had 1, 0.8 above normal.
Rain days in October
South Gate averages 1.1 rain days in October, 0.2 of them heavy, with 0.46 in of precipitation. Plan for 2 to cover 9 years in 10; the record is 8 (2004). October 2026 had 2, 0.9 above normal.
Rain days in November
South Gate averages 2.0 rain days in November, 0.4 of them heavy, with 0.78 in of precipitation. Plan for 4 to cover 9 years in 10; the record is 8 (1983). That is 0.7 fewer than the median California location (2.7). November 2025 had 6, 4.0 above normal.
Rain days in December
South Gate averages 4.0 rain days in December, 1.5 of them heavy, with 2.32 in of precipitation. Plan for 7 to cover 9 years in 10; the record is 12 (1984). That is 0.9 fewer than the median California location (4.9). December 2025 had 4, right on normal.
Using these numbers in a construction schedule
For South Gate, the normal column is the expected count: 25 days over a full year, 4 of them from April through October. Put those days in the schedule as non-work days or float before the job starts, not after it slips.
Average or plan-for? An average is exceeded about half the time. If February work has no float, carry 10 weather days for it rather than 5.6: South Gate had that many or fewer in 9 of 10 years from 1991 to 2020. Use the normals across a long job and the plan-for figure only for months on the critical path.
Heavy days. South Gate averages 9 days a year with 0.50 in or more, most often in January (2.4). Those are the days most likely to stop earthwork, paving and concrete outright.
Claiming time for abnormal weather. Under AIA A201-2017 §15.1.6.2, a claim for extra time because of adverse weather has to show the conditions were abnormal for the period, could not have been reasonably anticipated, and had an adverse effect on the scheduled work. The normals above show what could be anticipated in South Gate; the claim also needs the day-by-day record for your site and dates.
Price a rain-day report for a site in South Gate. Enter your dates to see actual rain days against this normal for free. The full PDF ($99) adds the daily record, a month-by-month comparison and a method statement you can attach to a schedule update or claim.
Check rain days near South GateNearby
South Gate is in Los Angeles County, which averages 26 rain days a year across the county. The two numbers are close but measure different things: the county figure averages all 595 of the county's grid cells, while South Gate's is the single 4 km cell at its Census point. A site elsewhere in Los Angeles County can differ from both.
The nearest larger city, Long Beach (11 mi away), averages 24 rain days a year: South Gate gets 1 more.
Closest other areas in California:
- Lynwood, California: 24 rain days / yr, 1 mi
- Bell, California: 26 rain days / yr, 3 mi
- Bell Gardens, California: 23 rain days / yr, 3 mi
- Huntington Park, California: 27 rain days / yr, 3 mi
- Paramount, California: 23 rain days / yr, 3 mi
- Downey, California: 23 rain days / yr, 4 mi
- Compton, California: 25 rain days / yr, 4 mi
- Bellflower, California: 24 rain days / yr, 5 mi
All California cities and counties
Related guides
- AIA A201 Weather Delay Claims (ยง15.1.6.2): The Three Tests, With Real Numbers
- How Many Weather Days to Put in a Construction Schedule (Normal vs Plan-For)
- How to Document Weather Delays on a Construction Project (Checklist + Daily Log)
Method and source
A rain day is a day with at least 0.10 in (2.54 mm) in PRISM's daily estimate, which covers the 24 hours ending 12:00 UTC. Heavy days use 0.50 in. Normals are 1991-2020 averages. Records run from 1981 to the last complete month. Figures are for the 4 km cell containing the Census point for South Gate (33.944159, -118.192761). Data through 2026-11-24; page updated 2026-11-25. How we count rain days.
Source: PRISM Group, Oregon State University, https://prism.oregonstate.edu. These are gridded estimates, not gauge readings; conditions at a particular site can differ.