Rain days in Clinton, Tennessee
Clinton averages 96 rain days a year, counting days with at least 0.10 in of precipitation in the PRISM 4 km grid cell that contains it (1991-2020 normals). July is the wettest month at 10.0 rain days and October the driest at 5.4. That is 4 more than the median Tennessee location (92).
Quick answers
How many rain days does Clinton get a year?
About 96: that many days in a normal year bring 0.10 in or more of rain or melted snow. That makes Clinton the 52nd wettest of 231 Tennessee cities and towns.
What is the wettest month in Clinton?
July, with 10.0 rain days in a normal year. To cover 9 years in 10, plan for 13.
What is the driest month?
October, with 5.4 rain days (plan for 9).
How many heavy-rain days does Clinton get?
37 a year with 0.50 in or more, most often in December (4.0).
Why these counts are lower than some weather sites': a rain day here means 0.10 in or more. Counts based on 0.01 in (NOAA's "days with precipitation") or 0.04 in (WeatherSpark) also include drizzle and trace days.
Rain days by month
The wettest three months are May-July, with 28.4 rain days combined; the driest are September-November, with 18.2. August swings the most from year to year: it averages 7.4 rain days, but covering 9 years in 10 takes 12. The most rain days in a single month since 1981 was 18, in July 2005.
| Month | Normal rain days | Plan for 9 of 10 yrs |
Heavy days ≥ 0.50 in |
Precip (in) | Record (year) |
|---|---|---|---|---|---|
| January | 8.3 | 11 | 3.9 | 5.32 | 13 (2017) |
| February | 8.0 | 10 | 3.4 | 5.24 | 17 (2018) |
| March | 8.8 | 12 | 3.7 | 5.16 | 13 (2020) |
| April | 8.2 | 11 | 3.4 | 5.23 | 13 (1984) |
| May | 9.1 | 12 | 2.8 | 4.43 | 16 (2003) |
| June | 9.3 | 12 | 2.9 | 4.64 | 16 (1989) |
| July | 10.0 | 13 | 3.3 | 5.12 | 18 (2005) |
| August | 7.4 | 12 | 2.4 | 3.46 | 13 (2020) |
| September | 6.1 | 9 | 2.4 | 4.06 | 12 (2018) |
| October | 5.4 | 9 | 1.9 | 3.04 | 11 (2021) |
| November | 6.7 | 10 | 3.2 | 4.33 | 13 (1985) |
| December | 8.4 | 11 | 4.0 | 5.61 | 15 (1990) |
| Year | 95.7 | 37.3 | 55.64 |
Rain day: at least 0.10 in. Plan for: the 90th percentile of 1991-2020 yearly counts, rounded up to a whole day. Record: 1981 to date.
The last 12 months vs normal
From November 2025 through October 2026, Clinton had 77 rain days against a normal of 95.7: a dry stretch, 18.7 days below normal. 2 of 12 months came in above normal and 10 below. The biggest departure was January 2026, with 4 rain days against a normal of 8.3. Precipitation totaled 49.38 in against 55.64 in normally.
| Month | Rain days | Normal | Difference | Precip (in) | Normal (in) |
|---|---|---|---|---|---|
| Nov 2025 | 6 | 6.7 | -0.7 | 4.26 | 4.33 |
| Dec 2025 | 5 | 8.4 | -3.4 | 2.10 | 5.61 |
| Jan 2026 | 4 | 8.3 | -4.3 | 4.52 | 5.32 |
| Feb 2026 | 7 | 8.0 | -1.0 | 4.72 | 5.24 |
| Mar 2026 | 5 | 8.8 | -3.8 | 3.44 | 5.16 |
| Apr 2026 | 5 | 8.2 | -3.2 | 3.39 | 5.23 |
| May 2026 | 7 | 9.1 | -2.1 | 6.57 | 4.43 |
| Jun 2026 | 5 | 9.3 | -4.3 | 5.57 | 4.64 |
| Jul 2026 | 14 | 10.0 | +4.0 | 6.10 | 5.12 |
| Aug 2026 | 9 | 7.4 | +1.6 | 4.21 | 3.46 |
| Sep 2026 | 6 | 6.1 | -0.1 | 2.47 | 4.06 |
| Oct 2026 | 4 | 5.4 | -1.4 | 2.03 | 3.04 |
Clinton rain days month by month
Against the median Tennessee location, Clinton gets more rain days in June and July, by half a day or more; other months are within half a day.
Rain days in January
Clinton averages 8.3 rain days in January, 3.9 of them heavy, with 5.32 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 13 (2017). January 2026 had 4, 4.3 below normal.
Rain days in February
Clinton averages 8.0 rain days in February, 3.4 of them heavy, with 5.24 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 17 (2018). February 2026 had 7, 1.0 below normal.
Rain days in March
Clinton averages 8.8 rain days in March, 3.7 of them heavy, with 5.16 in of precipitation. Plan for 12 to cover 9 years in 10; the record is 13 (2020). March 2026 had 5, 3.8 below normal.
Rain days in April
Clinton averages 8.2 rain days in April, 3.4 of them heavy, with 5.23 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 13 (1984). April 2026 had 5, 3.2 below normal.
Rain days in May
Clinton averages 9.1 rain days in May, 2.8 of them heavy, with 4.43 in of precipitation. Plan for 12 to cover 9 years in 10; the record is 16 (2003). May 2026 had 7, 2.1 below normal.
Rain days in June
Clinton averages 9.3 rain days in June, 2.9 of them heavy, with 4.64 in of precipitation. Plan for 12 to cover 9 years in 10; the record is 16 (1989). That is 0.6 more than the median Tennessee location (8.7). June 2026 had 5, 4.3 below normal.
Rain days in July
Clinton averages 10.0 rain days in July, 3.3 of them heavy, with 5.12 in of precipitation. Plan for 13 to cover 9 years in 10; the record is 18 (2005). That is 1.1 more than the median Tennessee location (8.9). July 2026 had 14, 4.0 above normal.
Rain days in August
Clinton averages 7.4 rain days in August, 2.4 of them heavy, with 3.46 in of precipitation. Plan for 12 to cover 9 years in 10; the record is 13 (2020). August 2026 had 9, 1.6 above normal.
Rain days in September
Clinton averages 6.1 rain days in September, 2.4 of them heavy, with 4.06 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 12 (2018). September 2026 had 6, right on normal.
Rain days in October
Clinton averages 5.4 rain days in October, 1.9 of them heavy, with 3.04 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 11 (2021). October 2026 had 4, 1.4 below normal.
Rain days in November
Clinton averages 6.7 rain days in November, 3.2 of them heavy, with 4.33 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 13 (1985). November 2025 had 6, 0.7 below normal.
Rain days in December
Clinton averages 8.4 rain days in December, 4.0 of them heavy, with 5.61 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 15 (1990). December 2025 had 5, 3.4 below normal.
Using these numbers in a construction schedule
For Clinton, the normal column is the expected count: 96 days over a full year, 56 of them from April through October. Put those days in the schedule as non-work days or float before the job starts, not after it slips.
Average or plan-for? An average is exceeded about half the time. If July work has no float, carry 13 weather days for it rather than 10.0: Clinton had that many or fewer in 9 of 10 years from 1991 to 2020. Use the normals across a long job and the plan-for figure only for months on the critical path.
Heavy days. Clinton averages 37 days a year with 0.50 in or more, most often in December (4.0). Those are the days most likely to stop earthwork, paving and concrete outright.
Claiming time for abnormal weather. Under AIA A201-2017 §15.1.6.2, a claim for extra time because of adverse weather has to show the conditions were abnormal for the period, could not have been reasonably anticipated, and had an adverse effect on the scheduled work. The normals above show what could be anticipated in Clinton; the claim also needs the day-by-day record for your site and dates.
Price a rain-day report for a site in Clinton. Enter your dates to see actual rain days against this normal for free. The full PDF ($99) adds the daily record, a month-by-month comparison and a method statement you can attach to a schedule update or claim.
Check rain days near ClintonNearby
Clinton is in Anderson County, which averages 100 rain days a year across the county. Clinton gets 4 fewer rain days a year than that county-wide average.
The nearest larger city, Knoxville (13 mi away), averages 91 rain days a year: Clinton gets 5 more.
Closest other areas in Tennessee:
- Anderson County, Tennessee: 100 rain days / yr, 4 mi
- Norris, Tennessee: 93 rain days / yr, 9 mi
- Rocky Top, Tennessee: 99 rain days / yr, 9 mi
- Oliver Springs, Tennessee: 99 rain days / yr, 12 mi
- Oak Ridge, Tennessee: 98 rain days / yr, 13 mi
- Knox County, Tennessee: 94 rain days / yr, 13 mi
- Knoxville, Tennessee: 91 rain days / yr, 13 mi
- Caryville, Tennessee: 101 rain days / yr, 15 mi
All Tennessee cities and counties
Related guides
- AIA A201 Weather Delay Claims (ยง15.1.6.2): The Three Tests, With Real Numbers
- How Many Weather Days to Put in a Construction Schedule (Normal vs Plan-For)
- How to Document Weather Delays on a Construction Project (Checklist + Daily Log)
Method and source
A rain day is a day with at least 0.10 in (2.54 mm) in PRISM's daily estimate, which covers the 24 hours ending 12:00 UTC. Heavy days use 0.50 in. Normals are 1991-2020 averages. Records run from 1981 to the last complete month. Figures are for the 4 km cell containing the Census point for Clinton (36.099501, -84.127857). Data through 2026-11-24; page updated 2026-11-25. How we count rain days.
Source: PRISM Group, Oregon State University, https://prism.oregonstate.edu. These are gridded estimates, not gauge readings; conditions at a particular site can differ.