Rain days in Geronimo, Oklahoma
Geronimo averages 54 rain days a year, counting days with at least 0.10 in of precipitation in the PRISM 4 km grid cell that contains it (1991-2020 normals). May is the wettest month at 6.9 rain days and January the driest at 2.8. That is 6 fewer than the median Oklahoma location (60).
Quick answers
How many rain days does Geronimo get a year?
About 54: that many days in a normal year bring 0.10 in or more of rain or melted snow. That makes Geronimo the 161st wettest of 210 Oklahoma cities and towns.
What is the wettest month in Geronimo?
May, with 6.9 rain days in a normal year. To cover 9 years in 10, plan for 11.
What is the driest month?
January, with 2.8 rain days (plan for 5).
How many heavy-rain days does Geronimo get?
21 a year with 0.50 in or more, most often in May (3.2).
Why these counts are lower than some weather sites': a rain day here means 0.10 in or more. Counts based on 0.01 in (NOAA's "days with precipitation") or 0.04 in (WeatherSpark) also include drizzle and trace days.
Rain days by month
The wettest three months are May-July, with 17.5 rain days combined; the driest are December-February, with 9.5. June swings the most from year to year: it averages 5.9 rain days, but covering 9 years in 10 takes 11. The most rain days in a single month since 1981 was 16, in May 2015.
| Month | Normal rain days | Plan for 9 of 10 yrs |
Heavy days ≥ 0.50 in |
Precip (in) | Record (year) |
|---|---|---|---|---|---|
| January | 2.8 | 5 | 0.8 | 1.31 | 6 (2024) |
| February | 3.5 | 6 | 0.9 | 1.50 | 8 (2004) |
| March | 4.3 | 7 | 1.6 | 2.48 | 9 (2000) |
| April | 4.6 | 7 | 2.0 | 2.84 | 12 (2025) |
| May | 6.9 | 11 | 3.2 | 4.47 | 16 (2015) |
| June | 5.9 | 11 | 2.6 | 3.81 | 16 (2007) |
| July | 4.7 | 8 | 1.6 | 2.59 | 8 (2023) |
| August | 4.5 | 8 | 1.8 | 2.73 | 12 (1996) |
| September | 4.9 | 8 | 2.2 | 3.11 | 14 (1986) |
| October | 4.9 | 10 | 2.1 | 3.10 | 10 (2018) |
| November | 3.6 | 7 | 1.3 | 1.96 | 12 (2004) |
| December | 3.2 | 5 | 1.4 | 1.77 | 9 (1991) |
| Year | 53.8 | 21.4 | 31.69 |
Rain day: at least 0.10 in. Plan for: the 90th percentile of 1991-2020 yearly counts, rounded up to a whole day. Record: 1981 to date.
The last 12 months vs normal
From November 2025 through October 2026, Geronimo had 34 rain days against a normal of 53.8: a dry stretch, 19.8 days below normal. 2 of 12 months came in above normal and 10 below. The biggest departure was March 2026, with 0 rain days against a normal of 4.3. Precipitation totaled 26.55 in against 31.67 in normally.
| Month | Rain days | Normal | Difference | Precip (in) | Normal (in) |
|---|---|---|---|---|---|
| Nov 2025 | 3 | 3.6 | -0.6 | 3.03 | 1.96 |
| Dec 2025 | 0 | 3.2 | -3.2 | 0.07 | 1.77 |
| Jan 2026 | 3 | 2.8 | +0.2 | 1.30 | 1.31 |
| Feb 2026 | 2 | 3.5 | -1.5 | 2.00 | 1.50 |
| Mar 2026 | 0 | 4.3 | -4.3 | 0.12 | 2.48 |
| Apr 2026 | 6 | 4.6 | +1.4 | 5.80 | 2.84 |
| May 2026 | 4 | 6.9 | -2.9 | 2.21 | 4.47 |
| Jun 2026 | 5 | 5.9 | -0.9 | 4.82 | 3.81 |
| Jul 2026 | 3 | 4.7 | -1.7 | 0.85 | 2.59 |
| Aug 2026 | 1 | 4.5 | -3.5 | 0.17 | 2.73 |
| Sep 2026 | 3 | 4.9 | -1.9 | 0.42 | 3.11 |
| Oct 2026 | 4 | 4.9 | -0.9 | 5.76 | 3.10 |
Geronimo rain days month by month
Against the median Oklahoma location, Geronimo gets fewer in March, April, May, June, August and December, by half a day or more; other months are within half a day.
Rain days in January
Geronimo averages 2.8 rain days in January, 0.8 of them heavy, with 1.31 in of precipitation. Plan for 5 to cover 9 years in 10; the record is 6 (2024). January 2026 had 3, right on normal.
Rain days in February
Geronimo averages 3.5 rain days in February, 0.9 of them heavy, with 1.50 in of precipitation. Plan for 6 to cover 9 years in 10; the record is 8 (2004). February 2026 had 2, 1.5 below normal.
Rain days in March
Geronimo averages 4.3 rain days in March, 1.6 of them heavy, with 2.48 in of precipitation. Plan for 7 to cover 9 years in 10; the record is 9 (2000). That is 0.6 fewer than the median Oklahoma location (4.9). March 2026 had 0, 4.3 below normal.
Rain days in April
Geronimo averages 4.6 rain days in April, 2.0 of them heavy, with 2.84 in of precipitation. Plan for 7 to cover 9 years in 10; the record is 12 (2025). That is 1.1 fewer than the median Oklahoma location (5.7). April 2026 had 6, 1.4 above normal.
Rain days in May
Geronimo averages 6.9 rain days in May, 3.2 of them heavy, with 4.47 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 16 (2015). That is 0.7 fewer than the median Oklahoma location (7.6). May 2026 had 4, 2.9 below normal.
Rain days in June
Geronimo averages 5.9 rain days in June, 2.6 of them heavy, with 3.81 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 16 (2007). That is 0.7 fewer than the median Oklahoma location (6.6). June 2026 had 5, 0.9 below normal.
Rain days in July
Geronimo averages 4.7 rain days in July, 1.6 of them heavy, with 2.59 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 8 (2023). July 2026 had 3, 1.7 below normal.
Rain days in August
Geronimo averages 4.5 rain days in August, 1.8 of them heavy, with 2.73 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 12 (1996). That is 0.6 fewer than the median Oklahoma location (5.1). August 2026 had 1, 3.5 below normal.
Rain days in September
Geronimo averages 4.9 rain days in September, 2.2 of them heavy, with 3.11 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 14 (1986). September 2026 had 3, 1.9 below normal.
Rain days in October
Geronimo averages 4.9 rain days in October, 2.1 of them heavy, with 3.10 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 10 (2018). October 2026 had 4, 0.9 below normal.
Rain days in November
Geronimo averages 3.6 rain days in November, 1.3 of them heavy, with 1.96 in of precipitation. Plan for 7 to cover 9 years in 10; the record is 12 (2004). November 2025 had 3, 0.6 below normal.
Rain days in December
Geronimo averages 3.2 rain days in December, 1.4 of them heavy, with 1.77 in of precipitation. Plan for 5 to cover 9 years in 10; the record is 9 (1991). That is 0.5 fewer than the median Oklahoma location (3.7). December 2025 had 0, 3.2 below normal.
Using these numbers in a construction schedule
For Geronimo, the normal column is the expected count: 54 days over a full year, 36 of them from April through October. Put those days in the schedule as non-work days or float before the job starts, not after it slips.
Average or plan-for? An average is exceeded about half the time. If May work has no float, carry 11 weather days for it rather than 6.9: Geronimo had that many or fewer in 9 of 10 years from 1991 to 2020. Use the normals across a long job and the plan-for figure only for months on the critical path.
Heavy days. Geronimo averages 21 days a year with 0.50 in or more, most often in May (3.2). Those are the days most likely to stop earthwork, paving and concrete outright.
Claiming time for abnormal weather. Under AIA A201-2017 §15.1.6.2, a claim for extra time because of adverse weather has to show the conditions were abnormal for the period, could not have been reasonably anticipated, and had an adverse effect on the scheduled work. The normals above show what could be anticipated in Geronimo; the claim also needs the day-by-day record for your site and dates.
Price a rain-day report for a site in Geronimo. Enter your dates to see actual rain days against this normal for free. The full PDF ($99) adds the daily record, a month-by-month comparison and a method statement you can attach to a schedule update or claim.
Check rain days near GeronimoNearby
Geronimo is in Comanche County, which averages 53 rain days a year across the county. Geronimo gets 1 more rain days a year than that county-wide average.
The nearest larger city, Lawton (10 mi away), averages 51 rain days a year: Geronimo gets 3 more.
Closest other areas in Oklahoma:
- Walters, Oklahoma: 50 rain days / yr, 9 mi
- Lawton, Oklahoma: 51 rain days / yr, 10 mi
- Cotton County, Oklahoma: 51 rain days / yr, 13 mi
- Comanche County, Oklahoma: 53 rain days / yr, 13 mi
- Cache, Oklahoma: 54 rain days / yr, 17 mi
- Central High, Oklahoma: 55 rain days / yr, 19 mi
- Elgin, Oklahoma: 53 rain days / yr, 22 mi
- Duncan, Oklahoma: 55 rain days / yr, 24 mi
All Oklahoma cities and counties
Related guides
- AIA A201 Weather Delay Claims (ยง15.1.6.2): The Three Tests, With Real Numbers
- How Many Weather Days to Put in a Construction Schedule (Normal vs Plan-For)
- How to Document Weather Delays on a Construction Project (Checklist + Daily Log)
Method and source
A rain day is a day with at least 0.10 in (2.54 mm) in PRISM's daily estimate, which covers the 24 hours ending 12:00 UTC. Heavy days use 0.50 in. Normals are 1991-2020 averages. Records run from 1981 to the last complete month. Figures are for the 4 km cell containing the Census point for Geronimo (34.4832, -98.388012). Data through 2026-11-24; page updated 2026-11-25. How we count rain days.
Source: PRISM Group, Oregon State University, https://prism.oregonstate.edu. These are gridded estimates, not gauge readings; conditions at a particular site can differ.