Rain days in Rockford, Ohio
Rockford averages 84 rain days a year, counting days with at least 0.10 in of precipitation in the PRISM 4 km grid cell that contains it (1991-2020 normals). May is the wettest month at 9.1 rain days and February the driest at 5.4. That is 4 fewer than the median Ohio location (88).
Quick answers
How many rain days does Rockford get a year?
About 84: that many days in a normal year bring 0.10 in or more of rain or melted snow. That makes Rockford the 406th wettest of 506 Ohio cities and towns.
What is the wettest month in Rockford?
May, with 9.1 rain days in a normal year. To cover 9 years in 10, plan for 13.
What is the driest month?
February, with 5.4 rain days (plan for 8).
How many heavy-rain days does Rockford get?
25 a year with 0.50 in or more, most often in July (3.1).
Why these counts are lower than some weather sites': a rain day here means 0.10 in or more. Counts based on 0.01 in (NOAA's "days with precipitation") or 0.04 in (WeatherSpark) also include drizzle and trace days.
Rain days by month
The wettest three months are April-June, with 26.3 rain days combined; the driest are December-February, with 17.8. May is also the least predictable month, with the widest gap between its average and its plan-for number. The most rain days in a single month since 1981 was 17, in June 2015.
| Month | Normal rain days | Plan for 9 of 10 yrs |
Heavy days ≥ 0.50 in |
Precip (in) | Record (year) |
|---|---|---|---|---|---|
| January | 6.2 | 9 | 1.5 | 2.65 | 11 (2005) |
| February | 5.4 | 8 | 1.0 | 2.18 | 9 (2019) |
| March | 7.1 | 9 | 1.7 | 2.80 | 13 (1982) |
| April | 8.3 | 12 | 2.4 | 3.85 | 14 (1983) |
| May | 9.1 | 13 | 2.9 | 4.53 | 14 (2006) |
| June | 8.9 | 12 | 2.9 | 4.30 | 17 (2015) |
| July | 7.7 | 11 | 3.1 | 4.48 | 13 (1992) |
| August | 6.3 | 9 | 2.7 | 3.85 | 15 (2026) |
| September | 5.8 | 8 | 2.0 | 3.07 | 11 (2011) |
| October | 6.2 | 10 | 1.7 | 2.86 | 12 (2012) |
| November | 6.6 | 9 | 1.9 | 2.98 | 14 (1982) |
| December | 6.2 | 8 | 1.2 | 2.54 | 12 (1990) |
| Year | 83.7 | 25.1 | 40.09 |
Rain day: at least 0.10 in. Plan for: the 90th percentile of 1991-2020 yearly counts, rounded up to a whole day. Record: 1981 to date.
The last 12 months vs normal
From November 2025 through October 2026, Rockford had 89 rain days against a normal of 83.8: a wet stretch, 5.2 days above normal. 4 of 12 months came in above normal and 8 below. The biggest departure was August 2026, with 15 rain days against a normal of 6.3. Precipitation totaled 42.90 in against 40.09 in normally.
| Month | Rain days | Normal | Difference | Precip (in) | Normal (in) |
|---|---|---|---|---|---|
| Nov 2025 | 6 | 6.6 | -0.6 | 1.50 | 2.98 |
| Dec 2025 | 5 | 6.2 | -1.2 | 1.32 | 2.54 |
| Jan 2026 | 4 | 6.2 | -2.2 | 1.13 | 2.65 |
| Feb 2026 | 2 | 5.4 | -3.4 | 0.78 | 2.18 |
| Mar 2026 | 7 | 7.1 | -0.1 | 3.95 | 2.80 |
| Apr 2026 | 13 | 8.3 | +4.7 | 6.62 | 3.85 |
| May 2026 | 9 | 9.1 | -0.1 | 3.94 | 4.53 |
| Jun 2026 | 10 | 8.9 | +1.1 | 4.77 | 4.30 |
| Jul 2026 | 7 | 7.7 | -0.7 | 2.07 | 4.48 |
| Aug 2026 | 15 | 6.3 | +8.7 | 7.90 | 3.85 |
| Sep 2026 | 10 | 5.8 | +4.2 | 8.26 | 3.07 |
| Oct 2026 | 1 | 6.2 | -5.2 | 0.66 | 2.86 |
Rockford rain days month by month
Against the median Ohio location, Rockford gets fewer in January, February and December, by half a day or more; other months are within half a day.
Rain days in January
Rockford averages 6.2 rain days in January, 1.5 of them heavy, with 2.65 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 11 (2005). That is 0.6 fewer than the median Ohio location (6.8). January 2026 had 4, 2.2 below normal.
Rain days in February
Rockford averages 5.4 rain days in February, 1.0 of them heavy, with 2.18 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 9 (2019). That is 0.5 fewer than the median Ohio location (5.9). February 2026 had 2, 3.4 below normal.
Rain days in March
Rockford averages 7.1 rain days in March, 1.7 of them heavy, with 2.80 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 13 (1982). March 2026 had 7, right on normal.
Rain days in April
Rockford averages 8.3 rain days in April, 2.4 of them heavy, with 3.85 in of precipitation. Plan for 12 to cover 9 years in 10; the record is 14 (1983). April 2026 had 13, 4.7 above normal.
Rain days in May
Rockford averages 9.1 rain days in May, 2.9 of them heavy, with 4.53 in of precipitation. Plan for 13 to cover 9 years in 10; the record is 14 (2006). May 2026 had 9, right on normal.
Rain days in June
Rockford averages 8.9 rain days in June, 2.9 of them heavy, with 4.30 in of precipitation. Plan for 12 to cover 9 years in 10; the record is 17 (2015). June 2026 had 10, 1.1 above normal.
Rain days in July
Rockford averages 7.7 rain days in July, 3.1 of them heavy, with 4.48 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 13 (1992). July 2026 had 7, 0.7 below normal.
Rain days in August
Rockford averages 6.3 rain days in August, 2.7 of them heavy, with 3.85 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 15 (2026). August 2026 had 15, 8.7 above normal.
Rain days in September
Rockford averages 5.8 rain days in September, 2.0 of them heavy, with 3.07 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 11 (2011). September 2026 had 10, 4.2 above normal.
Rain days in October
Rockford averages 6.2 rain days in October, 1.7 of them heavy, with 2.86 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 12 (2012). October 2026 had 1, 5.2 below normal.
Rain days in November
Rockford averages 6.6 rain days in November, 1.9 of them heavy, with 2.98 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 14 (1982). November 2025 had 6, 0.6 below normal.
Rain days in December
Rockford averages 6.2 rain days in December, 1.2 of them heavy, with 2.54 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 12 (1990). That is 0.7 fewer than the median Ohio location (6.9). December 2025 had 5, 1.2 below normal.
Using these numbers in a construction schedule
For Rockford, the normal column is the expected count: 84 days over a full year, 52 of them from April through October. Put those days in the schedule as non-work days or float before the job starts, not after it slips.
Average or plan-for? An average is exceeded about half the time. If May work has no float, carry 13 weather days for it rather than 9.1: Rockford had that many or fewer in 9 of 10 years from 1991 to 2020. Use the normals across a long job and the plan-for figure only for months on the critical path.
Heavy days. Rockford averages 25 days a year with 0.50 in or more, most often in July (3.1). Those are the days most likely to stop earthwork, paving and concrete outright.
Claiming time for abnormal weather. Under AIA A201-2017 §15.1.6.2, a claim for extra time because of adverse weather has to show the conditions were abnormal for the period, could not have been reasonably anticipated, and had an adverse effect on the scheduled work. The normals above show what could be anticipated in Rockford; the claim also needs the day-by-day record for your site and dates. With the last 12 months running 5.2 rain days above normal, it is worth pulling that record now.
Price a rain-day report for a site in Rockford. Enter your dates to see actual rain days against this normal for free. The full PDF ($99) adds the daily record, a month-by-month comparison and a method statement you can attach to a schedule update or claim.
Check rain days near RockfordNearby
Rockford is in Mercer County, which averages 83 rain days a year across the county. The two numbers are close but measure different things: the county figure averages all 81 of the county's grid cells, while Rockford's is the single 4 km cell at its Census point. A site elsewhere in Mercer County can differ from both.
The nearest larger city, Dayton (67 mi away), averages 82 rain days a year: Rockford gets 2 more.
Closest other areas in Ohio:
- Celina, Ohio: 78 rain days / yr, 10 mi
- Mercer County, Ohio: 83 rain days / yr, 11 mi
- Van Wert County, Ohio: 81 rain days / yr, 12 mi
- Van Wert, Ohio: 79 rain days / yr, 13 mi
- Coldwater, Ohio: 83 rain days / yr, 14 mi
- Spencerville, Ohio: 88 rain days / yr, 16 mi
- Convoy, Ohio: 81 rain days / yr, 16 mi
- St. Marys, Ohio: 80 rain days / yr, 17 mi
Related guides
- AIA A201 Weather Delay Claims (ยง15.1.6.2): The Three Tests, With Real Numbers
- How Many Weather Days to Put in a Construction Schedule (Normal vs Plan-For)
- How to Document Weather Delays on a Construction Project (Checklist + Daily Log)
Method and source
A rain day is a day with at least 0.10 in (2.54 mm) in PRISM's daily estimate, which covers the 24 hours ending 12:00 UTC. Heavy days use 0.50 in. Normals are 1991-2020 averages. Records run from 1981 to the last complete month. Figures are for the 4 km cell containing the Census point for Rockford (40.691027, -84.649909). Data through 2026-11-24; page updated 2026-11-25. How we count rain days.
Source: PRISM Group, Oregon State University, https://prism.oregonstate.edu. These are gridded estimates, not gauge readings; conditions at a particular site can differ.