Rain days in Vass, North Carolina
Vass averages 82 rain days a year, counting days with at least 0.10 in of precipitation in the PRISM 4 km grid cell that contains it (1991-2020 normals). July is the wettest month at 9.5 rain days and October the driest at 5.0. That is close to the North Carolina median of 84.
Quick answers
How many rain days does Vass get a year?
About 82: that many days in a normal year bring 0.10 in or more of rain or melted snow. That makes Vass the 196th wettest of 330 North Carolina cities and towns.
What is the wettest month in Vass?
July, with 9.5 rain days in a normal year. To cover 9 years in 10, plan for 13.
What is the driest month?
October, with 5.0 rain days (plan for 7).
How many heavy-rain days does Vass get?
32 a year with 0.50 in or more, most often in July (3.8).
Why these counts are lower than some weather sites': a rain day here means 0.10 in or more. Counts based on 0.01 in (NOAA's "days with precipitation") or 0.04 in (WeatherSpark) also include drizzle and trace days.
Rain days by month
The wettest three months are June-August, with 26.0 rain days combined; the driest are September-November, with 16.7. May swings the most from year to year: it averages 6.5 rain days, but covering 9 years in 10 takes 11. The most rain days in a single month since 1981 was 17, in July 2024.
| Month | Normal rain days | Plan for 9 of 10 yrs |
Heavy days ≥ 0.50 in |
Precip (in) | Record (year) |
|---|---|---|---|---|---|
| January | 6.9 | 11 | 2.4 | 3.54 | 12 (2000) |
| February | 6.3 | 9 | 2.0 | 3.14 | 12 (2021) |
| March | 6.9 | 9 | 2.4 | 3.81 | 12 (1989) |
| April | 6.3 | 9 | 2.3 | 3.39 | 12 (1998) |
| May | 6.5 | 11 | 2.4 | 3.45 | 12 (2016) |
| June | 8.1 | 12 | 2.9 | 4.94 | 15 (1995) |
| July | 9.5 | 13 | 3.8 | 5.54 | 17 (2024) |
| August | 8.4 | 11 | 3.3 | 4.80 | 13 (2018) |
| September | 6.4 | 10 | 3.1 | 5.52 | 12 (1999) |
| October | 5.0 | 7 | 2.3 | 3.44 | 9 (2015) |
| November | 5.3 | 8 | 2.3 | 3.45 | 11 (2018) |
| December | 6.7 | 9 | 2.5 | 3.61 | 11 (1997) |
| Year | 82.1 | 31.8 | 48.64 |
Rain day: at least 0.10 in. Plan for: the 90th percentile of 1991-2020 yearly counts, rounded up to a whole day. Record: 1981 to date.
The last 12 months vs normal
From November 2025 through October 2026, Vass had 69 rain days against a normal of 82.3: a dry stretch, 13.3 days below normal. 3 of 12 months came in above normal and 8 below. The biggest departure was April 2026, with 1 rain days against a normal of 6.3. Precipitation totaled 34.77 in against 48.63 in normally.
| Month | Rain days | Normal | Difference | Precip (in) | Normal (in) |
|---|---|---|---|---|---|
| Nov 2025 | 1 | 5.3 | -4.3 | 1.12 | 3.45 |
| Dec 2025 | 5 | 6.7 | -1.7 | 2.07 | 3.61 |
| Jan 2026 | 3 | 6.9 | -3.9 | 1.37 | 3.54 |
| Feb 2026 | 8 | 6.3 | +1.7 | 3.25 | 3.14 |
| Mar 2026 | 5 | 6.9 | -1.9 | 2.00 | 3.81 |
| Apr 2026 | 1 | 6.3 | -5.3 | 0.43 | 3.39 |
| May 2026 | 9 | 6.5 | +2.5 | 5.88 | 3.45 |
| Jun 2026 | 7 | 8.1 | -1.1 | 2.16 | 4.94 |
| Jul 2026 | 11 | 9.5 | +1.5 | 7.13 | 5.54 |
| Aug 2026 | 8 | 8.4 | -0.4 | 4.90 | 4.80 |
| Sep 2026 | 6 | 6.4 | -0.4 | 2.87 | 5.52 |
| Oct 2026 | 5 | 5.0 | +0.0 | 1.59 | 3.44 |
Vass rain days month by month
Against the median North Carolina location, Vass gets fewer in May, by half a day or more; other months are within half a day.
Rain days in January
Vass averages 6.9 rain days in January, 2.4 of them heavy, with 3.54 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 12 (2000). January 2026 had 3, 3.9 below normal.
Rain days in February
Vass averages 6.3 rain days in February, 2.0 of them heavy, with 3.14 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 12 (2021). February 2026 had 8, 1.7 above normal.
Rain days in March
Vass averages 6.9 rain days in March, 2.4 of them heavy, with 3.81 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 12 (1989). March 2026 had 5, 1.9 below normal.
Rain days in April
Vass averages 6.3 rain days in April, 2.3 of them heavy, with 3.39 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 12 (1998). April 2026 had 1, 5.3 below normal.
Rain days in May
Vass averages 6.5 rain days in May, 2.4 of them heavy, with 3.45 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 12 (2016). That is 0.6 fewer than the median North Carolina location (7.1). May 2026 had 9, 2.5 above normal.
Rain days in June
Vass averages 8.1 rain days in June, 2.9 of them heavy, with 4.94 in of precipitation. Plan for 12 to cover 9 years in 10; the record is 15 (1995). June 2026 had 7, 1.1 below normal.
Rain days in July
Vass averages 9.5 rain days in July, 3.8 of them heavy, with 5.54 in of precipitation. Plan for 13 to cover 9 years in 10; the record is 17 (2024). July 2026 had 11, 1.5 above normal.
Rain days in August
Vass averages 8.4 rain days in August, 3.3 of them heavy, with 4.80 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 13 (2018). August 2026 had 8, right on normal.
Rain days in September
Vass averages 6.4 rain days in September, 3.1 of them heavy, with 5.52 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 12 (1999). September 2026 had 6, right on normal.
Rain days in October
Vass averages 5.0 rain days in October, 2.3 of them heavy, with 3.44 in of precipitation. Plan for 7 to cover 9 years in 10; the record is 9 (2015). October 2026 had 5, right on normal.
Rain days in November
Vass averages 5.3 rain days in November, 2.3 of them heavy, with 3.45 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 11 (2018). November 2025 had 1, 4.3 below normal.
Rain days in December
Vass averages 6.7 rain days in December, 2.5 of them heavy, with 3.61 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 11 (1997). December 2025 had 5, 1.7 below normal.
Using these numbers in a construction schedule
For Vass, the normal column is the expected count: 82 days over a full year, 50 of them from April through October. Put those days in the schedule as non-work days or float before the job starts, not after it slips.
Average or plan-for? An average is exceeded about half the time. If July work has no float, carry 13 weather days for it rather than 9.5: Vass had that many or fewer in 9 of 10 years from 1991 to 2020. Use the normals across a long job and the plan-for figure only for months on the critical path.
Heavy days. Vass averages 32 days a year with 0.50 in or more, most often in July (3.8). Those are the days most likely to stop earthwork, paving and concrete outright.
Claiming time for abnormal weather. Under AIA A201-2017 §15.1.6.2, a claim for extra time because of adverse weather has to show the conditions were abnormal for the period, could not have been reasonably anticipated, and had an adverse effect on the scheduled work. The normals above show what could be anticipated in Vass; the claim also needs the day-by-day record for your site and dates.
Price a rain-day report for a site in Vass. Enter your dates to see actual rain days against this normal for free. The full PDF ($99) adds the daily record, a month-by-month comparison and a method statement you can attach to a schedule update or claim.
Check rain days near VassNearby
Vass is in Moore County, which averages 83 rain days a year across the county. Vass gets 1 fewer rain days a year than that county-wide average.
The nearest larger city, Fayetteville (21 mi away), averages 82 rain days a year, about the same as Vass.
Closest other areas in North Carolina:
- Whispering Pines, North Carolina: 79 rain days / yr, 5 mi
- Southern Pines, North Carolina: 82 rain days / yr, 8 mi
- Carthage, North Carolina: 79 rain days / yr, 9 mi
- Pinehurst, North Carolina: 84 rain days / yr, 11 mi
- Aberdeen, North Carolina: 86 rain days / yr, 12 mi
- Moore County, North Carolina: 83 rain days / yr, 12 mi
- Pinebluff, North Carolina: 86 rain days / yr, 15 mi
- Hoke County, North Carolina: 86 rain days / yr, 17 mi
All North Carolina cities and counties
Related guides
- AIA A201 Weather Delay Claims (ยง15.1.6.2): The Three Tests, With Real Numbers
- How Many Weather Days to Put in a Construction Schedule (Normal vs Plan-For)
- How to Document Weather Delays on a Construction Project (Checklist + Daily Log)
Method and source
A rain day is a day with at least 0.10 in (2.54 mm) in PRISM's daily estimate, which covers the 24 hours ending 12:00 UTC. Heavy days use 0.50 in. Normals are 1991-2020 averages. Records run from 1981 to the last complete month. Figures are for the 4 km cell containing the Census point for Vass (35.253875, -79.284645). Data through 2026-11-24; page updated 2026-11-25. How we count rain days.
Source: PRISM Group, Oregon State University, https://prism.oregonstate.edu. These are gridded estimates, not gauge readings; conditions at a particular site can differ.