Rain days in Four Oaks, North Carolina

Four Oaks averages 82 rain days a year, counting days with at least 0.10 in of precipitation in the PRISM 4 km grid cell that contains it (1991-2020 normals). July is the wettest month at 9.0 rain days and October the driest at 4.7. That is close to the North Carolina median of 84.

Quick answers

How many rain days does Four Oaks get a year?

About 82: that many days in a normal year bring 0.10 in or more of rain or melted snow. That makes Four Oaks the 210th wettest of 330 North Carolina cities and towns.

What is the wettest month in Four Oaks?

July, with 9.0 rain days in a normal year. To cover 9 years in 10, plan for 11.

What is the driest month?

October, with 4.7 rain days (plan for 6).

How many heavy-rain days does Four Oaks get?

33 a year with 0.50 in or more, most often in July (4.1).

Why these counts are lower than some weather sites': a rain day here means 0.10 in or more. Counts based on 0.01 in (NOAA's "days with precipitation") or 0.04 in (WeatherSpark) also include drizzle and trace days.

Rain days by month

The wettest three months are June-August, with 24.6 rain days combined; the driest are September-November, with 16.8. February swings the most from year to year: it averages 6.0 rain days, but covering 9 years in 10 takes 10. The most rain days in a single month since 1981 was 19, in June 1995.

051015JanFebMarAprMayJunJulAugSepOctNovDec
Month Normal rain days Plan for
9 of 10 yrs
Heavy days
≥ 0.50 in
Precip (in) Record (year)
January 6.9 9 2.5 3.55 12 (1982)
February 6.0 10 2.0 3.08 13 (2021)
March 6.9 10 2.8 3.95 12 (1989)
April 6.4 10 2.4 3.56 12 (1989)
May 7.2 11 2.7 4.02 14 (1982)
June 7.7 10 3.3 4.55 19 (1995)
July 9.0 11 4.1 5.32 14 (1996)
August 7.9 10 3.7 5.22 14 (2018)
September 6.7 9 3.0 5.70 13 (1999)
October 4.7 6 2.0 3.25 10 (1993)
November 5.4 9 2.2 3.40 10 (2009)
December 6.9 10 2.5 3.54 13 (1997)
Year 81.7 33.2 49.13

Rain day: at least 0.10 in. Plan for: the 90th percentile of 1991-2020 yearly counts, rounded up to a whole day. Record: 1981 to date.

The last 12 months vs normal

From November 2025 through October 2026, Four Oaks had 67 rain days against a normal of 81.7: a dry stretch, 14.7 days below normal. 3 of 12 months came in above normal and 9 below. The biggest departure was January 2026, with 3 rain days against a normal of 6.9. Precipitation totaled 35.57 in against 49.14 in normally.

MonthRain daysNormalDifferencePrecip (in)Normal (in)
Nov 2025 3 5.4 -2.4 1.27 3.40
Dec 2025 5 6.9 -1.9 2.29 3.54
Jan 2026 3 6.9 -3.9 1.65 3.55
Feb 2026 7 6.0 +1.0 3.11 3.08
Mar 2026 3 6.9 -3.9 1.60 3.95
Apr 2026 3 6.4 -3.4 1.30 3.56
May 2026 9 7.2 +1.8 4.65 4.02
Jun 2026 7 7.7 -0.7 2.79 4.55
Jul 2026 11 9.0 +2.0 9.56 5.32
Aug 2026 7 7.9 -0.9 3.10 5.22
Sep 2026 5 6.7 -1.7 3.03 5.70
Oct 2026 4 4.7 -0.7 1.22 3.25

Four Oaks rain days month by month

Every month in Four Oaks is within half a rain day of the median North Carolina location.

Rain days in January

Four Oaks averages 6.9 rain days in January, 2.5 of them heavy, with 3.55 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 12 (1982). January 2026 had 3, 3.9 below normal.

Rain days in February

Four Oaks averages 6.0 rain days in February, 2.0 of them heavy, with 3.08 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 13 (2021). February 2026 had 7, 1.0 above normal.

Rain days in March

Four Oaks averages 6.9 rain days in March, 2.8 of them heavy, with 3.95 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 12 (1989). March 2026 had 3, 3.9 below normal.

Rain days in April

Four Oaks averages 6.4 rain days in April, 2.4 of them heavy, with 3.56 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 12 (1989). April 2026 had 3, 3.4 below normal.

Rain days in May

Four Oaks averages 7.2 rain days in May, 2.7 of them heavy, with 4.02 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 14 (1982). May 2026 had 9, 1.8 above normal.

Rain days in June

Four Oaks averages 7.7 rain days in June, 3.3 of them heavy, with 4.55 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 19 (1995). June 2026 had 7, 0.7 below normal.

Rain days in July

Four Oaks averages 9.0 rain days in July, 4.1 of them heavy, with 5.32 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 14 (1996). July 2026 had 11, 2.0 above normal.

Rain days in August

Four Oaks averages 7.9 rain days in August, 3.7 of them heavy, with 5.22 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 14 (2018). August 2026 had 7, 0.9 below normal.

Rain days in September

Four Oaks averages 6.7 rain days in September, 3.0 of them heavy, with 5.70 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 13 (1999). September 2026 had 5, 1.7 below normal.

Rain days in October

Four Oaks averages 4.7 rain days in October, 2.0 of them heavy, with 3.25 in of precipitation. Plan for 6 to cover 9 years in 10; the record is 10 (1993). October 2026 had 4, 0.7 below normal.

Rain days in November

Four Oaks averages 5.4 rain days in November, 2.2 of them heavy, with 3.40 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 10 (2009). November 2025 had 3, 2.4 below normal.

Rain days in December

Four Oaks averages 6.9 rain days in December, 2.5 of them heavy, with 3.54 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 13 (1997). December 2025 had 5, 1.9 below normal.

Using these numbers in a construction schedule

For Four Oaks, the normal column is the expected count: 82 days over a full year, 50 of them from April through October. Put those days in the schedule as non-work days or float before the job starts, not after it slips.

Average or plan-for? An average is exceeded about half the time. If July work has no float, carry 11 weather days for it rather than 9.0: Four Oaks had that many or fewer in 9 of 10 years from 1991 to 2020. Use the normals across a long job and the plan-for figure only for months on the critical path.

Heavy days. Four Oaks averages 33 days a year with 0.50 in or more, most often in July (4.1). Those are the days most likely to stop earthwork, paving and concrete outright.

Claiming time for abnormal weather. Under AIA A201-2017 §15.1.6.2, a claim for extra time because of adverse weather has to show the conditions were abnormal for the period, could not have been reasonably anticipated, and had an adverse effect on the scheduled work. The normals above show what could be anticipated in Four Oaks; the claim also needs the day-by-day record for your site and dates.

Price a rain-day report for a site in Four Oaks. Enter your dates to see actual rain days against this normal for free. The full PDF ($99) adds the daily record, a month-by-month comparison and a method statement you can attach to a schedule update or claim.

Check rain days near Four Oaks

What the weather delay claim report includes

Nearby

Four Oaks is in Johnston County, which averages 83 rain days a year across the county. The two numbers are close but measure different things: the county figure averages all 119 of the county's grid cells, while Four Oaks's is the single 4 km cell at its Census point. A site elsewhere in Johnston County can differ from both.

The nearest larger city, Holly Springs (28 mi away), averages 80 rain days a year: Four Oaks gets 2 more.

Closest other areas in North Carolina:

All North Carolina cities and counties

Related guides

Method and source

A rain day is a day with at least 0.10 in (2.54 mm) in PRISM's daily estimate, which covers the 24 hours ending 12:00 UTC. Heavy days use 0.50 in. Normals are 1991-2020 averages. Records run from 1981 to the last complete month. Figures are for the 4 km cell containing the Census point for Four Oaks (35.445593, -78.417562). Data through 2026-11-24; page updated 2026-11-25. How we count rain days.

Source: PRISM Group, Oregon State University, https://prism.oregonstate.edu. These are gridded estimates, not gauge readings; conditions at a particular site can differ.