Rain days in Rumson, New Jersey
Rumson averages 81 rain days a year, counting days with at least 0.10 in of precipitation in the PRISM 4 km grid cell that contains it (1991-2020 normals). June is the wettest month at 7.5 rain days and February the driest at 5.7. That is 2 fewer than the median New Jersey location (83).
Quick answers
How many rain days does Rumson get a year?
About 81: that many days in a normal year bring 0.10 in or more of rain or melted snow. That makes Rumson the 196th wettest of 224 New Jersey cities and towns.
What is the wettest month in Rumson?
June, with 7.5 rain days in a normal year. To cover 9 years in 10, plan for 11.
What is the driest month?
February, with 5.7 rain days (plan for 9).
How many heavy-rain days does Rumson get?
32 a year with 0.50 in or more, most often in December (3.4).
Why these counts are lower than some weather sites': a rain day here means 0.10 in or more. Counts based on 0.01 in (NOAA's "days with precipitation") or 0.04 in (WeatherSpark) also include drizzle and trace days.
Rain days by month
The wettest three months are May-July, with 22.1 rain days combined; the driest are September-November, with 17.9. June is also the least predictable month, with the widest gap between its average and its plan-for number. The most rain days in a single month since 1981 was 14, in September 1993.
| Month | Normal rain days | Plan for 9 of 10 yrs |
Heavy days ≥ 0.50 in |
Precip (in) | Record (year) |
|---|---|---|---|---|---|
| January | 6.7 | 9 | 2.5 | 3.73 | 11 (2024) |
| February | 5.7 | 9 | 2.1 | 3.03 | 11 (2010) |
| March | 7.3 | 10 | 3.1 | 4.29 | 13 (1991) |
| April | 7.1 | 10 | 2.5 | 3.88 | 13 (2004) |
| May | 7.4 | 10 | 2.4 | 3.77 | 14 (1984) |
| June | 7.5 | 11 | 2.7 | 4.19 | 13 (2009) |
| July | 7.2 | 10 | 2.8 | 4.15 | 12 (1996) |
| August | 6.6 | 9 | 3.1 | 4.66 | 12 (2023) |
| September | 5.9 | 9 | 2.9 | 3.90 | 14 (1993) |
| October | 6.3 | 9 | 2.7 | 4.13 | 11 (2005) |
| November | 5.7 | 8 | 2.4 | 3.27 | 10 (2014) |
| December | 7.4 | 10 | 3.4 | 4.60 | 12 (1996) |
| Year | 80.6 | 32.5 | 47.59 |
Rain day: at least 0.10 in. Plan for: the 90th percentile of 1991-2020 yearly counts, rounded up to a whole day. Record: 1981 to date.
The last 12 months vs normal
From November 2025 through October 2026, Rumson had 73 rain days against a normal of 80.8: a dry stretch, 7.8 days below normal. 3 of 12 months came in above normal and 9 below. The biggest departure was September 2026, with 11 rain days against a normal of 5.9. Precipitation totaled 49.04 in against 47.60 in normally.
| Month | Rain days | Normal | Difference | Precip (in) | Normal (in) |
|---|---|---|---|---|---|
| Nov 2025 | 6 | 5.7 | +0.3 | 1.94 | 3.27 |
| Dec 2025 | 7 | 7.4 | -0.4 | 3.91 | 4.60 |
| Jan 2026 | 4 | 6.7 | -2.7 | 3.40 | 3.73 |
| Feb 2026 | 4 | 5.7 | -1.7 | 2.42 | 3.03 |
| Mar 2026 | 6 | 7.3 | -1.3 | 2.57 | 4.29 |
| Apr 2026 | 5 | 7.1 | -2.1 | 2.39 | 3.88 |
| May 2026 | 7 | 7.4 | -0.4 | 2.91 | 3.77 |
| Jun 2026 | 4 | 7.5 | -3.5 | 1.54 | 4.19 |
| Jul 2026 | 7 | 7.2 | -0.2 | 7.68 | 4.15 |
| Aug 2026 | 9 | 6.6 | +2.4 | 8.47 | 4.66 |
| Sep 2026 | 11 | 5.9 | +5.1 | 9.35 | 3.90 |
| Oct 2026 | 3 | 6.3 | -3.3 | 2.46 | 4.13 |
Rumson rain days month by month
Against the median New Jersey location, Rumson gets fewer in August, by half a day or more; other months are within half a day.
Rain days in January
Rumson averages 6.7 rain days in January, 2.5 of them heavy, with 3.73 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 11 (2024). January 2026 had 4, 2.7 below normal.
Rain days in February
Rumson averages 5.7 rain days in February, 2.1 of them heavy, with 3.03 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 11 (2010). February 2026 had 4, 1.7 below normal.
Rain days in March
Rumson averages 7.3 rain days in March, 3.1 of them heavy, with 4.29 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 13 (1991). March 2026 had 6, 1.3 below normal.
Rain days in April
Rumson averages 7.1 rain days in April, 2.5 of them heavy, with 3.88 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 13 (2004). April 2026 had 5, 2.1 below normal.
Rain days in May
Rumson averages 7.4 rain days in May, 2.4 of them heavy, with 3.77 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 14 (1984). May 2026 had 7, right on normal.
Rain days in June
Rumson averages 7.5 rain days in June, 2.7 of them heavy, with 4.19 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 13 (2009). June 2026 had 4, 3.5 below normal.
Rain days in July
Rumson averages 7.2 rain days in July, 2.8 of them heavy, with 4.15 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 12 (1996). July 2026 had 7, right on normal.
Rain days in August
Rumson averages 6.6 rain days in August, 3.1 of them heavy, with 4.66 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 12 (2023). That is 0.5 fewer than the median New Jersey location (7.1). August 2026 had 9, 2.4 above normal.
Rain days in September
Rumson averages 5.9 rain days in September, 2.9 of them heavy, with 3.90 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 14 (1993). September 2026 had 11, 5.1 above normal.
Rain days in October
Rumson averages 6.3 rain days in October, 2.7 of them heavy, with 4.13 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 11 (2005). October 2026 had 3, 3.3 below normal.
Rain days in November
Rumson averages 5.7 rain days in November, 2.4 of them heavy, with 3.27 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 10 (2014). November 2025 had 6, right on normal.
Rain days in December
Rumson averages 7.4 rain days in December, 3.4 of them heavy, with 4.60 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 12 (1996). December 2025 had 7, right on normal.
Using these numbers in a construction schedule
For Rumson, the normal column is the expected count: 81 days over a full year, 48 of them from April through October. Put those days in the schedule as non-work days or float before the job starts, not after it slips.
Average or plan-for? An average is exceeded about half the time. If June work has no float, carry 11 weather days for it rather than 7.5: Rumson had that many or fewer in 9 of 10 years from 1991 to 2020. Use the normals across a long job and the plan-for figure only for months on the critical path.
Heavy days. Rumson averages 32 days a year with 0.50 in or more, most often in December (3.4). Those are the days most likely to stop earthwork, paving and concrete outright.
Claiming time for abnormal weather. Under AIA A201-2017 §15.1.6.2, a claim for extra time because of adverse weather has to show the conditions were abnormal for the period, could not have been reasonably anticipated, and had an adverse effect on the scheduled work. The normals above show what could be anticipated in Rumson; the claim also needs the day-by-day record for your site and dates.
Price a rain-day report for a site in Rumson. Enter your dates to see actual rain days against this normal for free. The full PDF ($99) adds the daily record, a month-by-month comparison and a method statement you can attach to a schedule update or claim.
Check rain days near RumsonNearby
Rumson is in Monmouth County, which averages 83 rain days a year across the county. Rumson gets 2 fewer rain days a year than that county-wide average.
The nearest larger city, Perth Amboy (18 mi away), averages 82 rain days a year: Rumson gets 1 fewer.
Closest other areas in New Jersey:
- Fair Haven, New Jersey: 82 rain days / yr, 2 mi
- Little Silver, New Jersey: 81 rain days / yr, 2 mi
- Highlands, New Jersey: 80 rain days / yr, 3 mi
- Oceanport, New Jersey: 80 rain days / yr, 3 mi
- Red Bank, New Jersey: 83 rain days / yr, 3 mi
- Atlantic Highlands, New Jersey: 82 rain days / yr, 4 mi
- Long Branch, New Jersey: 80 rain days / yr, 5 mi
- Eatontown, New Jersey: 80 rain days / yr, 6 mi
All New Jersey cities and counties
Related guides
- AIA A201 Weather Delay Claims (ยง15.1.6.2): The Three Tests, With Real Numbers
- How Many Weather Days to Put in a Construction Schedule (Normal vs Plan-For)
- How to Document Weather Delays on a Construction Project (Checklist + Daily Log)
Method and source
A rain day is a day with at least 0.10 in (2.54 mm) in PRISM's daily estimate, which covers the 24 hours ending 12:00 UTC. Heavy days use 0.50 in. Normals are 1991-2020 averages. Records run from 1981 to the last complete month. Figures are for the 4 km cell containing the Census point for Rumson (40.362067, -74.00451). Data through 2026-11-24; page updated 2026-11-25. How we count rain days.
Source: PRISM Group, Oregon State University, https://prism.oregonstate.edu. These are gridded estimates, not gauge readings; conditions at a particular site can differ.