Rain days in Pemberton, New Jersey
Pemberton averages 82 rain days a year, counting days with at least 0.10 in of precipitation in the PRISM 4 km grid cell that contains it (1991-2020 normals). July is the wettest month at 7.7 rain days and September the driest at 5.8. That is close to the New Jersey median of 83.
Quick answers
How many rain days does Pemberton get a year?
About 82: that many days in a normal year bring 0.10 in or more of rain or melted snow. That makes Pemberton the 151st wettest of 224 New Jersey cities and towns.
What is the wettest month in Pemberton?
July, with 7.7 rain days in a normal year. To cover 9 years in 10, plan for 10.
What is the driest month?
September, with 5.8 rain days (plan for 10).
How many heavy-rain days does Pemberton get?
33 a year with 0.50 in or more, most often in March (3.5).
Why these counts are lower than some weather sites': a rain day here means 0.10 in or more. Counts based on 0.01 in (NOAA's "days with precipitation") or 0.04 in (WeatherSpark) also include drizzle and trace days.
Rain days by month
The wettest three months are May-July, with 22.5 rain days combined; the driest are September-November, with 18.0. June swings the most from year to year: it averages 7.4 rain days, but covering 9 years in 10 takes 13. The most rain days in a single month since 1981 was 15, in June 2009.
| Month | Normal rain days | Plan for 9 of 10 yrs |
Heavy days ≥ 0.50 in |
Precip (in) | Record (year) |
|---|---|---|---|---|---|
| January | 6.7 | 10 | 2.5 | 3.57 | 12 (1996) |
| February | 5.9 | 9 | 2.0 | 2.85 | 12 (2018) |
| March | 7.1 | 10 | 3.5 | 4.31 | 13 (1991) |
| April | 7.3 | 9 | 2.5 | 3.64 | 14 (2009) |
| May | 7.4 | 11 | 2.4 | 3.75 | 12 (2025) |
| June | 7.4 | 13 | 3.0 | 4.35 | 15 (2009) |
| July | 7.7 | 10 | 3.2 | 4.94 | 13 (2013) |
| August | 7.2 | 11 | 3.2 | 5.19 | 13 (2011) |
| September | 5.8 | 10 | 2.4 | 3.80 | 13 (2003) |
| October | 6.2 | 10 | 2.6 | 4.08 | 11 (2006) |
| November | 6.0 | 9 | 2.2 | 3.26 | 11 (1986) |
| December | 7.1 | 10 | 3.3 | 4.34 | 11 (2015) |
| Year | 81.9 | 32.9 | 48.09 |
Rain day: at least 0.10 in. Plan for: the 90th percentile of 1991-2020 yearly counts, rounded up to a whole day. Record: 1981 to date.
The last 12 months vs normal
From November 2025 through October 2026, Pemberton had 81 rain days against a normal of 81.8, close to normal overall. 3 of 12 months came in above normal and 8 below. The biggest departure was September 2026, with 10 rain days against a normal of 5.8. Precipitation totaled 46.12 in against 48.08 in normally.
| Month | Rain days | Normal | Difference | Precip (in) | Normal (in) |
|---|---|---|---|---|---|
| Nov 2025 | 6 | 6.0 | +0.0 | 2.17 | 3.26 |
| Dec 2025 | 7 | 7.1 | -0.1 | 3.89 | 4.34 |
| Jan 2026 | 5 | 6.7 | -1.7 | 3.40 | 3.57 |
| Feb 2026 | 7 | 5.9 | +1.1 | 2.44 | 2.85 |
| Mar 2026 | 7 | 7.1 | -0.1 | 2.65 | 4.31 |
| Apr 2026 | 5 | 7.3 | -2.3 | 2.70 | 3.64 |
| May 2026 | 7 | 7.4 | -0.4 | 2.98 | 3.75 |
| Jun 2026 | 6 | 7.4 | -1.4 | 2.86 | 4.35 |
| Jul 2026 | 10 | 7.7 | +2.3 | 5.73 | 4.94 |
| Aug 2026 | 7 | 7.2 | -0.2 | 5.86 | 5.19 |
| Sep 2026 | 10 | 5.8 | +4.2 | 8.51 | 3.80 |
| Oct 2026 | 4 | 6.2 | -2.2 | 2.93 | 4.08 |
Pemberton rain days month by month
Every month in Pemberton is within half a rain day of the median New Jersey location.
Rain days in January
Pemberton averages 6.7 rain days in January, 2.5 of them heavy, with 3.57 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 12 (1996). January 2026 had 5, 1.7 below normal.
Rain days in February
Pemberton averages 5.9 rain days in February, 2.0 of them heavy, with 2.85 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 12 (2018). February 2026 had 7, 1.1 above normal.
Rain days in March
Pemberton averages 7.1 rain days in March, 3.5 of them heavy, with 4.31 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 13 (1991). March 2026 had 7, right on normal.
Rain days in April
Pemberton averages 7.3 rain days in April, 2.5 of them heavy, with 3.64 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 14 (2009). April 2026 had 5, 2.3 below normal.
Rain days in May
Pemberton averages 7.4 rain days in May, 2.4 of them heavy, with 3.75 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 12 (2025). May 2026 had 7, right on normal.
Rain days in June
Pemberton averages 7.4 rain days in June, 3.0 of them heavy, with 4.35 in of precipitation. Plan for 13 to cover 9 years in 10; the record is 15 (2009). June 2026 had 6, 1.4 below normal.
Rain days in July
Pemberton averages 7.7 rain days in July, 3.2 of them heavy, with 4.94 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 13 (2013). July 2026 had 10, 2.3 above normal.
Rain days in August
Pemberton averages 7.2 rain days in August, 3.2 of them heavy, with 5.19 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 13 (2011). August 2026 had 7, right on normal.
Rain days in September
Pemberton averages 5.8 rain days in September, 2.4 of them heavy, with 3.80 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 13 (2003). September 2026 had 10, 4.2 above normal.
Rain days in October
Pemberton averages 6.2 rain days in October, 2.6 of them heavy, with 4.08 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 11 (2006). October 2026 had 4, 2.2 below normal.
Rain days in November
Pemberton averages 6.0 rain days in November, 2.2 of them heavy, with 3.26 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 11 (1986). November 2025 had 6, right on normal.
Rain days in December
Pemberton averages 7.1 rain days in December, 3.3 of them heavy, with 4.34 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 11 (2015). December 2025 had 7, right on normal.
Using these numbers in a construction schedule
For Pemberton, the normal column is the expected count: 82 days over a full year, 49 of them from April through October. Put those days in the schedule as non-work days or float before the job starts, not after it slips.
Average or plan-for? An average is exceeded about half the time. If July work has no float, carry 10 weather days for it rather than 7.7: Pemberton had that many or fewer in 9 of 10 years from 1991 to 2020. Use the normals across a long job and the plan-for figure only for months on the critical path.
Heavy days. Pemberton averages 33 days a year with 0.50 in or more, most often in March (3.5). Those are the days most likely to stop earthwork, paving and concrete outright.
Claiming time for abnormal weather. Under AIA A201-2017 §15.1.6.2, a claim for extra time because of adverse weather has to show the conditions were abnormal for the period, could not have been reasonably anticipated, and had an adverse effect on the scheduled work. The normals above show what could be anticipated in Pemberton; the claim also needs the day-by-day record for your site and dates.
Price a rain-day report for a site in Pemberton. Enter your dates to see actual rain days against this normal for free. The full PDF ($99) adds the daily record, a month-by-month comparison and a method statement you can attach to a schedule update or claim.
Check rain days near PembertonNearby
Pemberton is in Burlington County, which averages 85 rain days a year across the county. Pemberton gets 3 fewer rain days a year than that county-wide average.
The nearest larger city, Trenton (18 mi away), averages 83 rain days a year: Pemberton gets 1 fewer.
Closest other areas in New Jersey:
- Burlington County, New Jersey: 85 rain days / yr, 7 mi
- Medford Lakes, New Jersey: 84 rain days / yr, 11 mi
- Burlington, New Jersey: 84 rain days / yr, 11 mi
- Bordentown, New Jersey: 84 rain days / yr, 12 mi
- Beverly, New Jersey: 85 rain days / yr, 14 mi
- Allentown, New Jersey: 83 rain days / yr, 15 mi
- Riverton, New Jersey: 85 rain days / yr, 18 mi
- Gibbsboro, New Jersey: 85 rain days / yr, 18 mi
All New Jersey cities and counties
Related guides
- AIA A201 Weather Delay Claims (ยง15.1.6.2): The Three Tests, With Real Numbers
- How Many Weather Days to Put in a Construction Schedule (Normal vs Plan-For)
- How to Document Weather Delays on a Construction Project (Checklist + Daily Log)
Method and source
A rain day is a day with at least 0.10 in (2.54 mm) in PRISM's daily estimate, which covers the 24 hours ending 12:00 UTC. Heavy days use 0.50 in. Normals are 1991-2020 averages. Records run from 1981 to the last complete month. Figures are for the 4 km cell containing the Census point for Pemberton (39.973612, -74.686859). Data through 2026-11-24; page updated 2026-11-25. How we count rain days.
Source: PRISM Group, Oregon State University, https://prism.oregonstate.edu. These are gridded estimates, not gauge readings; conditions at a particular site can differ.