Rain days in Buena, New Jersey
Buena averages 85 rain days a year, counting days with at least 0.10 in of precipitation in the PRISM 4 km grid cell that contains it (1991-2020 normals). January is the wettest month at 7.6 rain days and November the driest at 6.1. That is 2 more than the median New Jersey location (83).
Quick answers
How many rain days does Buena get a year?
About 85: that many days in a normal year bring 0.10 in or more of rain or melted snow. That makes Buena the 31st wettest of 224 New Jersey cities and towns.
What is the wettest month in Buena?
January, with 7.6 rain days in a normal year. To cover 9 years in 10, plan for 10.
What is the driest month?
November, with 6.1 rain days (plan for 8).
How many heavy-rain days does Buena get?
32 a year with 0.50 in or more, most often in March (3.7).
Why these counts are lower than some weather sites': a rain day here means 0.10 in or more. Counts based on 0.01 in (NOAA's "days with precipitation") or 0.04 in (WeatherSpark) also include drizzle and trace days.
Rain days by month
The wettest three months are May-July, with 22.8 rain days combined; the driest are September-November, with 18.8. June swings the most from year to year: it averages 7.6 rain days, but covering 9 years in 10 takes 12. The most rain days in a single month since 1981 was 16, in June 2015.
| Month | Normal rain days | Plan for 9 of 10 yrs |
Heavy days ≥ 0.50 in |
Precip (in) | Record (year) |
|---|---|---|---|---|---|
| January | 7.6 | 10 | 2.5 | 3.60 | 12 (1991) |
| February | 6.5 | 10 | 2.2 | 3.05 | 12 (2021) |
| March | 7.6 | 11 | 3.7 | 4.55 | 14 (1983) |
| April | 7.2 | 9 | 2.3 | 3.56 | 13 (2009) |
| May | 7.6 | 11 | 2.2 | 3.43 | 14 (1996) |
| June | 7.6 | 12 | 2.8 | 4.27 | 16 (2015) |
| July | 7.6 | 10 | 2.9 | 4.57 | 13 (1996) |
| August | 7.1 | 11 | 3.3 | 4.85 | 15 (2020) |
| September | 6.4 | 9 | 2.4 | 4.05 | 11 (2018) |
| October | 6.3 | 8 | 2.6 | 3.98 | 11 (2005) |
| November | 6.1 | 8 | 2.3 | 3.26 | 12 (1986) |
| December | 7.6 | 11 | 3.3 | 4.49 | 12 (2015) |
| Year | 85.2 | 32.5 | 47.65 |
Rain day: at least 0.10 in. Plan for: the 90th percentile of 1991-2020 yearly counts, rounded up to a whole day. Record: 1981 to date.
The last 12 months vs normal
From November 2025 through October 2026, Buena had 79 rain days against a normal of 85.2: a dry stretch, 6.2 days below normal. 5 of 12 months came in above normal and 7 below. The biggest departure was September 2026, with 10 rain days against a normal of 6.4. Precipitation totaled 43.22 in against 47.66 in normally.
| Month | Rain days | Normal | Difference | Precip (in) | Normal (in) |
|---|---|---|---|---|---|
| Nov 2025 | 5 | 6.1 | -1.1 | 1.84 | 3.26 |
| Dec 2025 | 7 | 7.6 | -0.6 | 3.75 | 4.49 |
| Jan 2026 | 5 | 7.6 | -2.6 | 3.73 | 3.60 |
| Feb 2026 | 4 | 6.5 | -2.5 | 2.67 | 3.05 |
| Mar 2026 | 8 | 7.6 | +0.4 | 2.19 | 4.55 |
| Apr 2026 | 4 | 7.2 | -3.2 | 2.35 | 3.56 |
| May 2026 | 9 | 7.6 | +1.4 | 2.62 | 3.43 |
| Jun 2026 | 5 | 7.6 | -2.6 | 1.27 | 4.27 |
| Jul 2026 | 9 | 7.6 | +1.4 | 5.96 | 4.57 |
| Aug 2026 | 10 | 7.1 | +2.9 | 7.20 | 4.85 |
| Sep 2026 | 10 | 6.4 | +3.6 | 6.79 | 4.05 |
| Oct 2026 | 3 | 6.3 | -3.3 | 2.85 | 3.98 |
Buena rain days month by month
Against the median New Jersey location, Buena gets more rain days in January, by half a day or more; other months are within half a day.
Rain days in January
Buena averages 7.6 rain days in January, 2.5 of them heavy, with 3.60 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 12 (1991). That is 0.8 more than the median New Jersey location (6.8). January 2026 had 5, 2.6 below normal.
Rain days in February
Buena averages 6.5 rain days in February, 2.2 of them heavy, with 3.05 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 12 (2021). February 2026 had 4, 2.5 below normal.
Rain days in March
Buena averages 7.6 rain days in March, 3.7 of them heavy, with 4.55 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 14 (1983). March 2026 had 8, right on normal.
Rain days in April
Buena averages 7.2 rain days in April, 2.3 of them heavy, with 3.56 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 13 (2009). April 2026 had 4, 3.2 below normal.
Rain days in May
Buena averages 7.6 rain days in May, 2.2 of them heavy, with 3.43 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 14 (1996). May 2026 had 9, 1.4 above normal.
Rain days in June
Buena averages 7.6 rain days in June, 2.8 of them heavy, with 4.27 in of precipitation. Plan for 12 to cover 9 years in 10; the record is 16 (2015). June 2026 had 5, 2.6 below normal.
Rain days in July
Buena averages 7.6 rain days in July, 2.9 of them heavy, with 4.57 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 13 (1996). July 2026 had 9, 1.4 above normal.
Rain days in August
Buena averages 7.1 rain days in August, 3.3 of them heavy, with 4.85 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 15 (2020). August 2026 had 10, 2.9 above normal.
Rain days in September
Buena averages 6.4 rain days in September, 2.4 of them heavy, with 4.05 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 11 (2018). September 2026 had 10, 3.6 above normal.
Rain days in October
Buena averages 6.3 rain days in October, 2.6 of them heavy, with 3.98 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 11 (2005). October 2026 had 3, 3.3 below normal.
Rain days in November
Buena averages 6.1 rain days in November, 2.3 of them heavy, with 3.26 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 12 (1986). November 2025 had 5, 1.1 below normal.
Rain days in December
Buena averages 7.6 rain days in December, 3.3 of them heavy, with 4.49 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 12 (2015). December 2025 had 7, 0.6 below normal.
Using these numbers in a construction schedule
For Buena, the normal column is the expected count: 85 days over a full year, 50 of them from April through October. Put those days in the schedule as non-work days or float before the job starts, not after it slips.
Average or plan-for? An average is exceeded about half the time. If January work has no float, carry 10 weather days for it rather than 7.6: Buena had that many or fewer in 9 of 10 years from 1991 to 2020. Use the normals across a long job and the plan-for figure only for months on the critical path.
Heavy days. Buena averages 32 days a year with 0.50 in or more, most often in March (3.7). Those are the days most likely to stop earthwork, paving and concrete outright.
Claiming time for abnormal weather. Under AIA A201-2017 §15.1.6.2, a claim for extra time because of adverse weather has to show the conditions were abnormal for the period, could not have been reasonably anticipated, and had an adverse effect on the scheduled work. The normals above show what could be anticipated in Buena; the claim also needs the day-by-day record for your site and dates.
Price a rain-day report for a site in Buena. Enter your dates to see actual rain days against this normal for free. The full PDF ($99) adds the daily record, a month-by-month comparison and a method statement you can attach to a schedule update or claim.
Check rain days near BuenaNearby
Buena is in Gloucester County, which averages 84 rain days a year across the county. Buena gets 2 more rain days a year than that county-wide average.
The nearest larger city, Vineland (5 mi away), averages 84 rain days a year: Buena gets 1 more.
Closest other areas in New Jersey:
- Newfield, New Jersey: 85 rain days / yr, 4 mi
- Vineland, New Jersey: 84 rain days / yr, 5 mi
- Folsom, New Jersey: 86 rain days / yr, 7 mi
- Millville, New Jersey: 84 rain days / yr, 11 mi
- Clayton, New Jersey: 82 rain days / yr, 12 mi
- Elmer, New Jersey: 82 rain days / yr, 13 mi
- Hammonton, New Jersey: 86 rain days / yr, 13 mi
- Chesilhurst, New Jersey: 86 rain days / yr, 14 mi
All New Jersey cities and counties
Related guides
- AIA A201 Weather Delay Claims (ยง15.1.6.2): The Three Tests, With Real Numbers
- How Many Weather Days to Put in a Construction Schedule (Normal vs Plan-For)
- How to Document Weather Delays on a Construction Project (Checklist + Daily Log)
Method and source
A rain day is a day with at least 0.10 in (2.54 mm) in PRISM's daily estimate, which covers the 24 hours ending 12:00 UTC. Heavy days use 0.50 in. Normals are 1991-2020 averages. Records run from 1981 to the last complete month. Figures are for the 4 km cell containing the Census point for Buena (39.52917, -74.945204). Data through 2026-11-24; page updated 2026-11-25. How we count rain days.
Source: PRISM Group, Oregon State University, https://prism.oregonstate.edu. These are gridded estimates, not gauge readings; conditions at a particular site can differ.