Rain days in Carencro, Louisiana
Carencro averages 85 rain days a year, counting days with at least 0.10 in of precipitation in the PRISM 4 km grid cell that contains it (1991-2020 normals). July is the wettest month at 10.5 rain days and October the driest at 5.1. That is close to the Louisiana median of 85.
Quick answers
How many rain days does Carencro get a year?
About 85: that many days in a normal year bring 0.10 in or more of rain or melted snow. That makes Carencro the 74th wettest of 156 Louisiana cities and towns.
What is the wettest month in Carencro?
July, with 10.5 rain days in a normal year. To cover 9 years in 10, plan for 14.
What is the driest month?
October, with 5.1 rain days (plan for 9).
How many heavy-rain days does Carencro get?
41 a year with 0.50 in or more, most often in June (4.4).
Why these counts are lower than some weather sites': a rain day here means 0.10 in or more. Counts based on 0.01 in (NOAA's "days with precipitation") or 0.04 in (WeatherSpark) also include drizzle and trace days.
Rain days by month
The wettest three months are June-August, with 29.6 rain days combined; the driest are March-May, with 17.1. June swings the most from year to year: it averages 10.1 rain days, but covering 9 years in 10 takes 15. The most rain days in a single month since 1981 was 19, in July 2012.
| Month | Normal rain days | Plan for 9 of 10 yrs |
Heavy days ≥ 0.50 in |
Precip (in) | Record (year) |
|---|---|---|---|---|---|
| January | 7.8 | 11 | 4.1 | 6.74 | 12 (2020) |
| February | 6.3 | 9 | 3.2 | 4.63 | 12 (1988) |
| March | 5.6 | 8 | 2.6 | 4.44 | 12 (2001) |
| April | 5.3 | 9 | 3.2 | 5.15 | 12 (2015) |
| May | 6.2 | 10 | 3.3 | 5.87 | 17 (1991) |
| June | 10.1 | 15 | 4.4 | 6.85 | 17 (2017) |
| July | 10.5 | 14 | 3.7 | 5.88 | 19 (2012) |
| August | 9.0 | 13 | 3.4 | 5.61 | 15 (2022) |
| September | 6.9 | 9 | 3.2 | 5.36 | 16 (2018) |
| October | 5.1 | 9 | 2.7 | 5.01 | 15 (2002) |
| November | 5.5 | 8 | 3.2 | 4.82 | 12 (2004) |
| December | 6.7 | 9 | 3.5 | 5.19 | 12 (2009) |
| Year | 85.1 | 40.7 | 65.53 |
Rain day: at least 0.10 in. Plan for: the 90th percentile of 1991-2020 yearly counts, rounded up to a whole day. Record: 1981 to date.
The last 12 months vs normal
From November 2025 through October 2026, Carencro had 77 rain days against a normal of 85: a dry stretch, 8 days below normal. 4 of 12 months came in above normal and 8 below. The biggest departure was May 2026, with 13 rain days against a normal of 6.2. Precipitation totaled 55.82 in against 65.55 in normally.
| Month | Rain days | Normal | Difference | Precip (in) | Normal (in) |
|---|---|---|---|---|---|
| Nov 2025 | 1 | 5.5 | -4.5 | 0.47 | 4.82 |
| Dec 2025 | 8 | 6.7 | +1.3 | 5.67 | 5.19 |
| Jan 2026 | 5 | 7.8 | -2.8 | 5.27 | 6.74 |
| Feb 2026 | 2 | 6.3 | -4.3 | 2.41 | 4.63 |
| Mar 2026 | 4 | 5.6 | -1.6 | 5.69 | 4.44 |
| Apr 2026 | 4 | 5.3 | -1.3 | 2.73 | 5.15 |
| May 2026 | 13 | 6.2 | +6.8 | 14.46 | 5.87 |
| Jun 2026 | 12 | 10.1 | +1.9 | 6.45 | 6.85 |
| Jul 2026 | 10 | 10.5 | -0.5 | 6.59 | 5.88 |
| Aug 2026 | 6 | 9.0 | -3.0 | 2.13 | 5.61 |
| Sep 2026 | 8 | 6.9 | +1.1 | 2.20 | 5.36 |
| Oct 2026 | 4 | 5.1 | -1.1 | 1.75 | 5.01 |
Carencro rain days month by month
Against the median Louisiana location, Carencro gets more rain days in June and fewer in March and April, by half a day or more; other months are within half a day.
Rain days in January
Carencro averages 7.8 rain days in January, 4.1 of them heavy, with 6.74 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 12 (2020). January 2026 had 5, 2.8 below normal.
Rain days in February
Carencro averages 6.3 rain days in February, 3.2 of them heavy, with 4.63 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 12 (1988). February 2026 had 2, 4.3 below normal.
Rain days in March
Carencro averages 5.6 rain days in March, 2.6 of them heavy, with 4.44 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 12 (2001). That is 0.7 fewer than the median Louisiana location (6.2). March 2026 had 4, 1.6 below normal.
Rain days in April
Carencro averages 5.3 rain days in April, 3.2 of them heavy, with 5.15 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 12 (2015). That is 0.5 fewer than the median Louisiana location (5.8). April 2026 had 4, 1.3 below normal.
Rain days in May
Carencro averages 6.2 rain days in May, 3.3 of them heavy, with 5.87 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 17 (1991). May 2026 had 13, 6.8 above normal.
Rain days in June
Carencro averages 10.1 rain days in June, 4.4 of them heavy, with 6.85 in of precipitation. Plan for 15 to cover 9 years in 10; the record is 17 (2017). That is 0.6 more than the median Louisiana location (9.5). June 2026 had 12, 1.9 above normal.
Rain days in July
Carencro averages 10.5 rain days in July, 3.7 of them heavy, with 5.88 in of precipitation. Plan for 14 to cover 9 years in 10; the record is 19 (2012). July 2026 had 10, 0.5 below normal.
Rain days in August
Carencro averages 9.0 rain days in August, 3.4 of them heavy, with 5.61 in of precipitation. Plan for 13 to cover 9 years in 10; the record is 15 (2022). August 2026 had 6, 3.0 below normal.
Rain days in September
Carencro averages 6.9 rain days in September, 3.2 of them heavy, with 5.36 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 16 (2018). September 2026 had 8, 1.1 above normal.
Rain days in October
Carencro averages 5.1 rain days in October, 2.7 of them heavy, with 5.01 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 15 (2002). October 2026 had 4, 1.1 below normal.
Rain days in November
Carencro averages 5.5 rain days in November, 3.2 of them heavy, with 4.82 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 12 (2004). November 2025 had 1, 4.5 below normal.
Rain days in December
Carencro averages 6.7 rain days in December, 3.5 of them heavy, with 5.19 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 12 (2009). December 2025 had 8, 1.3 above normal.
Using these numbers in a construction schedule
For Carencro, the normal column is the expected count: 85 days over a full year, 53 of them from April through October. Put those days in the schedule as non-work days or float before the job starts, not after it slips.
Average or plan-for? An average is exceeded about half the time. If July work has no float, carry 14 weather days for it rather than 10.5: Carencro had that many or fewer in 9 of 10 years from 1991 to 2020. Use the normals across a long job and the plan-for figure only for months on the critical path.
Heavy days. Carencro averages 41 days a year with 0.50 in or more, most often in June (4.4). Those are the days most likely to stop earthwork, paving and concrete outright.
Claiming time for abnormal weather. Under AIA A201-2017 §15.1.6.2, a claim for extra time because of adverse weather has to show the conditions were abnormal for the period, could not have been reasonably anticipated, and had an adverse effect on the scheduled work. The normals above show what could be anticipated in Carencro; the claim also needs the day-by-day record for your site and dates.
Price a rain-day report for a site in Carencro. Enter your dates to see actual rain days against this normal for free. The full PDF ($99) adds the daily record, a month-by-month comparison and a method statement you can attach to a schedule update or claim.
Check rain days near CarencroNearby
Carencro is in Lafayette Parish, which averages 90 rain days a year across the county. Carencro gets 5 fewer rain days a year than that county-wide average.
The nearest larger city, Lafayette (7 mi away), averages 89 rain days a year: Carencro gets 4 fewer.
Closest other areas in Louisiana:
- Scott, Louisiana: 89 rain days / yr, 6 mi
- Sunset, Louisiana: 86 rain days / yr, 7 mi
- Lafayette, Louisiana: 89 rain days / yr, 7 mi
- Lafayette Parish, Louisiana: 90 rain days / yr, 7 mi
- Breaux Bridge, Louisiana: 92 rain days / yr, 8 mi
- Duson, Louisiana: 90 rain days / yr, 10 mi
- Church Point, Louisiana: 90 rain days / yr, 12 mi
- Broussard, Louisiana: 93 rain days / yr, 13 mi
All Louisiana cities and counties
Related guides
- AIA A201 Weather Delay Claims (ยง15.1.6.2): The Three Tests, With Real Numbers
- How Many Weather Days to Put in a Construction Schedule (Normal vs Plan-For)
- How to Document Weather Delays on a Construction Project (Checklist + Daily Log)
Method and source
A rain day is a day with at least 0.10 in (2.54 mm) in PRISM's daily estimate, which covers the 24 hours ending 12:00 UTC. Heavy days use 0.50 in. Normals are 1991-2020 averages. Records run from 1981 to the last complete month. Figures are for the 4 km cell containing the Census point for Carencro (30.312561, -92.038706). Data through 2026-11-24; page updated 2026-11-25. How we count rain days.
Source: PRISM Group, Oregon State University, https://prism.oregonstate.edu. These are gridded estimates, not gauge readings; conditions at a particular site can differ.