Rain days in Baker, Louisiana
Baker averages 85 rain days a year, counting days with at least 0.10 in of precipitation in the PRISM 4 km grid cell that contains it (1991-2020 normals). July is the wettest month at 10.4 rain days and October the driest at 5.0. That is close to the Louisiana median of 85.
Quick answers
How many rain days does Baker get a year?
About 85: that many days in a normal year bring 0.10 in or more of rain or melted snow. That makes Baker the 77th wettest of 156 Louisiana cities and towns.
What is the wettest month in Baker?
July, with 10.4 rain days in a normal year. To cover 9 years in 10, plan for 14.
What is the driest month?
October, with 5.0 rain days (plan for 8).
How many heavy-rain days does Baker get?
40 a year with 0.50 in or more, most often in August (4.0).
Why these counts are lower than some weather sites': a rain day here means 0.10 in or more. Counts based on 0.01 in (NOAA's "days with precipitation") or 0.04 in (WeatherSpark) also include drizzle and trace days.
Rain days by month
The wettest three months are June-August, with 29.4 rain days combined; the driest are September-November, with 16.7. June swings the most from year to year: it averages 10.1 rain days, but covering 9 years in 10 takes 15. The most rain days in a single month since 1981 was 19, in August 2022.
| Month | Normal rain days | Plan for 9 of 10 yrs |
Heavy days ≥ 0.50 in |
Precip (in) | Record (year) |
|---|---|---|---|---|---|
| January | 7.5 | 11 | 3.9 | 6.56 | 11 (2020) |
| February | 6.2 | 9 | 3.0 | 4.85 | 12 (1997) |
| March | 6.2 | 9 | 2.9 | 4.58 | 11 (2001) |
| April | 5.8 | 8 | 2.9 | 5.03 | 12 (2015) |
| May | 6.0 | 9 | 3.3 | 5.62 | 16 (1991) |
| June | 10.1 | 15 | 3.7 | 6.35 | 17 (2017) |
| July | 10.4 | 14 | 3.8 | 5.70 | 17 (2001) |
| August | 8.9 | 12 | 4.0 | 6.64 | 19 (2022) |
| September | 6.3 | 9 | 2.9 | 4.67 | 14 (2018) |
| October | 5.0 | 8 | 2.7 | 4.93 | 13 (2009) |
| November | 5.4 | 9 | 2.9 | 4.15 | 12 (2000) |
| December | 7.0 | 9 | 3.5 | 5.39 | 13 (2009) |
| Year | 84.9 | 39.8 | 64.47 |
Rain day: at least 0.10 in. Plan for: the 90th percentile of 1991-2020 yearly counts, rounded up to a whole day. Record: 1981 to date.
The last 12 months vs normal
From November 2025 through October 2026, Baker had 74 rain days against a normal of 84.8: a dry stretch, 10.8 days below normal. 4 of 12 months came in above normal and 8 below. The biggest departure was May 2026, with 12 rain days against a normal of 6.0. Precipitation totaled 53.47 in against 64.47 in normally.
| Month | Rain days | Normal | Difference | Precip (in) | Normal (in) |
|---|---|---|---|---|---|
| Nov 2025 | 1 | 5.4 | -4.4 | 0.29 | 4.15 |
| Dec 2025 | 9 | 7.0 | +2.0 | 6.35 | 5.39 |
| Jan 2026 | 5 | 7.5 | -2.5 | 5.91 | 6.56 |
| Feb 2026 | 3 | 6.2 | -3.2 | 1.88 | 4.85 |
| Mar 2026 | 5 | 6.2 | -1.2 | 5.58 | 4.58 |
| Apr 2026 | 5 | 5.8 | -0.8 | 3.50 | 5.03 |
| May 2026 | 12 | 6.0 | +6.0 | 9.07 | 5.62 |
| Jun 2026 | 11 | 10.1 | +0.9 | 9.70 | 6.35 |
| Jul 2026 | 7 | 10.4 | -3.4 | 3.99 | 5.70 |
| Aug 2026 | 7 | 8.9 | -1.9 | 3.75 | 6.64 |
| Sep 2026 | 7 | 6.3 | +0.7 | 2.17 | 4.67 |
| Oct 2026 | 2 | 5.0 | -3.0 | 1.28 | 4.93 |
Baker rain days month by month
Against the median Louisiana location, Baker gets more rain days in June and fewer in May and November, by half a day or more; other months are within half a day.
Rain days in January
Baker averages 7.5 rain days in January, 3.9 of them heavy, with 6.56 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 11 (2020). January 2026 had 5, 2.5 below normal.
Rain days in February
Baker averages 6.2 rain days in February, 3.0 of them heavy, with 4.85 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 12 (1997). February 2026 had 3, 3.2 below normal.
Rain days in March
Baker averages 6.2 rain days in March, 2.9 of them heavy, with 4.58 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 11 (2001). March 2026 had 5, 1.2 below normal.
Rain days in April
Baker averages 5.8 rain days in April, 2.9 of them heavy, with 5.03 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 12 (2015). April 2026 had 5, 0.8 below normal.
Rain days in May
Baker averages 6.0 rain days in May, 3.3 of them heavy, with 5.62 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 16 (1991). That is 0.5 fewer than the median Louisiana location (6.5). May 2026 had 12, 6.0 above normal.
Rain days in June
Baker averages 10.1 rain days in June, 3.7 of them heavy, with 6.35 in of precipitation. Plan for 15 to cover 9 years in 10; the record is 17 (2017). That is 0.6 more than the median Louisiana location (9.5). June 2026 had 11, 0.9 above normal.
Rain days in July
Baker averages 10.4 rain days in July, 3.8 of them heavy, with 5.70 in of precipitation. Plan for 14 to cover 9 years in 10; the record is 17 (2001). July 2026 had 7, 3.4 below normal.
Rain days in August
Baker averages 8.9 rain days in August, 4.0 of them heavy, with 6.64 in of precipitation. Plan for 12 to cover 9 years in 10; the record is 19 (2022). August 2026 had 7, 1.9 below normal.
Rain days in September
Baker averages 6.3 rain days in September, 2.9 of them heavy, with 4.67 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 14 (2018). September 2026 had 7, 0.7 above normal.
Rain days in October
Baker averages 5.0 rain days in October, 2.7 of them heavy, with 4.93 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 13 (2009). October 2026 had 2, 3.0 below normal.
Rain days in November
Baker averages 5.4 rain days in November, 2.9 of them heavy, with 4.15 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 12 (2000). That is 0.5 fewer than the median Louisiana location (5.9). November 2025 had 1, 4.4 below normal.
Rain days in December
Baker averages 7.0 rain days in December, 3.5 of them heavy, with 5.39 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 13 (2009). December 2025 had 9, 2.0 above normal.
Using these numbers in a construction schedule
For Baker, the normal column is the expected count: 85 days over a full year, 52 of them from April through October. Put those days in the schedule as non-work days or float before the job starts, not after it slips.
Average or plan-for? An average is exceeded about half the time. If July work has no float, carry 14 weather days for it rather than 10.4: Baker had that many or fewer in 9 of 10 years from 1991 to 2020. Use the normals across a long job and the plan-for figure only for months on the critical path.
Heavy days. Baker averages 40 days a year with 0.50 in or more, most often in August (4.0). Those are the days most likely to stop earthwork, paving and concrete outright.
Claiming time for abnormal weather. Under AIA A201-2017 §15.1.6.2, a claim for extra time because of adverse weather has to show the conditions were abnormal for the period, could not have been reasonably anticipated, and had an adverse effect on the scheduled work. The normals above show what could be anticipated in Baker; the claim also needs the day-by-day record for your site and dates.
Price a rain-day report for a site in Baker. Enter your dates to see actual rain days against this normal for free. The full PDF ($99) adds the daily record, a month-by-month comparison and a method statement you can attach to a schedule update or claim.
Check rain days near BakerNearby
Baker is in East Baton Rouge Parish, which averages 89 rain days a year across the county. Baker gets 4 fewer rain days a year than that county-wide average.
The nearest larger city, Baton Rouge (10 mi away), averages 92 rain days a year: Baker gets 7 fewer.
Closest other areas in Louisiana:
- East Baton Rouge Parish, Louisiana: 89 rain days / yr, 5 mi
- Zachary, Louisiana: 86 rain days / yr, 6 mi
- Central, Louisiana: 86 rain days / yr, 7 mi
- Baton Rouge, Louisiana: 92 rain days / yr, 10 mi
- Port Allen, Louisiana: 85 rain days / yr, 10 mi
- West Baton Rouge Parish, Louisiana: 90 rain days / yr, 12 mi
- Denham Springs, Louisiana: 85 rain days / yr, 14 mi
- Addis, Louisiana: 86 rain days / yr, 16 mi
All Louisiana cities and counties
Related guides
- AIA A201 Weather Delay Claims (ยง15.1.6.2): The Three Tests, With Real Numbers
- How Many Weather Days to Put in a Construction Schedule (Normal vs Plan-For)
- How to Document Weather Delays on a Construction Project (Checklist + Daily Log)
Method and source
A rain day is a day with at least 0.10 in (2.54 mm) in PRISM's daily estimate, which covers the 24 hours ending 12:00 UTC. Heavy days use 0.50 in. Normals are 1991-2020 averages. Records run from 1981 to the last complete month. Figures are for the 4 km cell containing the Census point for Baker (30.583197, -91.158179). Data through 2026-11-24; page updated 2026-11-25. How we count rain days.
Source: PRISM Group, Oregon State University, https://prism.oregonstate.edu. These are gridded estimates, not gauge readings; conditions at a particular site can differ.