Rain days in El Dorado, Kansas
El Dorado averages 59 rain days a year, counting days with at least 0.10 in of precipitation in the PRISM 4 km grid cell that contains it (1991-2020 normals). May is the wettest month at 8.3 rain days and January the driest at 2.3. That is 2 more than the median Kansas location (57).
Quick answers
How many rain days does El Dorado get a year?
About 59: that many days in a normal year bring 0.10 in or more of rain or melted snow. That makes El Dorado the 84th wettest of 189 Kansas cities and towns.
What is the wettest month in El Dorado?
May, with 8.3 rain days in a normal year. To cover 9 years in 10, plan for 13.
What is the driest month?
January, with 2.3 rain days (plan for 4).
How many heavy-rain days does El Dorado get?
24 a year with 0.50 in or more, most often in May (3.8).
Why these counts are lower than some weather sites': a rain day here means 0.10 in or more. Counts based on 0.01 in (NOAA's "days with precipitation") or 0.04 in (WeatherSpark) also include drizzle and trace days.
Rain days by month
The wettest three months are May-July, with 22.2 rain days combined; the driest are November-January, with 8.3. May is also the least predictable month, with the widest gap between its average and its plan-for number. The most rain days in a single month since 1981 was 15, in May 2015.
| Month | Normal rain days | Plan for 9 of 10 yrs |
Heavy days ≥ 0.50 in |
Precip (in) | Record (year) |
|---|---|---|---|---|---|
| January | 2.3 | 4 | 0.5 | 0.87 | 6 (2021) |
| February | 3.1 | 6 | 0.7 | 1.43 | 7 (2008) |
| March | 4.9 | 8 | 1.4 | 2.44 | 11 (1984) |
| April | 5.6 | 9 | 2.4 | 3.32 | 12 (1999) |
| May | 8.3 | 13 | 3.8 | 5.67 | 15 (2015) |
| June | 7.4 | 12 | 3.5 | 5.36 | 13 (1992) |
| July | 6.5 | 11 | 2.7 | 4.29 | 14 (1998) |
| August | 5.9 | 10 | 2.9 | 4.38 | 14 (1989) |
| September | 4.5 | 7 | 2.3 | 3.60 | 8 (2025) |
| October | 5.0 | 8 | 2.3 | 3.23 | 11 (2018) |
| November | 3.1 | 6 | 1.1 | 1.83 | 11 (1992) |
| December | 2.9 | 5 | 0.8 | 1.30 | 9 (1984) |
| Year | 59.4 | 24.5 | 37.71 |
Rain day: at least 0.10 in. Plan for: the 90th percentile of 1991-2020 yearly counts, rounded up to a whole day. Record: 1981 to date.
The last 12 months vs normal
From November 2025 through October 2026, El Dorado had 51 rain days against a normal of 59.5: a dry stretch, 8.5 days below normal. 4 of 12 months came in above normal and 7 below. The biggest departure was June 2026, with 12 rain days against a normal of 7.4. Precipitation totaled 31.52 in against 37.72 in normally.
| Month | Rain days | Normal | Difference | Precip (in) | Normal (in) |
|---|---|---|---|---|---|
| Nov 2025 | 4 | 3.1 | +0.9 | 1.81 | 1.83 |
| Dec 2025 | 0 | 2.9 | -2.9 | 0.01 | 1.30 |
| Jan 2026 | 2 | 2.3 | -0.3 | 1.31 | 0.87 |
| Feb 2026 | 2 | 3.1 | -1.1 | 1.47 | 1.43 |
| Mar 2026 | 4 | 4.9 | -0.9 | 2.46 | 2.44 |
| Apr 2026 | 6 | 5.6 | +0.4 | 2.62 | 3.32 |
| May 2026 | 5 | 8.3 | -3.3 | 2.62 | 5.67 |
| Jun 2026 | 12 | 7.4 | +4.6 | 7.81 | 5.36 |
| Jul 2026 | 4 | 6.5 | -2.5 | 2.58 | 4.29 |
| Aug 2026 | 2 | 5.9 | -3.9 | 1.35 | 4.38 |
| Sep 2026 | 5 | 4.5 | +0.5 | 2.66 | 3.60 |
| Oct 2026 | 5 | 5.0 | +0.0 | 4.82 | 3.23 |
El Dorado rain days month by month
Against the median Kansas location, El Dorado gets more rain days in March, May and June, by half a day or more; other months are within half a day.
Rain days in January
El Dorado averages 2.3 rain days in January, 0.5 of them heavy, with 0.87 in of precipitation. Plan for 4 to cover 9 years in 10; the record is 6 (2021). January 2026 had 2, right on normal.
Rain days in February
El Dorado averages 3.1 rain days in February, 0.7 of them heavy, with 1.43 in of precipitation. Plan for 6 to cover 9 years in 10; the record is 7 (2008). February 2026 had 2, 1.1 below normal.
Rain days in March
El Dorado averages 4.9 rain days in March, 1.4 of them heavy, with 2.44 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 11 (1984). That is 0.5 more than the median Kansas location (4.4). March 2026 had 4, 0.9 below normal.
Rain days in April
El Dorado averages 5.6 rain days in April, 2.4 of them heavy, with 3.32 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 12 (1999). April 2026 had 6, right on normal.
Rain days in May
El Dorado averages 8.3 rain days in May, 3.8 of them heavy, with 5.67 in of precipitation. Plan for 13 to cover 9 years in 10; the record is 15 (2015). That is 0.6 more than the median Kansas location (7.7). May 2026 had 5, 3.3 below normal.
Rain days in June
El Dorado averages 7.4 rain days in June, 3.5 of them heavy, with 5.36 in of precipitation. Plan for 12 to cover 9 years in 10; the record is 13 (1992). That is 0.6 more than the median Kansas location (6.8). June 2026 had 12, 4.6 above normal.
Rain days in July
El Dorado averages 6.5 rain days in July, 2.7 of them heavy, with 4.29 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 14 (1998). July 2026 had 4, 2.5 below normal.
Rain days in August
El Dorado averages 5.9 rain days in August, 2.9 of them heavy, with 4.38 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 14 (1989). August 2026 had 2, 3.9 below normal.
Rain days in September
El Dorado averages 4.5 rain days in September, 2.3 of them heavy, with 3.60 in of precipitation. Plan for 7 to cover 9 years in 10; the record is 8 (2025). September 2026 had 5, 0.5 above normal.
Rain days in October
El Dorado averages 5.0 rain days in October, 2.3 of them heavy, with 3.23 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 11 (2018). October 2026 had 5, right on normal.
Rain days in November
El Dorado averages 3.1 rain days in November, 1.1 of them heavy, with 1.83 in of precipitation. Plan for 6 to cover 9 years in 10; the record is 11 (1992). November 2025 had 4, 0.9 above normal.
Rain days in December
El Dorado averages 2.9 rain days in December, 0.8 of them heavy, with 1.30 in of precipitation. Plan for 5 to cover 9 years in 10; the record is 9 (1984). December 2025 had 0, 2.9 below normal.
Using these numbers in a construction schedule
For El Dorado, the normal column is the expected count: 59 days over a full year, 43 of them from April through October. Put those days in the schedule as non-work days or float before the job starts, not after it slips.
Average or plan-for? An average is exceeded about half the time. If May work has no float, carry 13 weather days for it rather than 8.3: El Dorado had that many or fewer in 9 of 10 years from 1991 to 2020. Use the normals across a long job and the plan-for figure only for months on the critical path.
Heavy days. El Dorado averages 24 days a year with 0.50 in or more, most often in May (3.8). Those are the days most likely to stop earthwork, paving and concrete outright.
Claiming time for abnormal weather. Under AIA A201-2017 §15.1.6.2, a claim for extra time because of adverse weather has to show the conditions were abnormal for the period, could not have been reasonably anticipated, and had an adverse effect on the scheduled work. The normals above show what could be anticipated in El Dorado; the claim also needs the day-by-day record for your site and dates.
Price a rain-day report for a site in El Dorado. Enter your dates to see actual rain days against this normal for free. The full PDF ($99) adds the daily record, a month-by-month comparison and a method statement you can attach to a schedule update or claim.
Check rain days near El DoradoNearby
El Dorado is in Butler County, which averages 61 rain days a year across the county. El Dorado gets 2 fewer rain days a year than that county-wide average.
The nearest larger city, Wichita (28 mi away), averages 59 rain days a year, about the same as El Dorado.
Closest other areas in Kansas:
- Butler County, Kansas: 61 rain days / yr, 3 mi
- Towanda, Kansas: 63 rain days / yr, 7 mi
- Augusta, Kansas: 58 rain days / yr, 10 mi
- Andover, Kansas: 61 rain days / yr, 17 mi
- Bel Aire, Kansas: 59 rain days / yr, 21 mi
- Douglass, Kansas: 64 rain days / yr, 22 mi
- Rose Hill, Kansas: 62 rain days / yr, 23 mi
- Park City, Kansas: 58 rain days / yr, 25 mi
All Kansas cities and counties
Related guides
- AIA A201 Weather Delay Claims (ยง15.1.6.2): The Three Tests, With Real Numbers
- How Many Weather Days to Put in a Construction Schedule (Normal vs Plan-For)
- How to Document Weather Delays on a Construction Project (Checklist + Daily Log)
Method and source
A rain day is a day with at least 0.10 in (2.54 mm) in PRISM's daily estimate, which covers the 24 hours ending 12:00 UTC. Heavy days use 0.50 in. Normals are 1991-2020 averages. Records run from 1981 to the last complete month. Figures are for the 4 km cell containing the Census point for El Dorado (37.820429, -96.862979). Data through 2026-11-24; page updated 2026-11-25. How we count rain days.
Source: PRISM Group, Oregon State University, https://prism.oregonstate.edu. These are gridded estimates, not gauge readings; conditions at a particular site can differ.