Rain days in Sherman, Illinois
Sherman averages 75 rain days a year, counting days with at least 0.10 in of precipitation in the PRISM 4 km grid cell that contains it (1991-2020 normals). May is the wettest month at 8.7 rain days and February the driest at 4.4. That is close to the Illinois median of 75.
Quick answers
How many rain days does Sherman get a year?
About 75: that many days in a normal year bring 0.10 in or more of rain or melted snow. That makes Sherman the 367th wettest of 599 Illinois cities and towns.
What is the wettest month in Sherman?
May, with 8.7 rain days in a normal year. To cover 9 years in 10, plan for 13.
What is the driest month?
February, with 4.4 rain days (plan for 8).
How many heavy-rain days does Sherman get?
25 a year with 0.50 in or more, most often in May (3.1).
Why these counts are lower than some weather sites': a rain day here means 0.10 in or more. Counts based on 0.01 in (NOAA's "days with precipitation") or 0.04 in (WeatherSpark) also include drizzle and trace days.
Rain days by month
The wettest three months are April-June, with 23.7 rain days combined; the driest are December-February, with 14.1. August swings the most from year to year: it averages 6.0 rain days, but covering 9 years in 10 takes 11. The most rain days in a single month since 1981 was 16, in July 1993.
| Month | Normal rain days | Plan for 9 of 10 yrs |
Heavy days ≥ 0.50 in |
Precip (in) | Record (year) |
|---|---|---|---|---|---|
| January | 4.8 | 7 | 1.1 | 2.12 | 9 (2024) |
| February | 4.4 | 8 | 1.3 | 2.01 | 10 (2008) |
| March | 6.3 | 8 | 1.7 | 2.79 | 11 (1984) |
| April | 7.6 | 10 | 3.0 | 4.12 | 12 (1995) |
| May | 8.7 | 13 | 3.1 | 4.53 | 14 (1996) |
| June | 7.4 | 11 | 3.0 | 4.64 | 14 (2015) |
| July | 7.0 | 10 | 2.3 | 4.00 | 16 (1993) |
| August | 6.0 | 11 | 1.9 | 3.36 | 11 (2016) |
| September | 5.3 | 8 | 1.9 | 3.16 | 15 (1993) |
| October | 6.2 | 9 | 2.2 | 3.30 | 13 (2009) |
| November | 6.1 | 9 | 1.9 | 2.94 | 16 (1992) |
| December | 4.9 | 8 | 1.4 | 2.21 | 11 (2007) |
| Year | 74.7 | 24.9 | 39.20 |
Rain day: at least 0.10 in. Plan for: the 90th percentile of 1991-2020 yearly counts, rounded up to a whole day. Record: 1981 to date.
The last 12 months vs normal
From November 2025 through October 2026, Sherman had 68 rain days against a normal of 74.7: a dry stretch, 6.7 days below normal. 4 of 12 months came in above normal and 7 below. The biggest departure was October 2026, with 3 rain days against a normal of 6.2. Precipitation totaled 42.20 in against 39.18 in normally.
| Month | Rain days | Normal | Difference | Precip (in) | Normal (in) |
|---|---|---|---|---|---|
| Nov 2025 | 7 | 6.1 | +0.9 | 2.25 | 2.94 |
| Dec 2025 | 4 | 4.9 | -0.9 | 1.34 | 2.21 |
| Jan 2026 | 4 | 4.8 | -0.8 | 0.83 | 2.12 |
| Feb 2026 | 2 | 4.4 | -2.4 | 0.54 | 2.01 |
| Mar 2026 | 8 | 6.3 | +1.7 | 6.81 | 2.79 |
| Apr 2026 | 8 | 7.6 | +0.4 | 6.80 | 4.12 |
| May 2026 | 7 | 8.7 | -1.7 | 2.79 | 4.53 |
| Jun 2026 | 7 | 7.4 | -0.4 | 8.16 | 4.64 |
| Jul 2026 | 7 | 7.0 | +0.0 | 4.24 | 4.00 |
| Aug 2026 | 7 | 6.0 | +1.0 | 4.63 | 3.36 |
| Sep 2026 | 4 | 5.3 | -1.3 | 2.20 | 3.16 |
| Oct 2026 | 3 | 6.2 | -3.2 | 1.61 | 3.30 |
Sherman rain days month by month
Every month in Sherman is within half a rain day of the median Illinois location.
Rain days in January
Sherman averages 4.8 rain days in January, 1.1 of them heavy, with 2.12 in of precipitation. Plan for 7 to cover 9 years in 10; the record is 9 (2024). January 2026 had 4, 0.8 below normal.
Rain days in February
Sherman averages 4.4 rain days in February, 1.3 of them heavy, with 2.01 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 10 (2008). February 2026 had 2, 2.4 below normal.
Rain days in March
Sherman averages 6.3 rain days in March, 1.7 of them heavy, with 2.79 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 11 (1984). March 2026 had 8, 1.7 above normal.
Rain days in April
Sherman averages 7.6 rain days in April, 3.0 of them heavy, with 4.12 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 12 (1995). April 2026 had 8, right on normal.
Rain days in May
Sherman averages 8.7 rain days in May, 3.1 of them heavy, with 4.53 in of precipitation. Plan for 13 to cover 9 years in 10; the record is 14 (1996). May 2026 had 7, 1.7 below normal.
Rain days in June
Sherman averages 7.4 rain days in June, 3.0 of them heavy, with 4.64 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 14 (2015). June 2026 had 7, right on normal.
Rain days in July
Sherman averages 7.0 rain days in July, 2.3 of them heavy, with 4.00 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 16 (1993). July 2026 had 7, right on normal.
Rain days in August
Sherman averages 6.0 rain days in August, 1.9 of them heavy, with 3.36 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 11 (2016). August 2026 had 7, 1.0 above normal.
Rain days in September
Sherman averages 5.3 rain days in September, 1.9 of them heavy, with 3.16 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 15 (1993). September 2026 had 4, 1.3 below normal.
Rain days in October
Sherman averages 6.2 rain days in October, 2.2 of them heavy, with 3.30 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 13 (2009). October 2026 had 3, 3.2 below normal.
Rain days in November
Sherman averages 6.1 rain days in November, 1.9 of them heavy, with 2.94 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 16 (1992). November 2025 had 7, 0.9 above normal.
Rain days in December
Sherman averages 4.9 rain days in December, 1.4 of them heavy, with 2.21 in of precipitation. Plan for 8 to cover 9 years in 10; the record is 11 (2007). December 2025 had 4, 0.9 below normal.
Using these numbers in a construction schedule
For Sherman, the normal column is the expected count: 75 days over a full year, 48 of them from April through October. Put those days in the schedule as non-work days or float before the job starts, not after it slips.
Average or plan-for? An average is exceeded about half the time. If May work has no float, carry 13 weather days for it rather than 8.7: Sherman had that many or fewer in 9 of 10 years from 1991 to 2020. Use the normals across a long job and the plan-for figure only for months on the critical path.
Heavy days. Sherman averages 25 days a year with 0.50 in or more, most often in May (3.1). Those are the days most likely to stop earthwork, paving and concrete outright.
Claiming time for abnormal weather. Under AIA A201-2017 §15.1.6.2, a claim for extra time because of adverse weather has to show the conditions were abnormal for the period, could not have been reasonably anticipated, and had an adverse effect on the scheduled work. The normals above show what could be anticipated in Sherman; the claim also needs the day-by-day record for your site and dates.
Price a rain-day report for a site in Sherman. Enter your dates to see actual rain days against this normal for free. The full PDF ($99) adds the daily record, a month-by-month comparison and a method statement you can attach to a schedule update or claim.
Check rain days near ShermanNearby
Sherman is in Sangamon County, which averages 74 rain days a year across the county. The two numbers are close but measure different things: the county figure averages all 139 of the county's grid cells, while Sherman's is the single 4 km cell at its Census point. A site elsewhere in Sangamon County can differ from both.
The nearest larger city, Springfield (7 mi away), averages 75 rain days a year, about the same as Sherman.
Closest other areas in Illinois:
- Riverton, Illinois: 74 rain days / yr, 5 mi
- Grandview, Illinois: 75 rain days / yr, 5 mi
- Williamsville, Illinois: 75 rain days / yr, 6 mi
- Springfield, Illinois: 75 rain days / yr, 7 mi
- Athens, Illinois: 74 rain days / yr, 8 mi
- Leland Grove, Illinois: 75 rain days / yr, 8 mi
- Jerome, Illinois: 75 rain days / yr, 9 mi
- Sangamon County, Illinois: 74 rain days / yr, 9 mi
All Illinois cities and counties
Related guides
- AIA A201 Weather Delay Claims (ยง15.1.6.2): The Three Tests, With Real Numbers
- How Many Weather Days to Put in a Construction Schedule (Normal vs Plan-For)
- How to Document Weather Delays on a Construction Project (Checklist + Daily Log)
Method and source
A rain day is a day with at least 0.10 in (2.54 mm) in PRISM's daily estimate, which covers the 24 hours ending 12:00 UTC. Heavy days use 0.50 in. Normals are 1991-2020 averages. Records run from 1981 to the last complete month. Figures are for the 4 km cell containing the Census point for Sherman (39.885142, -89.606904). Data through 2026-11-24; page updated 2026-11-25. How we count rain days.
Source: PRISM Group, Oregon State University, https://prism.oregonstate.edu. These are gridded estimates, not gauge readings; conditions at a particular site can differ.