Rain days in Oviedo, Florida
Oviedo averages 101 rain days a year, counting days with at least 0.10 in of precipitation in the PRISM 4 km grid cell that contains it (1991-2020 normals). August is the wettest month at 15.8 rain days and November the driest at 3.6. That is 9 more than the median Florida location (93).
Quick answers
How many rain days does Oviedo get a year?
About 101: that many days in a normal year bring 0.10 in or more of rain or melted snow. That makes Oviedo the 100th wettest of 309 Florida cities and towns.
What is the wettest month in Oviedo?
August, with 15.8 rain days in a normal year. To cover 9 years in 10, plan for 21.
What is the driest month?
November, with 3.6 rain days (plan for 6).
How many heavy-rain days does Oviedo get?
35 a year with 0.50 in or more, most often in June (5.8).
Why these counts are lower than some weather sites': a rain day here means 0.10 in or more. Counts based on 0.01 in (NOAA's "days with precipitation") or 0.04 in (WeatherSpark) also include drizzle and trace days.
Rain days by month
The wettest three months are June-August, with 46.2 rain days combined; the driest are November-January, with 12.7. July swings the most from year to year: it averages 15.1 rain days, but covering 9 years in 10 takes 21. The most rain days in a single month since 1981 was 24, in July 1997.
| Month | Normal rain days | Plan for 9 of 10 yrs |
Heavy days ≥ 0.50 in |
Precip (in) | Record (year) |
|---|---|---|---|---|---|
| January | 5.1 | 7 | 1.7 | 2.60 | 14 (1993) |
| February | 4.5 | 7 | 1.5 | 2.24 | 11 (1998) |
| March | 5.7 | 11 | 2.0 | 3.20 | 16 (2003) |
| April | 5.2 | 9 | 1.6 | 2.65 | 14 (1991) |
| May | 7.3 | 11 | 2.6 | 3.83 | 15 (2018) |
| June | 15.3 | 21 | 5.8 | 8.26 | 23 (2005) |
| July | 15.1 | 21 | 5.2 | 8.01 | 24 (1997) |
| August | 15.8 | 21 | 5.2 | 8.26 | 23 (1985) |
| September | 12.3 | 17 | 4.2 | 6.70 | 21 (2001) |
| October | 7.3 | 11 | 2.4 | 4.07 | 16 (1983) |
| November | 3.6 | 6 | 1.1 | 2.06 | 12 (1987) |
| December | 4.0 | 6 | 1.6 | 2.39 | 13 (1997) |
| Year | 101.1 | 35.0 | 54.27 |
Rain day: at least 0.10 in. Plan for: the 90th percentile of 1991-2020 yearly counts, rounded up to a whole day. Record: 1981 to date.
The last 12 months vs normal
From November 2025 through October 2026, Oviedo had 91 rain days against a normal of 101.2: a dry stretch, 10.2 days below normal. 3 of 12 months came in above normal and 9 below. The biggest departure was October 2026, with 11 rain days against a normal of 7.3. Precipitation totaled 48.53 in against 54.27 in normally.
| Month | Rain days | Normal | Difference | Precip (in) | Normal (in) |
|---|---|---|---|---|---|
| Nov 2025 | 1 | 3.6 | -2.6 | 0.61 | 2.06 |
| Dec 2025 | 2 | 4.0 | -2.0 | 2.70 | 2.39 |
| Jan 2026 | 3 | 5.1 | -2.1 | 0.88 | 2.60 |
| Feb 2026 | 2 | 4.5 | -2.5 | 1.42 | 2.24 |
| Mar 2026 | 4 | 5.7 | -1.7 | 1.44 | 3.20 |
| Apr 2026 | 6 | 5.2 | +0.8 | 1.72 | 2.65 |
| May 2026 | 9 | 7.3 | +1.7 | 5.44 | 3.83 |
| Jun 2026 | 14 | 15.3 | -1.3 | 4.16 | 8.26 |
| Jul 2026 | 14 | 15.1 | -1.1 | 9.74 | 8.01 |
| Aug 2026 | 13 | 15.8 | -2.8 | 7.46 | 8.26 |
| Sep 2026 | 12 | 12.3 | -0.3 | 6.46 | 6.70 |
| Oct 2026 | 11 | 7.3 | +3.7 | 6.50 | 4.07 |
Oviedo rain days month by month
Against the median Florida location, Oviedo gets more rain days in March, May, June, July, August, September and October, by half a day or more; other months are within half a day.
Rain days in January
Oviedo averages 5.1 rain days in January, 1.7 of them heavy, with 2.60 in of precipitation. Plan for 7 to cover 9 years in 10; the record is 14 (1993). January 2026 had 3, 2.1 below normal.
Rain days in February
Oviedo averages 4.5 rain days in February, 1.5 of them heavy, with 2.24 in of precipitation. Plan for 7 to cover 9 years in 10; the record is 11 (1998). February 2026 had 2, 2.5 below normal.
Rain days in March
Oviedo averages 5.7 rain days in March, 2.0 of them heavy, with 3.20 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 16 (2003). That is 0.6 more than the median Florida location (5.1). March 2026 had 4, 1.7 below normal.
Rain days in April
Oviedo averages 5.2 rain days in April, 1.6 of them heavy, with 2.65 in of precipitation. Plan for 9 to cover 9 years in 10; the record is 14 (1991). April 2026 had 6, 0.8 above normal.
Rain days in May
Oviedo averages 7.3 rain days in May, 2.6 of them heavy, with 3.83 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 15 (2018). That is 1.2 more than the median Florida location (6.1). May 2026 had 9, 1.7 above normal.
Rain days in June
Oviedo averages 15.3 rain days in June, 5.8 of them heavy, with 8.26 in of precipitation. Plan for 21 to cover 9 years in 10; the record is 23 (2005). That is 2.3 more than the median Florida location (13.0). June 2026 had 14, 1.3 below normal.
Rain days in July
Oviedo averages 15.1 rain days in July, 5.2 of them heavy, with 8.01 in of precipitation. Plan for 21 to cover 9 years in 10; the record is 24 (1997). That is 1.0 more than the median Florida location (14.1). July 2026 had 14, 1.1 below normal.
Rain days in August
Oviedo averages 15.8 rain days in August, 5.2 of them heavy, with 8.26 in of precipitation. Plan for 21 to cover 9 years in 10; the record is 23 (1985). That is 1.2 more than the median Florida location (14.6). August 2026 had 13, 2.8 below normal.
Rain days in September
Oviedo averages 12.3 rain days in September, 4.2 of them heavy, with 6.70 in of precipitation. Plan for 17 to cover 9 years in 10; the record is 21 (2001). That is 1.0 more than the median Florida location (11.3). September 2026 had 12, right on normal.
Rain days in October
Oviedo averages 7.3 rain days in October, 2.4 of them heavy, with 4.07 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 16 (1983). That is 1.2 more than the median Florida location (6.1). October 2026 had 11, 3.7 above normal.
Rain days in November
Oviedo averages 3.6 rain days in November, 1.1 of them heavy, with 2.06 in of precipitation. Plan for 6 to cover 9 years in 10; the record is 12 (1987). November 2025 had 1, 2.6 below normal.
Rain days in December
Oviedo averages 4.0 rain days in December, 1.6 of them heavy, with 2.39 in of precipitation. Plan for 6 to cover 9 years in 10; the record is 13 (1997). December 2025 had 2, 2.0 below normal.
Using these numbers in a construction schedule
For Oviedo, the normal column is the expected count: 101 days over a full year, 78 of them from April through October. Put those days in the schedule as non-work days or float before the job starts, not after it slips.
Average or plan-for? An average is exceeded about half the time. If August work has no float, carry 21 weather days for it rather than 15.8: Oviedo had that many or fewer in 9 of 10 years from 1991 to 2020. Use the normals across a long job and the plan-for figure only for months on the critical path.
Heavy days. Oviedo averages 35 days a year with 0.50 in or more, most often in June (5.8). Those are the days most likely to stop earthwork, paving and concrete outright.
Claiming time for abnormal weather. Under AIA A201-2017 §15.1.6.2, a claim for extra time because of adverse weather has to show the conditions were abnormal for the period, could not have been reasonably anticipated, and had an adverse effect on the scheduled work. The normals above show what could be anticipated in Oviedo; the claim also needs the day-by-day record for your site and dates.
Price a rain-day report for a site in Oviedo. Enter your dates to see actual rain days against this normal for free. The full PDF ($99) adds the daily record, a month-by-month comparison and a method statement you can attach to a schedule update or claim.
Check rain days near OviedoNearby
Oviedo is in Seminole County, which averages 97 rain days a year across the county. Oviedo gets 4 more rain days a year than that county-wide average.
The nearest larger city, Orlando (15 mi away), averages 95 rain days a year: Oviedo gets 6 more.
Closest other areas in Florida:
- Seminole County, Florida: 97 rain days / yr, 4 mi
- Winter Springs, Florida: 96 rain days / yr, 6 mi
- Casselberry, Florida: 104 rain days / yr, 8 mi
- Sanford, Florida: 86 rain days / yr, 10 mi
- Longwood, Florida: 98 rain days / yr, 10 mi
- Winter Park, Florida: 106 rain days / yr, 11 mi
- Lake Mary, Florida: 92 rain days / yr, 11 mi
- Maitland, Florida: 106 rain days / yr, 11 mi
All Florida cities and counties
Related guides
- AIA A201 Weather Delay Claims (ยง15.1.6.2): The Three Tests, With Real Numbers
- How Many Weather Days to Put in a Construction Schedule (Normal vs Plan-For)
- How to Document Weather Delays on a Construction Project (Checklist + Daily Log)
Method and source
A rain day is a day with at least 0.10 in (2.54 mm) in PRISM's daily estimate, which covers the 24 hours ending 12:00 UTC. Heavy days use 0.50 in. Normals are 1991-2020 averages. Records run from 1981 to the last complete month. Figures are for the 4 km cell containing the Census point for Oviedo (28.66193, -81.187101). Data through 2026-11-24; page updated 2026-11-25. How we count rain days.
Source: PRISM Group, Oregon State University, https://prism.oregonstate.edu. These are gridded estimates, not gauge readings; conditions at a particular site can differ.