Rain days in Vance, Alabama
Vance averages 89 rain days a year, counting days with at least 0.10 in of precipitation in the PRISM 4 km grid cell that contains it (1991-2020 normals). July is the wettest month at 9.2 rain days and October the driest at 4.9. That is 2 more than the median Alabama location (87).
Quick answers
How many rain days does Vance get a year?
About 89: that many days in a normal year bring 0.10 in or more of rain or melted snow. That makes Vance the 78th wettest of 257 Alabama cities and towns.
What is the wettest month in Vance?
July, with 9.2 rain days in a normal year. To cover 9 years in 10, plan for 14.
What is the driest month?
October, with 4.9 rain days (plan for 10).
How many heavy-rain days does Vance get?
38 a year with 0.50 in or more, most often in February (4.3).
Why these counts are lower than some weather sites': a rain day here means 0.10 in or more. Counts based on 0.01 in (NOAA's "days with precipitation") or 0.04 in (WeatherSpark) also include drizzle and trace days.
Rain days by month
The wettest three months are June-August, with 26.0 rain days combined; the driest are September-November, with 17.1. June swings the most from year to year: it averages 8.5 rain days, but covering 9 years in 10 takes 14. The most rain days in a single month since 1981 was 20, in May 2025.
| Month | Normal rain days | Plan for 9 of 10 yrs |
Heavy days ≥ 0.50 in |
Precip (in) | Record (year) |
|---|---|---|---|---|---|
| January | 8.3 | 13 | 4.0 | 5.56 | 14 (1998) |
| February | 8.2 | 12 | 4.3 | 5.80 | 13 (2020) |
| March | 7.8 | 11 | 3.5 | 5.41 | 13 (2020) |
| April | 7.2 | 10 | 3.5 | 5.25 | 13 (2015) |
| May | 6.5 | 10 | 2.6 | 4.03 | 20 (2025) |
| June | 8.5 | 14 | 3.2 | 4.45 | 18 (1997) |
| July | 9.2 | 14 | 2.6 | 4.56 | 18 (2021) |
| August | 8.3 | 12 | 2.8 | 4.14 | 13 (2012) |
| September | 5.7 | 10 | 2.2 | 4.23 | 14 (2009) |
| October | 4.9 | 10 | 2.4 | 3.43 | 12 (1994) |
| November | 6.5 | 11 | 3.3 | 4.78 | 14 (1986) |
| December | 8.2 | 11 | 3.5 | 5.18 | 13 (1997) |
| Year | 89.3 | 37.8 | 56.82 |
Rain day: at least 0.10 in. Plan for: the 90th percentile of 1991-2020 yearly counts, rounded up to a whole day. Record: 1981 to date.
The last 12 months vs normal
From November 2025 through October 2026, Vance had 74 rain days against a normal of 89.3: a dry stretch, 15.3 days below normal. 2 of 12 months came in above normal and 10 below. The biggest departure was May 2026, with 11 rain days against a normal of 6.5. Precipitation totaled 49.11 in against 56.82 in normally.
| Month | Rain days | Normal | Difference | Precip (in) | Normal (in) |
|---|---|---|---|---|---|
| Nov 2025 | 4 | 6.5 | -2.5 | 4.70 | 4.78 |
| Dec 2025 | 5 | 8.2 | -3.2 | 1.57 | 5.18 |
| Jan 2026 | 8 | 8.3 | -0.3 | 7.91 | 5.56 |
| Feb 2026 | 6 | 8.2 | -2.2 | 2.45 | 5.80 |
| Mar 2026 | 4 | 7.8 | -3.8 | 4.53 | 5.41 |
| Apr 2026 | 5 | 7.2 | -2.2 | 4.17 | 5.25 |
| May 2026 | 11 | 6.5 | +4.5 | 4.99 | 4.03 |
| Jun 2026 | 11 | 8.5 | +2.5 | 6.65 | 4.45 |
| Jul 2026 | 9 | 9.2 | -0.2 | 3.88 | 4.56 |
| Aug 2026 | 5 | 8.3 | -3.3 | 2.79 | 4.14 |
| Sep 2026 | 3 | 5.7 | -2.7 | 2.12 | 4.23 |
| Oct 2026 | 3 | 4.9 | -1.9 | 3.35 | 3.43 |
Vance rain days month by month
Against the median Alabama location, Vance gets more rain days in January, February and November and fewer in May, by half a day or more; other months are within half a day.
Rain days in January
Vance averages 8.3 rain days in January, 4.0 of them heavy, with 5.56 in of precipitation. Plan for 13 to cover 9 years in 10; the record is 14 (1998). That is 0.6 more than the median Alabama location (7.7). January 2026 had 8, right on normal.
Rain days in February
Vance averages 8.2 rain days in February, 4.3 of them heavy, with 5.80 in of precipitation. Plan for 12 to cover 9 years in 10; the record is 13 (2020). That is 0.9 more than the median Alabama location (7.3). February 2026 had 6, 2.2 below normal.
Rain days in March
Vance averages 7.8 rain days in March, 3.5 of them heavy, with 5.41 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 13 (2020). March 2026 had 4, 3.8 below normal.
Rain days in April
Vance averages 7.2 rain days in April, 3.5 of them heavy, with 5.25 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 13 (2015). April 2026 had 5, 2.2 below normal.
Rain days in May
Vance averages 6.5 rain days in May, 2.6 of them heavy, with 4.03 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 20 (2025). That is 0.5 fewer than the median Alabama location (7.0). May 2026 had 11, 4.5 above normal.
Rain days in June
Vance averages 8.5 rain days in June, 3.2 of them heavy, with 4.45 in of precipitation. Plan for 14 to cover 9 years in 10; the record is 18 (1997). June 2026 had 11, 2.5 above normal.
Rain days in July
Vance averages 9.2 rain days in July, 2.6 of them heavy, with 4.56 in of precipitation. Plan for 14 to cover 9 years in 10; the record is 18 (2021). July 2026 had 9, right on normal.
Rain days in August
Vance averages 8.3 rain days in August, 2.8 of them heavy, with 4.14 in of precipitation. Plan for 12 to cover 9 years in 10; the record is 13 (2012). August 2026 had 5, 3.3 below normal.
Rain days in September
Vance averages 5.7 rain days in September, 2.2 of them heavy, with 4.23 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 14 (2009). September 2026 had 3, 2.7 below normal.
Rain days in October
Vance averages 4.9 rain days in October, 2.4 of them heavy, with 3.43 in of precipitation. Plan for 10 to cover 9 years in 10; the record is 12 (1994). October 2026 had 3, 1.9 below normal.
Rain days in November
Vance averages 6.5 rain days in November, 3.3 of them heavy, with 4.78 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 14 (1986). That is 0.5 more than the median Alabama location (6.0). November 2025 had 4, 2.5 below normal.
Rain days in December
Vance averages 8.2 rain days in December, 3.5 of them heavy, with 5.18 in of precipitation. Plan for 11 to cover 9 years in 10; the record is 13 (1997). December 2025 had 5, 3.2 below normal.
Using these numbers in a construction schedule
For Vance, the normal column is the expected count: 89 days over a full year, 50 of them from April through October. Put those days in the schedule as non-work days or float before the job starts, not after it slips.
Average or plan-for? An average is exceeded about half the time. If July work has no float, carry 14 weather days for it rather than 9.2: Vance had that many or fewer in 9 of 10 years from 1991 to 2020. Use the normals across a long job and the plan-for figure only for months on the critical path.
Heavy days. Vance averages 38 days a year with 0.50 in or more, most often in February (4.3). Those are the days most likely to stop earthwork, paving and concrete outright.
Claiming time for abnormal weather. Under AIA A201-2017 §15.1.6.2, a claim for extra time because of adverse weather has to show the conditions were abnormal for the period, could not have been reasonably anticipated, and had an adverse effect on the scheduled work. The normals above show what could be anticipated in Vance; the claim also needs the day-by-day record for your site and dates.
Price a rain-day report for a site in Vance. Enter your dates to see actual rain days against this normal for free. The full PDF ($99) adds the daily record, a month-by-month comparison and a method statement you can attach to a schedule update or claim.
Check rain days near VanceNearby
Vance is in Tuscaloosa County, which averages 88 rain days a year across the county. Vance gets 1 more rain days a year than that county-wide average.
The nearest larger city, Tuscaloosa (18 mi away), averages 86 rain days a year: Vance gets 4 more.
Closest other areas in Alabama:
- Woodstock, Alabama: 90 rain days / yr, 5 mi
- West Blocton, Alabama: 80 rain days / yr, 7 mi
- Coaling, Alabama: 90 rain days / yr, 7 mi
- Brookwood, Alabama: 84 rain days / yr, 8 mi
- Lake View, Alabama: 90 rain days / yr, 9 mi
- Bibb County, Alabama: 86 rain days / yr, 12 mi
- Centreville, Alabama: 85 rain days / yr, 16 mi
- Brent, Alabama: 86 rain days / yr, 16 mi
All Alabama cities and counties
Related guides
- AIA A201 Weather Delay Claims (ยง15.1.6.2): The Three Tests, With Real Numbers
- How Many Weather Days to Put in a Construction Schedule (Normal vs Plan-For)
- How to Document Weather Delays on a Construction Project (Checklist + Daily Log)
Method and source
A rain day is a day with at least 0.10 in (2.54 mm) in PRISM's daily estimate, which covers the 24 hours ending 12:00 UTC. Heavy days use 0.50 in. Normals are 1991-2020 averages. Records run from 1981 to the last complete month. Figures are for the 4 km cell containing the Census point for Vance (33.173616, -87.226258). Data through 2026-11-24; page updated 2026-11-25. How we count rain days.
Source: PRISM Group, Oregon State University, https://prism.oregonstate.edu. These are gridded estimates, not gauge readings; conditions at a particular site can differ.