What Counts as 'Abnormal' or 'Unusually Severe' Weather? AIA A201, ConsensusDocs 200 and FAR Compared

The main US construction contract forms excuse weather beyond what a contractor should have planned for. None of them says how much rain that takes. That gets settled later, often in a dispute, and the baseline each side uses drives the answer.

This guide puts the AIA, ConsensusDocs and federal language side by side, then sets out a percentile test built on 30-year normals. All rain-day figures are PRISM 1991-2020 normals for the 4 km cell containing each city, with data through 2026-11-24. A rain day is a day with at least 0.10 inch. This is not legal advice; check your contract and any supplementary conditions.

Three contracts, one idea

AIA A201-2017, §15.1.6.2. A claim for time based on weather must be documented by data showing the conditions were "abnormal for the period of time" and "could not have been reasonably anticipated" (AIA A201-2017), and that they had an adverse effect on the scheduled construction. Our A201 weather delay guide walks through each test.

ConsensusDocs 200. The delay article lists "adverse weather conditions not reasonably anticipated" (ConsensusDocs 200, §6.3.1 in recent editions) among the causes beyond the Constructor's control (ConsensusDocs' term for the contractor) that support an equitable extension of the Contract Time.

FAR 52.249-10, Default (Fixed-Price Construction). On federal jobs, the contractor's right to proceed is not terminated, and it is not charged damages, for delay from unforeseeable causes beyond its control and without its fault or negligence. The clause's list of examples includes "unusually severe weather." The contractor must notify the contracting officer in writing within 10 days from the beginning of the delay, unless the contracting officer extends that time (52.249-10(b)(2)).

Contract Standard What it asks for Notice
AIA A201-2017 Abnormal for the period, not reasonably anticipated Data on the weather plus adverse effect on the schedule 21 days (§15.1.3.1)
ConsensusDocs 200 Not reasonably anticipated A cause beyond the contractor's control that delayed the work See the notice terms in your edition
FAR 52.249-10 Unusually severe Unforeseeable, beyond control, without fault, and it caused delay 10 days to the contracting officer
USACE weather table Days beyond the monthly table Logged delay days on critical work, compared to the table Per the contract provision

All three come down to the same question: was this weather worse than a careful bidder would have expected at this place, at this time of year?

Federal jobs: the anticipated weather table

The US Army Corps of Engineers removes some of the guesswork. Many USACE construction contracts include a provision titled Time Extensions for Unusually Severe Weather, usually in the special contract requirements; where it sits varies by district and solicitation. It contains a table of anticipated adverse weather delay days for each month, stated on a five-day work week and based on NOAA or similar data for the project location. The USACE regulation behind the practice is ER 415-1-15, Construction Time Extensions for Weather.

The typical wording works like this:

Under this provision the claim becomes a count: lost workdays on the critical path against the table. The table still has to be realistic, and site data is how you test it. Our schedule guide explains how to build a monthly table for private jobs that want the same structure.

Government delay complicates this. If a suspension or late change pushes work into a wetter season, the extra weather time is often argued as part of the suspension or change claim rather than against the table. Boards of contract appeals have decided disputes of this kind, and results turn on clause wording and facts, so have counsel check decisions on point.

Choosing the baseline

If the contract does not fix the expected weather, the baseline is the first thing each side will attack. The usual candidates:

Wet years cluster, which is why the window matters. Across the 100 largest US cities, we looked at which year holds the most rain days for each calendar month since 1981. Of those 1,200 city-month records, 2015 holds 61, 1998 holds 58 and 2018 holds 55. Forty-six different years appear, but three of them account for about one record in seven. Thirteen of the 58 records from 1998 are California Februaries, during the strong 1997-98 El Nino.

A 10-year window from 2011 to 2020 contains both 2015 and 2018. A window from 2016 to 2025 contains only 2018. In some cities that choice alone can change whether a month looks abnormal. A 30-year baseline still includes those years, but it dilutes them. The methodology page explains how the PRISM grid gives every address a 1991-2020 normal, including rural sites with no station nearby.

A defensible line: the 90th percentile

The normal is an average, and plenty of months beat it. Beating it by a day or two says little about whether weather was abnormal.

A stronger line is the 90th percentile of the 30 monthly counts, which our city pages call the plan-for figure. We use the nearest-rank method, so a month above the plan-for count had more rain days than at least 27 of the 30 years from 1991 to 2020. Any arbitrator or contracting officer can follow that.

Over the last 12 complete months (November 2025 through October 2026), in the 100 largest US cities:

City and month Rain days Normal Plan-for (p90) Most since 1981
Houston, TX, Apr 2026 8 4.8 8 10 (1997)
Corpus Christi, TX, Jun 2026 9 4.8 9 14 (1981)
Dallas, TX, Apr 2026 10 5.4 9 11 (1995)
Atlanta, GA, Jul 2026 17 10.0 13 23 (1994)
Raleigh, NC, Jul 2026 15 8.7 12 15 (2026)
El Paso, TX, Sep 2026 13 4.0 8 13 (2026)

Houston in April 2026 had two thirds more rain days than normal, yet it landed exactly on the plan-for count. Corpus Christi in June nearly doubled its normal and also landed on it. Both sound like claims and both will draw a "reasonably anticipated" defense. Dallas in April cleared the plan-for by one day. Atlanta cleared it by four without approaching its 1994 record.

Raleigh and El Paso are the clearest cases: no July in Raleigh and no September in El Paso since 1981 had more rain days. The record column includes 2026 and credits ties to the most recent year, so these months either set the record or equaled it.

Severity is necessary, not sufficient

Proving the weather was unusual proves nothing about delay. A201 §15.1.6.2 requires an adverse effect on the scheduled construction, FAR 52.249-10 requires that the cause actually delayed the work, and the USACE provision counts only days that stopped critical activities.

So pair the weather data with project records: the schedule showing the affected activities were critical, daily logs showing crews stood down and why, and dry-out days after heavy rain. Our checklist for documenting weather delays covers the daily log. Rain on a non-working day, or while only interior work was underway, rarely supports a claim.

Decision table: where a month usually stands

Month at the site Likely position
At or below the normal Weak. The weather was within the average for that month.
Above the normal, at or below the plan-for Contested. Within the range of about 9 years in 10; expect a reasonably-anticipated defense.
Above the plan-for Strong on severity. Causation still has to be shown.
Tied or set the most rain days since 1981 Strongest available evidence of abnormal weather.
Federal job with a weather table Count lost workdays on critical work against the table; use percentiles as a check on the table.

For a delay spanning several months, check whether your contract lets the owner offset dry months against wet ones, and run the table month by month.

Frequently asked questions

What is unusually severe weather in construction?

Weather more severe than the contractor could reasonably have expected at that location for that time of year. The phrase comes from federal clauses such as FAR 52.249-10; A201 and ConsensusDocs 200 use similar ideas in different words. None sets a number, so the comparison is made against historical data for the site.

Is above-average rain enough for a weather delay claim?

Usually not on its own. In the 100 largest US cities, about a third of city-months over the last 12 months came in above normal (393 of 1,200). A month above the 90th percentile of the 30-year record, meaning more rain days than at least 27 of the 30 years from 1991 to 2020, is a much stronger showing. You still need to prove the weather delayed critical work.

Which baseline should a weather delay claim use?

If your contract names one, use it. Otherwise the 1991-2020 normal, the current official US climate normals period, is hard to attack as cherry-picked. Short windows of 5 or 10 years can swing with whether a very wet year such as 2015 or 2018 falls inside them.

Do ConsensusDocs 200 and A201 treat weather the same way?

The idea is similar: both excuse weather that was not reasonably anticipated. A201-2017 adds an explicit documentation standard in §15.1.6.2 and a 21-day claim notice in §15.1.3.1. Read the delay and notice provisions in your edition and any amendments. This is not legal advice.

Get the numbers for your site

The free lookup on the home page shows rain days at any US address for a chosen period next to the normal and plan-for count. For a claim file, the $99 Rain-Day Report gives the daily record and the month-by-month comparison as a PDF. See a sample report first.